TUV Rheinland of North America, Inc.: Applications for Expansion of Recognition and Proposed Modification to the List of Appropriate NRTL Test Standards

Download PDF
Federal RegisterOct 31, 2016
81 Fed. Reg. 75444 (Oct. 31, 2016)

AGENCY:

Occupational Safety and Health Administration (OSHA), Labor.

ACTION:

Notice.

SUMMARY:

In this notice, OSHA announces the applications of TUV Rheinland of North America, Inc., for expansion of its recognition as a Nationally Recognized Testing Laboratory (NRTL) and presents the Agency's preliminary finding to grant the applications. Additionally, OSHA proposes to add a new test standard to the NRTL listing of Appropriate Test Standards.

DATES:

Submit comments, information, and documents in response to this notice, or requests for an extension of time to make a submission, on or before November 15, 2016.

ADDRESSES:

Submit comments by any of the following methods:

1. Electronically: Submit comments and attachments electronically at http://www.regulations.gov,, which is the Federal eRulemaking Portal. Follow the instructions online for making electronic submissions.

2. Facsimile: If submissions, including attachments, are not longer than 10 pages, commenters may fax them to the OSHA Docket Office at (202) 693-1648.

3. Regular or express mail, hand delivery, or messenger (courier) service: Submit comments, requests, and any attachments to the OSHA Docket Office, Docket No. OSHA-2007-0042, Technical Data Center, U.S. Department of Labor, 200 Constitution Avenue NW., Room N-2625, Washington, DC 20210; telephone: (202) 693-2350 (TTY number: (877) 889-5627). Note that security procedures may result in significant delays in receiving comments and other written materials by regular mail. Contact the OSHA Docket Office for information about security procedures concerning delivery of materials by express mail, hand delivery, or messenger service. The hours of operation for the OSHA Docket Office are 8:15 a.m.-4:45 p.m., e.t.

4. Instructions: All submissions must include the Agency name and the OSHA docket number (OSHA-2007-0042). OSHA places comments and other materials, including any personal information, in the public docket without revision, and these materials will be available online at http://www.regulations.gov. Therefore, the Agency cautions commenters about submitting statements they do not want made available to the public, or submitting comments that contain personal information (either about themselves or others) such as Social Security numbers, birth dates, and medical data.

5. Docket: To read or download submissions or other material in the docket, go to http://www.regulations.gov or the OSHA Docket Office at the address above. All documents in the docket are listed in the http://www.regulations.gov index; however, some information (e.g., copyrighted material) is not publicly available to read or download through the Web site. All submissions, including copyrighted material, are available for inspection at the OSHA Docket Office. Contact the OSHA Docket Office for assistance in locating docket submissions.

6. Extension of comment period: Submit requests for an extension of the comment period on or before November 15, 2016 to the Office of Technical Programs and Coordination Activities, Directorate of Technical Support and Emergency Management, Occupational Safety and Health Administration, U.S. Department of Labor, 200 Constitution Avenue NW., Room N-3655, Washington, DC 20210, or by fax to (202) 693-1644.

FOR FURTHER INFORMATION CONTACT:

Information regarding this notice is available from the following sources:

Press inquiries: Contact Mr. Frank Meilinger, Director, OSHA Office of Communications, U.S. Department of Labor, 200 Constitution Avenue NW., Room N-3647, Washington, DC 20210; telephone: (202) 693-1999; email: meilinger.francis2@dol.gov.

General and technical information: Contact Mr. Kevin Robinson, Director, Office of Technical Programs and Coordination Activities, Directorate of Technical Support and Emergency Management, Occupational Safety and Health Administration, U.S. Department of Labor, 200 Constitution Avenue NW., Room N-3655, Washington, DC 20210; phone: (202) 693-2110 or email: robinson.kevin@dol.gov.

SUPPLEMENTARY INFORMATION:

I. Notice of the Application for Expansion

The Occupational Safety and Health Administration is providing notice that TUV Rheinland of North America, Inc. (TUVRNA), is applying for expansion of its current recognition as an NRTL. TUVRNA requests the addition of three test standards and two additional recognized sites to its NRTL scope of recognition.

OSHA recognition of an NRTL signifies that the organization meets the requirements specified in 29 CFR 1910.7. Recognition is an acknowledgment that the organization can perform independent safety testing and certification of the specific products covered within its scope of recognition. Each NRTL's scope of recognition includes (1) the type of products the NRTL may test, with each type specified by its applicable test standard; and (2) the recognized site(s) that has/have the technical capability to perform the product-testing and product-certification activities for test standards within the NRTL's scope. Recognition is not a delegation or grant of government authority; however, recognition enables employers to use products approved by the NRTL to meet OSHA standards that require product testing and certification.

The Agency processes applications by an NRTL for initial recognition and for an expansion or renewal of this recognition, following requirements in Appendix A to 29 CFR 1910.7. This appendix requires that the Agency publish two notices in the Federal Register in processing an application. In the first notice, OSHA announces the application and provides its preliminary finding. In the second notice, the Agency provides its final decision on the application. These notices set forth the NRTL's scope of recognition or modifications of that scope. OSHA maintains an informational Web page for each NRTL, including TUVRNA, which details the NRTL's scope of recognition. These pages are available from the OSHA Web site at http://www.osha.gov/dts/otpca/nrtl/index.html.

TUVRNA currently has three facilities (sites) recognized by OSHA for product testing and certification, with its headquarters located at: TUV Rheinland of North America, Inc., 12 Commerce Road, Newtown, Connecticut 06470. A complete list of TUVRNA's scope of recognition is available at https://www.osha.gov/dts/otpca/nrtl/tuv.html.

II. General Background on the Application

TUVRNA submitted five applications, dated April 1, 2015 (OSHA-2007-0042-0016), May 6, 2015 (OSHA-2007-0042-0017), August 20, 2015 (OSHA-2007-0042-0018), December 7, 2015 (OSHA-2007-0042-0019) and March 2, 2016 (OSHA-2007-0042-0020), to expand its recognition to include three additional test standards and two additional recognized sites. The two proposed recognized testing sites are located at: TUV Rheinland Japan Ltd., Global Technology Assessment Center, 4-25-2 Kita-Yamata, Tsuzuki-ku, Yokohama, Kanagawa, 224-0021 JAPAN and TUV Rheinland LGA Products GmbH, Am Grauen Stein 29, Koln, NRW 51105 GERMANY. OSHA performed on-site reviews of TUV Yokohama on February 16-17, 2016, and TUV Cologne on June 9-10, 2016, in relation to these applications, in which assessors found some nonconformances with the requirements of 29 CFR 1910.7. TUVRNA addressed these issues sufficiently and OSHA staff preliminarily determined that OSHA should grant the additional site applications.

TUVRNA's expansion application also requested the addition of three test standards to its NRTL scope of recognition. OSHA staff performed a detailed analysis of the application packet and reviewed other pertinent information as well as conducted the on-site reviews discussed above. Table 1 below lists the appropriate test standards found in TUVRNA's applications for expansion for testing and certification of products under the NRTL Program.

Table 1—Proposed List of Appropriate Test Standards for Inclusion in TUVRNA's NRTL Scope of Recognition

Test standard Test standard title
UL 62368-1 Audio/Visual Information and Communication Technology Equipment—Part 1: Safety Requirements.
UL 1004-1 Standard for Rotating Electrical Machines—General Requirements.
UL 62109-1 * Safety of Power Converters for Use in Photovoltaic Power Systems—Part 1: General Requirements.
* Indicates the standard that OSHA proposes to add to the NRTL List of Appropriate Test Standards.

III. Proposal To Add New Test Standard to the NRTL Program's List of Appropriate Test Standards

Periodically, OSHA will propose to add new test standards to the NRTL list of appropriate test standards following an evaluation of the test standard document. To qualify as an appropriate test standard, the Agency evaluates the document to (1) verify it represents a product category for which OSHA requires certification by an NRTL, (2) verify the document represents an end product and not a component, and (3) verify the document defines safety test specifications (not installation or operational performance specifications). OSHA becomes aware of new test standards through various avenues. For example, OSHA may become aware of new test standards by: (1) Monitoring notifications issued by certain SDOs; (2) reviewing applications by NRTLs or applicants seeking recognition to include a new test standard in their scopes of recognition; and (3) obtaining notification from manufacturers, manufacturing organizations, government agencies, or other parties that a new test standard may be appropriate to add to its list of appropriate standards. OSHA may determine to include a new test standard in the list, for example, if the test standard is for a particular type of product that another test standard also covers or it covers a type of product that no standard previously covered.

In this notice, OSHA proposes to add a new test standard to the NRTL Program's list of appropriate test standards. Table 2, below, lists the test standard that is new to the NRTL Program. OSHA preliminarily determined that this test standard is an appropriate test standard and proposes to include it in the NRTL Program's List of Appropriate Test Standards. OSHA seeks public comment on this preliminary determination.

Table 2—Test Standards OSHA Is Proposing To Add to the NRTL Program's List of Appropriate Test Standards

Test standard Test standard title
UL 62109-1 Safety of Power Converters for Use in Photovoltaic Power Systems—Part 1: General Requirements.

IV. Preliminary Findings on the Application

TUVRNA submitted acceptable applications for expansion of its scope of recognition. OSHA's review of the application files, and pertinent documentation, indicate that TUVRNA can meet the requirements prescribed by 29 CFR 1910.7 for expanding its recognition to include the addition of these three test standards for NRTL testing and certification listed above. OSHA's detailed on-site assessments indicate that TUVRNA can meet the requirements prescribed by 29 CFR 1910.7 for expanding its recognition to include the addition of two sites for NRTL testing and certification. This preliminary finding does not constitute an interim or temporary approval of TUVRNA's applications.

OSHA welcomes public comment as to whether TUVRNA meets the requirements of 29 CFR 1910.7 for expansion of its recognition as an NRTL. Comments should consist of pertinent written documents and exhibits. Commenters needing more time to comment must submit a request in writing, stating the reasons for the request. Commenters must submit the written request for an extension by the due date for comments. OSHA will limit any extension to 10 days unless the requester justifies a longer period. OSHA may deny a request for an extension if the request is not adequately justified. To obtain or review copies of the exhibits identified in this notice, as well as comments submitted to the docket, contact the Docket Office, Room N-2625, Occupational Safety and Health Administration, U.S. Department of Labor, at the above address. These materials also are available online at http://www.regulations.gov under Docket No. OSHA-2007-0042.

OSHA staff will review all comments to the docket submitted in a timely manner and, after addressing the issues raised by these comments, will recommend to the Assistant Secretary for Occupational Safety and Health whether to grant TUVRNA's application for expansion of its scope of recognition. The Assistant Secretary will make the final decision on granting the application. In making this decision, the Assistant Secretary may undertake other proceedings prescribed in Appendix A to 29 CFR 1910.7.

OSHA will publish a public notice of its final decision in the Federal Register.

Authority and Signature

David Michaels, Ph.D., MPH, Assistant Secretary of Labor for Occupational Safety and Health, 200 Constitution Avenue NW., Washington, DC 20210, authorized the preparation of this notice. Accordingly, the Agency is issuing this notice pursuant to 29 U.S.C. 657(g)(2), Secretary of Labor's Order No. 1-2012 (77 FR 3912, Jan. 25, 2012), and 29 CFR 1910.7.

Signed at Washington, DC, on October 25, 2016.

David Michaels,

Assistant Secretary of Labor for Occupational Safety and Health.

[FR Doc. 2016-26204 Filed 10-28-16; 8:45 am]

BILLING CODE 4510-26-P