Section 335-15-7-.24 - Project Initiation
(1) The recipient shall expeditiously initiate and complete the project in accordance with the project schedule contained in the Fund loan agreement. Failure to promptly initiate and complete a project may result in the imposition of sanctions included in this Chapter.
(2) The recipient shall not advertise any contract until written notice of concurrence with the proposed agreement has been issued by the Department.
(3) Once bids for the project are received, the recipient shall not award the contract(s) until authorization to award has been given by the Department.
(4) The recipient and the contractor shall attend a pre-remediation conference with Department personnel prior to the issuance of a notice to proceed by the recipient.
(5) The recipient shall award the contract(s) and issue notice(s) to proceed, where required, for completing all "significant" elements of the project no later than 12 months after execution of the loan agreement, unless a specific extension has been approved by the Department.

Authors: Aubrey H. White, Lawrence A. Norris

Ala. Admin. Code r. 335-15-7-.24

New Rule: Filed October 21, 2004; effective November 25, 2004.

Statutory Authority:Code of Ala. 1975, §§ 22-30F-2, 22-30F-4.