Ala. Admin. Code r. 400-5-6-.02

Current through Register Vol. 43, No. 1, October 31, 2024
Section 400-5-6-.02 - Casing Requirements For Converted Wells

All newly converted wells shall comply with the following requirements:

(1) Casing and cement specifications are to be in accordance with Rule 400-1-4-.09 or 400-2-4-.09, whichever is applicable.
(2) The top of cement and the degree of bonding of the cement used to anchor the production casing shall be verified by cement bond log, cement evaluation log or other logs approved by the Supervisor.
(3) Injection shall not result in the movement of fluids into an underground source of drinking water.

Author: State Oil And Gas Board

Ala. Admin. Code r. 400-5-6-.02

New Rule: Filed April 11, 2000; effective May 16, 2000.

Statutory Authority:Code of Ala. 1975, §§ 9-17-1etseq.