Section 335-13-4-.11 - General Design Standards For Disposal Facilities
(1)General Standards. 335-13-4-.12 through 335-13-4-.20 provides standards for establishing a landfill unit providing that the siting standards of 335-13-4-.01 have been fully complied with to the satisfaction of the Department. Certain requirements contained in 335-13-4-.01 through 335-13-4-.20 may be enhanced or reduced by the Department as deemed necessary to comply with the Act and this Division.
(2)Hydrogeology Standards.
(a) For purposes of designing the bottom elevation of the proposed cell, the applicant shall measure the groundwater elevation at the location of the proposed cell or liner system. Such determinations shall be based on groundwater measurements taken in the area of the proposed cell or liner system as approved by the Department. At each measuring location, the applicant shall obtain a minimum of two measurements taken during each of the three consecutive months of February, March and April, or as otherwise approved by the Department, with no two measurements taken within any twelve-day period. Having obtained the measurements, the applicant shall design the facility so that the bottom elevation of the proposed cell or liner system shall be a minimum of five feet above the highest measured groundwater level. The applicant shall submit to the Department all data known to exist concerning groundwater elevations at the landfill site and shall submit to the Department a location map showing all monitoring wells or piezometers and drilling logs for all monitoring wells or piezometers used to obtain any groundwater elevation data that is submitted. Nothing herein shall prevent the Department from requiring additional groundwater measurements or from requiring an additional buffer as it may deem appropriate with respect to a particular site.
(b) When the geological and hydrological data so indicate, the Department may specify greater separation distances, a liner(s), or a leachate collection system, or combination of the above to protect the groundwater.
(c) When the geological and hydrological data so indicate, the Department may allow engineering controls to remove, divert, drain, or otherwise modify zones of saturation above the uppermost aquifer.

Ala. Admin. Code r. 335-13-4-.11

November 18, 1981; Amended: July 21, 1988. Amended: Filed September 28, 1993; effective November 2, 1993. Amended: June 21, 1996; effective July 26, 1996.
Amended by Alabama Administrative Monthly Volume XL, Issue No. 01, October 29, 2021, eff. 12/13/2021.

Authors: Russell A. Kelly, S. Scott Story

Statutory Authority:Code of Ala. 1975, §§ 22-27-3, 22-27-7.