Notice of Quarterly Report (October 1, 2013-December 31, 2014)

Download PDF
Federal RegisterOct 11, 2016
81 Fed. Reg. 70139 (Oct. 11, 2016)

AGENCY:

Millennium Challenge Corporation.

ACTION:

Notice.

SUMMARY:

The Millennium Challenge Corporation (MCC) is reporting for the fiscal year (FY) quarters October 1, 2013 to December 31, 2014, on assistance provided under section 605 of the Millennium Challenge Act of 2003 (22 U.S.C. 7701 et seq.), as amended (the Act), and on transfers or allocations of funds to other federal agencies under section 619(b) of the Act. The following report will be made available to the public by publication in the Federal Register and on the Internet Web site of the MCC ( www.mcc.gov ) in accordance with section 612(b) of the Act.

Dated: October 5, 2016.

Sarah E. Fandell,

VP/General Counsel and Corporate Secretary, Millennium Challenge Corporation.

As used in MCC's disclosures under section 605 of the Act:

  • “Total Obligation” for listed Compacts includes both “Compact Implementation Funding” under section 609(g) of the Act as well as funding under section 605 of the Act.
  • “Disbursements” are cash outlays rather than expenditures.
  • “Measures” are the same Key Performance Indicators that MCC reports each quarter. The Key Performance Indicators may change over time to more accurately reflect compact implementation progress. The unit for these measures is “a number of” unless otherwise indicated.
  • “Program Administration and Control” funds are used to pay items such as salaries, rent, and the cost of office equipment, as well as audit and oversight agent fees.
  • “Pending Subsequent Reports” amounts represent disbursements made to the Compact permitted account that will be allocated to individual projects in subsequent quarters and reported as such in subsequent quarterly reports. The “Cumulative Disbursements” amount for “Pending Subsequent Reports” represents the balance of such outlays remaining at the end of the reporting period.
  • Closed Compacts do not have any quarterly disbursements; however, they are included in the report if deobligations took place during the reporting period. Closed Compacts include: Armenia, Benin I, Burkina Faso, Cabo Verde I, El Salvador I, Georgia I, Ghana I, Honduras, Lesotho I, Madagascar, Mali, Mongolia I, Morocco I, Mozambique, Namibia, Nicaragua, Tanzania and Vanuatu.
  • Unless otherwise indicated, all programs and projects were solicited.

605 Assistance—Disbursements

[In United States dollars]

Entity provided assistance Program/project name Total obligation FY 2014 Quarter 1 FY 2014 Quarter 2 FY 2014 Quarter 3 FY 2014 Quarter 4 FY 2015 Quarter 1 Cumulative disbursements
Burkina Faso Agriculture Project 141,510,059 11,393,735 9,790,338 15,405,386 8,402,118 3,324,525 140,420,941
Bright 2 School Project 26,840,570 0 0 0 0 0 26,840,570
Land Tenure Project 58,434,615 3,975,944 5,654,577 7,801,917 9,865,824 3,447,221 58,244,614
Monitoring and Evaluation 7,880,000 424,223 242,078 67,134 437,447 191,644 4,669,395
Pending Subsequent Report 0 −507,539 484,451 453,947 −754,421 −180,104 363,539
Program Administration and Control 49,758,545 2,404,048 1,718,737 2,052,781 2,175,099 2,480,361 48,345,809
Roads Project 194,530,681 13,041,011 24,609,125 31,397,256 29,573,406 17,544,857 193,891,857
Total Burkina Faso 478,954,470 30,731,422 42,499,307 57,178,420 49,699,473 26,808,504 472,776,725
Cabo Verde II Land Management For Investment Projects 17,260,000 615,975 559,468 333,731 490,929 259,147 3,268,991
Monitoring and Evaluation 1,390,000 566 −1,481 10,220 11,150 10,735 36,765
Pending Subsequent Report 0 69,969 −62,154 22,752 −11,104 6,032 25,495
Program Administration and Control 7,850,000 258,835 349,255 320,156 343,206 270,631 2,841,607
Water, Sanitation and Hygiene Project 39,730,000 501,339 200,358 678,551 898,674 1,267,782 4,050,504
Total Cabo Verde II 66,230,000 1,446,684 1,045,446 1,365,409 1,732,856 1,814,326 10,223,361
El Salvador II Business Development Services 3,300,000 0 0 0 0 0 0
Human Capital Project 900,000 0 0 0 0 0 0
Infrastructure Project 1,500,000 0 0 0 0 0 0
Monitoring and Evaluation 400,000 0 0 0 0 0 0
Pending Subsequent Report 0 0 0 0 0 0 0
Program Administration and Control 3,900,000 0 0 0 0 0 0
Total El Salvador II 10,000,000 0 0 0 0 0 0
Georgia II Education Project 76,500,000 44,290 159,933 140,131 1,294 331,945 677,594
Monitoring and Evaluation 3,500,000 0 0 0 0 0 0
Pending Subsequent Report 0 209,055 −77,780 177,616 51,163 −320,798 39,256
Program Administration and Control 14,000,000 505,624 407,151 334,171 391,417 736,270 2,374,633
Tertiary Education Project 30,000,000 431,731 388,954 199,789 1,463,627 1,532,985 4,017,085
Vocational Education Project 16,000,000 0 0 0 0 69,300 69,300
Total Georgia II 140,000,000 1,190,700 878,258 851,707 1,907,501 2,349,702 7,177,868
Ghana Administrative 0 0 0 0 0 0 0
Agriculture Project 188,731,530 −407,393 0 407,393 −180,293 0 188,731,530
Infrastructure Project 0 0 0 0 0 0 0
Monitoring and Evaluation 6,941,811 0 0 0 0 0 6,941,811
Pending Subsequent Report 0 3,700,000 0 −3,700,000 0 0 0
Program Administration and Control 36,874,551 0 0 0 1 0 36,874,550
Rural Development Project 76,030,565 0 0 0 127,291 0 76,030,565
Transportation Project 227,710,512 −3,292,608 0 3,292,608 53,000 0 227,710,512
Total Ghana 536,288,969 0 0 0 0 0 536,288,968
Ghana II Access to Electricity Project 700,000 0 0 0 0 0 0
Energy Efficiency and Demand Side Management Project 0 0 0 0 0 0 0
Financial and Operational Turnaround (Electricity Company of Ghana 1) 7,600,800 0 0 0 0 0 0
Financial and Operational Turnaround (Northern Electricity Distribution Company) 3,529,000 0 0 0 0 0 0
Financial and Operational Turnaround (Electricity Company of Ghana 2) 0 0 0 0 0 0 0
Monitoring and Evaluation 1,510,000 0 0 0 0 0 0
Pending Subsequent Report 0 0 0 0 0 0 0
Power Generation Sector Improvement Project 4,854,800 0 0 0 0 0 0
Program Administration and Control 7,455,400 0 0 0 0 0 0
Regulatory Strengthening and Capacity Building Project 3,250,000 0 0 0 0 0 0
Total Ghana II 28,900,000 0 0 0 0 0 0
Indonesia Community Nutrition Project 129,500,000 5,335 36,978 181,792 253,944 11,822,595 34,759,317
Green Prosperity Project 332,500,000 34,962 62,580 66,609 141,356 777,506 1,182,494
Monitoring and Evaluation 12,200,000 0 0 0 0 720,664 720,664
Pending Subsequent Report 0 317,285 −120,503 377,840 −174,359 256,222 729,754
Procurement Modernization Project 50,000,000 351,912 341,260 471,128 816,074 1,925,931 4,009,914
Program Administration and Control 75,800,000 1,402,143 1,512,095 1,954,049 2,499,064 2,322,534 13,595,118
Total Indonesia 600,000,000 2,111,637 1,832,410 3,051,419 3,536,080 17,825,452 54,997,260
Jordan Expansion of Wastewater Treatment Capacity 97,120,950 15,128,511 11,768,335 940,143 9,282,359 1,248,335 76,116,031
Monitoring and Evaluation 2,809,894 21,610 28,847 219,805 21,662 21,675 375,783
Pending Subsequent Report 0 −35,119 4,053 −5,097 23,043 3,021 34,447
Program Administration and Control 19,650,805 386,135 467,561 429,410 490,247 575,135 4,326,590
Wastewater Collection 66,989,225 3,532,261 2,768,093 3,419,241 5,502,460 4,992,258 32,752,377
Water Network Restructuring and Rehabilitation 88,529,127 3,669,481 4,160,537 2,180,324 3,954,905 6,103,494 24,484,800
Total Jordan 275,100,000 22,702,880 19,197,425 7,183,826 19,274,676 12,943,918 138,090,029
Lesotho Capacity Building 0 0 0 0 0 0 0
Civil/Legal Sector Support 0 0 0 0 0 0 0
Health Sector Project 143,650,195 15,919,722 −753,987 23,881 0 0 143,650,195
Land Tenure Project 0 0 0 0 0 0 0
Monitoring and Evaluation 5,500,728 256,974 181,013 0 0 0 5,500,728
Pending Subsequent Report 0 −199,501 1 −12,942 0 0 0
Private Sector Development Project 24,162,433 1,986,028 0 0 0 0 24,162,433
Procurement and Administration 0 0 0 0 0 0 0
Program Administration and Control 34,918,925 2,188,853 101,302 −10,939 0 0 34,918,925
Water Sector Project 149,813,612 14,004,878 −1 0 0 0 149,813,612
Total Lesotho 358,045,892 34,156,953 −471,671 0 0 0 358,045,892
Malawi Gender Integration Project 0 0 0 0 0 0 0
Monitoring and Evaluation 6,960,100 35,880 143,520 0 0 1,131 186,464
Natural Resource Management Project 28,026,000 213,866 91,018 379,585 300,685 10,819 995,972
Pending Subsequent Report 0 248,392 −180,088 −11,041 45,236 −6,728 250,859
Power Project 255,648,800 572,012 134,447 1,035,243 2,253,940 1,735,978 5,731,621
Power Sector Reform Project 25,553,400 221,705 249,385 724,681 718,116 1,335,602 3,472,531
Program Administration and Control 34,511,700 1,027,028 1,383,181 2,356,867 1,627,106 1,629,994 9,346,909
Total Malawi 350,700,000 2,318,884 1,821,463 4,485,335 4,945,082 4,706,796 19,984,357
Mali Alatona Irrigation Project 252,895,691 0 0 0 0 0 252,895,69
Bamako-Senou Airport Improvement Project 143,371,915 0 0 0 −31,476 0 143,371,915
Industrial Park Project 2,637,472 0 0 0 0 0 2,637,472
Monitoring and Evaluation 1,688,026 0 0 0 0 0 1,688,027
Pending Subsequent Report 0 0 0 0 0 0 0
Program Administration and Control 35,003,642 0 0 0 0 0 35,003,642
Total Mali 435,596,747 0 0 0 −31,476 0 435,596,747
Moldova Monitoring and Evaluation 3,538,930 213,834 63,212 382,519 220,343 14,623 1,634,272
Pending Subsequent Report 0 −118,059 199,517 810,446 −293,684 −594,765 134,081
Program Administration and Control 23,247,668 1,223,387 813,895 832,821 836,381 905,775 13,680,202
Road Rehabilitation Project 112,390,000 20,756,036 2,755,131 11,349,069 14,836,137 21,216,346 101,421,448
Transition To High Value Agriculture Project 122,823,402 9,798,457 4,753,661 15,362,042 10,226,080 12,254,189 72,924,459
Total Moldova 262,000,000 31,873,654 8,585,415 28,736,897 25,825,256 33,796,167 189,794,463
Mongolia Energy and Environmental Project 40,420,819 275,302 14,282 17,246 0 0 40,420,819
Health Project 41,873,775 3,261,083 18,608 0 0 0 41,873,776
Monitoring and Evaluation 5,085,246 392,984 0 0 0 0 5,085,246
Pending Subsequent Report 0 −615,790 −57,984 0 0 0 0
Program Administration and Control 28,610,318 1,328,261 662,064 149,507 −74,754 0 28,610,318
Property Rights Project 28,543,830 318,125 20,212 0 0 0 28,543,830
Rail Project 369,560 0 0 0 0 0 369,560
Roads Project 74,775,867 6,147,460 4,236 0 0 0 74,775,867
Vocational Education Project 49,322,727 111,456 17,530 0 0 0 49,322,727
Total Mongolia 269,002,143 11,218,881 678,948 166,754 −74,754 0 269,002,143
Morocco Artisan and Fez Medina Project 84,019,666 15,726,838 −323,055 329,816 0 0 84,019,666
Enterprise Support Project 15,126,518 3,211 49 0 0 0 15,126,518
Financial Accountability 0 0 0 0 0 0 0
Financial Services Project 42,817,020 1,928,094 0 0 0 0 42,817,020
Fruit Tree Productivity Project 324,163,440 30,388,407 1 0 0 0 323,369,991
Monitoring and Evaluation 16,255,526 2,789,915 0 0 0 0 16,255,526
Pending Subsequent Report 0 −1,053,506 −136,770 −46,373 0 0 0
Program Administration and Control 56,500,517 3,891,292 −18 26,022 0 0 56,500,517
Rural Development Project 0 0 0 0 0 0 0
Small-Scale Fisheries Project 111,281,204 18,507,220 310,950 −309,465 0 0 111,281,204
Transportation Project 0 0 0 0 0 0 0
Total Morocco 650,163,890 72,181,470 −148,843 0 0 0 649,370,442
Mozambique Farmer Income Support Project 18,857,349 1,855,435 19,893 0 0 0 18,857,349
Land Tenure Project 39,466,421 3,668,233 −31,999 0 0 0 39,466,421
Monitoring and Evaluation 4,073,077 851,699 21,760 0 0 0 4,073,077
Pending Subsequent Report 0 −2,837,741 −3,115,537 −46,329 0 0 0
Program Administration and Control 48,483,703 6,187,513 1,870,307 46,329 706,997 0 48,483,703
Rehabilitation/Construction Of Roads Project 136,802,301 17,844,298 95,729 0 0 0 136,802,301
Water Supply and Sanitation Project 200,221,661 23,300,256 2,150,510 0 0 0 200,221,661
Total Mozambique 447,904,512 50,869,694 1,010,662 0 706,997 0 447,904,512
Namibia Agriculture Project 51,439,139 3,092,659 4,301,409 3,858,573 2,064,357 2,237,463 50,029,275
Education Project 141,886,916 12,286,634 8,956,394 9,803,025 13,032,538 4,370,143 137,237,213
Monitoring and Evaluation 6,886,182 84,364 290,198 632,806 672,659 773,743 6,415,390
Pending Subsequent Report 0 1,676,086 −516,092 −7,268,389 310,960 646,860 3,716,700
Program Administration and Control 35,789,383 1,665,196 1,235,533 1,423,372 1,598,913 3,994,297 33,365,598
Rural Development Project 0 0 0 0 0 0 0
Tourism Project 68,475,842 4,619,357 5,669,962 11,283,451 10,496,386 6,288,359 65,464,315
Total Namibia 304,477,463 23,424,296 19,937,405 19,732,839 28,175,814 18,310,864 296,228,491
Philippines Community Development Grants Project 120,000,000 4,129,561 7,696,771 7,155,121 7,748,991 7,125,483 75,901,515
KALAHI-CIDSS Project 0 0 0 0 0 0 0
Monitoring and Evaluation 8,207,000 173,308 135,260 99,022 139,294 168,264 2,027,532
Pending Subsequent Report 0 2,111,447 21,877 −1,617,650 911,404 −1,092,558 5,058,482
Program Administration and Control 36,910,000 1,060,649 1,075,900 1,114,616 1,113,703 1,468,306 14,398,261
Revenue Administration Reform Project 54,300,000 55,909 1,125,801 2,645,058 875,506 1,116,814 11,666,358
Roads Project 214,493,000 7,517,140 3,797,637 8,678,866 16,632,689 10,530,412 95,566,371
Total Philippines 433,910,000 15,048,013 13,853,246 18,075,033 27,421,587 19,316,721 204,618,519
Senegal Demand Assessment 0 0 0 0 0 0 0
Irrigation 170,341,171 8,082,655 16,444,544 19,022,475 12,166,091 15,456,116 100,655,919
Land Tenure Project 0 0 0 0 0 0 0
Monitoring and Evaluation 3,757,500 16,716 28,420 24,849 41,683 128,216 774,411
Pending Subsequent Report 0 −719,147 166,031 −535,530 249,080 22,606 568,061
Pre-Feasibility and Feasibility Analysis 0 0 0 0 0 0 0
Program Administration and Control 41,188,830 1,212,154 1,243,739 1,768,298 1,290,872 1,433,630 20,493,819
Roads Project 324,712,499 10,925,884 16,542,582 25,570,082 17,326,600 24,658,251 135,713,053
Total Senegal 540,000,000 19,518,262 34,425,315 45,850,174 31,074,326 41,698,818 258,205,264
Tanzania Energy Sector Project 199,461,627 22,613,285 0 0 0 0 199,461,627
Monitoring and Evaluation 4,632,363 387,554 0 0 0 0 4,632,363
Pending Subsequent Report 0 0 0 0 0 0 0
Program Administration and Control 30,480,760 1,631,748 10,372 0 0 0 30,480,760
Transport Sector Project 405,402,512 44,755,778 0 0 0 0 405,402,512
Water Sector Project 54,568,652 5,093,064 0 0 0 0 54,568,652
Total Tanzania 694,545,914 74,481,428 10,372 0 0 0 694,545,914
Zambia Infrastructure Project 0 0 0 0 0 0 0
Monitoring and Evaluation 5,841,000 0 6,843 1,268 0 0 25,999
Pending Subsequent Report 0 −17,617 18,233 58,777 6,634 7,788 110,436
Program Administration and Control 38,823,951 1,716,377 1,050,630 1,612,473 1,673,344 1,928,332 10,096,838
Water Supply and Sanitation Project 8,137,125 0 0 −1,324,821 0 1,205,107 8,017,411
Water Supply, Sanitation and Drainage Project 301,955,564 62,473 80,042 173,719 529,434 322,397 1,456,503
Total Zambia 354,757,640 1,761,233 1,155,748 521,417 2,209,413 3,463,624 19,707,186

605 Assistance—Measures

Country Objectives FY 2014 FY 2015
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Quarter 1
Burkina Faso Agriculture Development Project Objectives: Expanded productive use of land in order to increase the volume and value of agricultural production in Project Zones Hectares of new perimeter development in Di Responsible members of Water User Associations trained in the Sourou Farmers trained Farmers who have applied improved practices as a result of training Hectares of new perimeter development in Di Responsible members of Water User Associations trained in the Sourou Farmers trained Farmers who have applied improved practices as a result of training Hectares of new perimeter development in Di Responsible members of Water User Associations trained in the Sourou Farmers trained Farmers who have applied improved practices as a result of training Hectares of new perimeter development in Di Responsible members of Water User Associations trained in the Sourou Farmers trained Farmers who have applied improved practices as a result of training
Local water committees established and operational in the Comoé and Mouhoun Local water committees established and operational in the Comoé and Mouhoun Local water committees established and operational in the Comoé and Mouhoun Local water committees established and operational in the Comoé and Mouhoun
Basin Water Resources Development and Management Master Plan developed and validated Basin Water Resources Development and Management Master Plan developed and validated Basin Water Resources Development and Management Master Plan developed and validated Basin Water Resources Development and Management Master Plan developed and validated
Hectares under improved practices as a result of training Hectares under improved practices as a result of training Hectares under improved practices as a result of training Hectares under improved practices as a result of training
BRIGHT II School Project Objectives: Increased primary school completion rates for girls Percent of girls regularly attending (90 percent attendance) BRIGHT II schools Girls promotion rates to next grade in BRIGHT II schools Percent of girls regularly attending (90 percent attendance) BRIGHT II schools Girls promotion rates to next grade in BRIGHT II schools Percent of girls regularly attending (90 percent attendance) BRIGHT II schools Girls promotion rates to next grade in BRIGHT II schools Percent of girls regularly attending (90 percent attendance) BRIGHT II schools Girls promotion rates to next grade in BRIGHT II schools
Percent of girls dropping out of school Percent of girls dropping out of school Percent of girls dropping out of school Percent of girls dropping out of school
Percent of girls passing the annual Primary Certificate exam in BRIGHT II schools Percent of girls passing the annual Primary Certificate exam in BRIGHT II schools Percent of girls passing the annual Primary Certificate exam in BRIGHT II schools Percent of girls passing the annual Primary Certificate exam in BRIGHT II schools
Students enrolled in BRIGHT II schools (both girls and boys) Students enrolled in BRIGHT II schools (both girls and boys) Students enrolled in BRIGHT II schools (both girls and boys) Students enrolled in BRIGHT II schools (both girls and boys)
Land Tenure Project Objectives: Increased investment in land and rural productivity through improved land tenure security and land management Stakeholders trained Rural hectares formalized in the new zone of Di, targeted under the Agriculture Development project Land administration offices established or upgraded Stakeholders trained Rural hectares formalized in the new zone of Di, targeted under the Agriculture Development project Land administration offices established or upgraded Stakeholders trained Rural hectares formalized in the new zone of Di, targeted under the Agriculture Development project Land administration offices established or upgraded Stakeholders trained Rural hectares formalized in the new zone of Di, targeted under the Agriculture Development project Land administration offices established or upgraded
Municipal buildings constructed Municipal buildings constructed Municipal buildings constructed Municipal buildings constructed
Rural land possession certificates approved by the local government Rural and possession certificates approved by the local government Rural land possession certificates approved by the local government Rural land possession certificates approved by the local government
Land conflicts recorded in the 17 communes of phase I of the Rural Land Governance project Land conflicts recorded in the 17 communes of phase I of the Rural Land Governance project Land conflicts recorded in the 17 communes of phase I of the Rural Land Governance project Land conflicts recorded in the 17 communes of phase I of the Rural Land Governance project
Land resolved in the 17 communes of Phase I of the Rural Land Governance project Land resolved in the 17 communes of Phase I of the Rural Land Governance project Land resolved in the 17 communes of Phase I of the Rural Land Governance project Land resolved in the 17 communes of Phase I of the Rural Land Governance project
Roads Project Objectives: Enhanced access to markets through investments in the road network Periodic road maintenance coverage rate (for all funds) (percent) Kilometers of primary roads completed Periodic road maintenance coverage rate (for all funds) (percent) Kilometers of primary roads completed Periodic road maintenance coverage rate (for all funds) (percent) Kilometers of primary roads completed Periodic road maintenance coverage rate (for all funds) (percent) Kilometers of primary roads completed
Percent disbursed of road construction contracts (primary roads) Percent disbursed of road construction contracts (primary roads) Percent disbursed of road construction contracts (primary roads) Percent disbursed of road construction contracts (primary roads)
Kilometers of rural roads completed Kilometers of rural roads completed Kilometers of rural roads completed Kilometers of rural roads completed
Percent disbursed of road construction contracts (rural roads) Percent disbursed of road construction contracts (rural roads) Percent disbursed of road construction contracts (rural roads) Percent disbursed of road construction contracts (rural roads)
Cabo Verde II Land Management for Investment Projects Objectives: Increased investments in and value of property; improved ease of doing business; increased investments and value added in tourism; increased employment Legal and regulatory reforms adopted Field test of “Fieldwork Operations Manual” and methodology completed on Sal Stakeholders receiving formal on-the-job training or technical assistance regarding roles, responsibilities or new technologies Legal and regulatory reforms adopted Field test of “Fieldwork Operations Manual” and methodology completed on Sal Stakeholders receiving formal on-the-job training or technical assistance regarding roles, responsibilities or new technologies Legal and regulatory reforms adopted Field test of “Fieldwork Operations Manual” and methodology completed on Sal Stakeholders receiving formal on-the-job training or technical assistance regarding roles, responsibilities or new technologies Legal and regulatory reforms adopted Field test of “Fieldwork Operations Manual” and methodology completed on Sal Stakeholders receiving formal on-the-job training or technical assistance regarding roles, responsibilities or new technologies Legal and regulatory reforms adopted. Field test of “Fieldwork Operations Manual” and methodology completed on Sal.
Percent of targeted surface area on target island (Sal) incorporated into the Land Management Information and Transaction System (LMITS).
Households in intervention island(s) of high tourism investment potential with land rights formalized through project.
Parcels corrected or incorporated in land system.
Land administration offices established or upgraded.
Adoption of “Operations Manual” for the Rights and Boundaries Activity fieldwork in full force and effect.
Water, Sanitation, and Hygiene Project Objectives: Increased access to improved water and sanitation; reduced household costs for water; reduced incidence of waterborne disease; improved capital accumulation; increase productive government spending Value of implicit subsidy reduction (U.S. dollars) Operating cost coverage (percent) Service coverage by corporatized utilities (percent) Continuity of service (hours/day) Objective measure of water quality (percent Non-revenue water for Multiple Municipal Utility/utilities (percent) Value of implicit subsidy reduction (U.S. dollars) Operating cost coverage (percent) Service coverage by corporatized utilities (percent) Continuity of service (hours/day) Objective measure of water quality (percent Non-revenue water for Multiple Municipal Utility/utilities (percent) Value of implicit subsidy reduction (U.S. dollars) Operating cost coverage (percent) Service coverage by corporatized utilities (percent) Continuity of service (hours/day) Objective measure of water quality (percent Non-revenue water for Multiple Municipal Utility/utilities (percent) Value of implicit subsidy reduction (U.S. dollars) Operating cost coverage (percent) Service coverage by corporatized utilities (percent) Continuity of service (hours/day) Objective measure of water quality (percent Non-revenue water for Multiple Municipal Utility/utilities (percent) Value of implicit subsidy reduction (U.S. dollars). Operating cost coverage (percent). Service coverage by corporatized utilities (percent). Continuity of service (hours/day). Objective measure of water quality (percent). Non-revenue water for Multiple Municipal Utility/utilities (percent).
Value of signed water and sanitation construction contracts Value of signed water and sanitation construction contracts Value of signed water and sanitation construction contracts Value of signed water and sanitation construction contracts Value of signed water and sanitation construction works contracts.
Percent disbursed of water and sanitation construction contracts Percent disbursed of water and sanitation construction contracts Percent disbursed of water and sanitation construction contracts Percent disbursed of water and sanitation construction contracts Percent disbursed of water and sanitation construction works contracts.
Strategic National Master Plan and Strategic Environmental and Social Assessment approved by appropriate authorities Strategic National Master Plan and Strategic Environmental and Social Assessment approved by appropriate authorities Strategic National Master Plan and Strategic Environmental and Social Assessment approved by appropriate authorities Strategic National Master Plan and Strategic Environmental and Social Assessment approved by appropriate authorities Strategic National Master Plan and Strategic Environmental and Social Assessment approved by appropriate authorities.
Value of signed water and sanitation feasibility and design contracts Value of signed water and sanitation feasibility and design contracts Value of signed water and sanitation feasibility and design contracts Value of signed water and sanitation feasibility and design contracts Value of signed water and sanitation feasibility and design contracts.
Percent disbursed of water and sanitation feasibility and design contracts Percent disbursed of water and sanitation feasibility and design contracts Percent disbursed of water and sanitation feasibility and design contracts Percent disbursed of water and sanitation feasibility and design contracts Percent disbursed of water and sanitation feasibility and design contracts.
Percent disbursed of technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project Percent disbursed of technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project Percent disbursed of technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project Percent disbursed of technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project Percent disbursed of technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project.
Value disbursed of Infrastructure Grant Facility Social Funds for disadvantaged groups and/or poor households Value disbursed of Infrastructure Grant Facility Social Funds for disadvantaged groups and/or poor households Value disbursed of Infrastructure Grant Facility Social Funds for disadvantaged groups and/or poor households Value disbursed of Infrastructure Grant Facility Social Funds for disadvantaged groups and/or poor households Value disbursed of Infrastructure Grant Facility Social Funds for disadvantaged groups and/or poor households.
Value of all signed technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project Value of all signed technical advisory services and training contracts in support of the Water, Sanitation and Hygiene Project
Collection Ratio.
Multiple municipal utilities staff per 1,000 potable water connections.
El Salvador II Business Development Services Measures pending Measures pending Measures pending Measures pending Measures pending.
Human Capital Project
Infrastructure Project
Georgia II Education Project Measures pending Measures pending Measures pending Measures pending Schools fully rehabilitated.
Science labs installed and equipped.
Percent disbursed of educational facility construction, rehabilitation, and equipping contracts.
School-based professional development facilitators trained.
School principals trained.
Science, math, English, and information and communication technology teachers trained.
Completion of teacher training design framework.
International assessments completed
Completion of pilot testing of national assessment instruments.
Vocational Education Project Measures pending Measures pending Measures pending Measures pending Students participating in MCC-supported Technical Vocational Education and Training (TVET) programs.
Industry co-investment in TVET provision.
Date first grant agreement is signed.
Total grant outlays.
Tertiary Education Project Measures pending Measures pending Measures pending Measures pending Students enrolled in MCC-supported U.S. bachelor's programs.
First cohort of students enter MCC-funded science, technology, engineering and math bachelor's program.
Signing of partnership agreement between the Government of Georgia and university partner.
Georgian partner university faculty members receiving training from U.S. partner institution.
Ghana II Access to Electricity Project Measures pending Measures pending Measures pending Measures pending Measures pending.
Energy Efficiency and Demand Side Management Project
Power Generation Sector Improvement Project
Regulatory Strengthening and Capacity Building Project
Indonesia Community Nutrition Project Objectives: Reduce and prevent low birth weight and childhood stunting and malnourishment of children in project areas, and to increase household income through cost savings, productivity growth and higher lifetime earnings Value of Generasi block grants funded Value of Generasi block grants funded Value of Generasi block grants funded Value of Generasi block grants funded Value of Generasi block grants funded.
Service providers trained on infant and young child feeding Service providers trained on infant and young child feeding Service providers trained on infant and young child feeding Service providers trained on infant and young child feeding Service providers trained on infant and young child feeding Service providers trained on mother, infant and young child feeding.
Communications Campaign design complete Communications Campaign design complete Communications Campaign design complete Communications Campaign design complete Communications Campaign design complete Date Communications Campaign design complete.
Micro-nutrient packages delivered (Iron Folic) (millions) Micro-nutrient packages delivered (Iron Folic) (millions) Micro-nutrient packages delivered (Iron Folic) (millions) Micro-nutrient packages delivered (Iron Folic) (millions) Micro-nutrient packages delivered (Iron Folic) (millions) Micro-nutrient packages delivered (Iron Folic).
Micro-nutrient packages delivered (Taburia) (millions) Micro-nutrient packages delivered (Taburia) (millions) Micro-nutrient packages delivered (Taburia) (millions) Micro-nutrient packages delivered (Taburia) (millions) Micro-nutrient packages delivered (Taburia).
Generasi proposals Generasi proposals Generasi proposals Generasi proposals
Generasi facilitators trained on stunting and gender Generasi facilitators trained on stunting and gender Generasi facilitators trained on stunting and gender Generasi facilitators trained on stunting and gender
Sanitation triggering events.
Service providers trained on growth monitoring.
Green Prosperity Project Objectives: Increase productivity and reduce reliance on fossil fuels by expanding renewable energy; and Increase productivity and reduce land-based greenhouse gas emissions by improving land use practices and management of natural resources Signed memoranda of understanding between the Indonesia accountable entity and districts Green Knowledge work plan completed Financial service provider partnerships established (loan agreement) Financial service provider partnerships established (grant partnerships) Signed memoranda of understanding between the Indonesia accountable entity and districts Green Knowledge work plan completed Financial service provider partnerships established (loan agreement) Financial service provider partnerships established (grant partnerships) Signed memoranda of understanding between the Indonesia accountable entity and districts Green Knowledge work plan completed Financial service provider partnerships established (loan agreement) Financial service provider partnerships established (grant partnerships) Signed memoranda of understanding between the Indonesia accountable entity and districts Green Knowledge work plan completed Financial service provider partnerships established (loan agreement) Financial service provider partnerships established (grant partnerships) Signed memoranda of understanding between the Indonesia accountable entity and districts. Green Knowledge work plan completed.
Financial service provider partnerships established (grant managers) Financial service provider partnerships established (grant managers) Financial service provider partnerships established (grant managers) Financial service provider partnerships established (grant managers)
Project financing approved by the Green Prosperity Finance Facility Project financing approved by the Green Prosperity Finance Facility Project financing approved by the Green Prosperity Finance Facility Project financing approved by the Green Prosperity Finance Facility
Formal district adoption of guidelines for participatory village boundary setting Formal district adoption of guidelines for participatory village boundary setting Formal district adoption of guidelines for participatory village boundary setting Formal district adoption of guidelines for participatory village boundary setting
Financial service provider partnerships established (implementing entity agreements) Financial service provider partnerships established (implementing entity agreements) Financial service provider partnerships established (implementing entity agreements) Financial service provider partnerships established (implementing entity agreements)
Project funds disbursed by the Technical Assistance and Oversight Activity (percent) Project funds disbursed by the Technical Assistance and Oversight Activity (percent) Project funds disbursed by the Technical Assistance and Oversight Activity (percent) Project funds disbursed by the Technical Assistance and Oversight Activity (percent)
Hectares targeted for improved practices for sustainable agriculture (including agro-forestry) as a result of Green Prosperity-funded projects and/or partnerships.
Hectares targeted for protection through Green Prosperity-funded projects and/or partnerships.
Additional capacity of renewable energy planned.
Grant agreements approved by Green Prosperity Finance Facility.
Villages assisted in participatory boundary setting.
District land use, land cover, and permits and licenses inventories created.
Proposals that receive project preparation support.
Procurement Modernization Project Objectives: Achieve significant government expenditure savings on procured goods and services, while assuring their quality satisfies the public need, and to achieve the delivery of public services as planned Procurement management information system adopted Creation of sustainable procurement policy National Action Plan Framework agreements signed and catalogued Procurement Service Unit staff trained Creation of public private partnership standard bidding documents Procurement management information system adopted Creation of sustainable procurement policy National Action Plan Framework agreements signed and catalogued Procurement Service Unit staff trained Creation of public private partnership standard bidding documents Procurement management information system adopted Creation of sustainable procurement policy National Action Plan Framework agreements signed and catalogued Procurement Service Unit staff trained Creation of public private partnership standard bidding documents Procurement management information system adopted Creation of sustainable procurement policy National Action Plan Framework agreements signed and catalogued Procurement Service Unit staff trained Creation of public private partnership standard bidding documents Procurement management information system adopted (Phase I). Date the sustainable procurement policy National Action Plan endorsed.
Date e-catalogue system established.
Mentor visits conducted.
Hours of training conducted.
Jordan Expansion Of Wastewater Treatment Capacity Objectives: Increase the volume of treated wastewater available as a substitute for freshwater in agricultural use Treated wastewater used in agriculture (as a percent of all water used for irrigation in Northern and Middle Jordan Valley) Value disbursed of construction contracts; MCC contribution Treated wastewater used in agriculture (as a percent of all water used for irrigation in Northern and Middle Jordan Valley) Value disbursed of construction contracts; MCC contribution Treated wastewater used in agriculture (as a percent of all water used for irrigation in Northern and Middle Jordan Valley) Value disbursed of construction contracts; MCC contribution Treated wastewater used in agriculture (as a percent of all water used for irrigation in Northern and Middle Jordan Valley) Value disbursed of construction contracts; MCC contribution Treated wastewater used in agriculture (as a percent of all water used for irrigation in Northern and Middle Jordan Valley). Value disbursed of construction contracts; MCC contribution.
Total engineering, procurement, and construction costs of As-Samra Expansion Total engineering, procurement, and construction costs of As-Samra Expansion Total engineering, procurement, and construction costs of As-Samra Expansion Total engineering, procurement, and construction costs of As-Samra Expansion Total engineering, procurement, and construction costs of As-Samra Expansion.
Wastewater Collection Objectives: Increase access to the wastewater network, increase the volume of wastewater collected and reduce the incidents of sewage overflow Sewer blockage events; annual Volume of wastewater collected; (millions of cubic meters per year) Residential population connected to the sewer system (percent) Sewer blockage events; annual Volume of wastewater collected; (millions of cubic meters per year) Residential population connected to the sewer system (percent) Sewer blockage events; annual Volume of wastewater collected; (millions of cubic meters per year) Residential population connected to the sewer system (percent) Sewer blockage events; annual Volume of wastewater collected; (millions of cubic meters per year) Residential population connected to the sewer system (percent) Sewer blockage events; annual. Volume of wastewater collected; (millions of cubic meters per year). Residential population connected to the sewer system (percent).
Expand network (kilometers) Expand network (kilometers) Expand network (kilometers) Expand network (kilometers) Expand network (kilometers).
Value disbursed of sanitation construction contracts Value disbursed of sanitation construction contracts Value disbursed of sanitation construction contracts Value disbursed of sanitation construction contracts Value disbursed of sanitation construction contracts.
Water Network Restructuring and Rehabilitation Objectives: Reduce water losses, improve continuity of water service and improve overall efficiency and use of network water delivery leading to households substituting network water for costly alternatives Network water consumption per capita (residential and non-residential); liters/capita/day Operating cost coverage—Water Authority Jordan Zarqa Non-Revenue Water (percent) Continuity of Supply time; hours per week Restructured and rehabilitated primary and secondary pipelines (kilometers) Network water consumption per capita (residential and non-residential); liters/capita/day Operating cost coverage—Water Authority Jordan Zarqa Non-Revenue Water (percent) Continuity of Supply time; hours per week Restructured and rehabilitated primary and secondary pipelines (kilometers) Network water consumption per capita (residential and non-residential); liters/capita/day Operating cost coverage—Water Authority Jordan Zarqa Non-Revenue Water (percent) Continuity of Supply time; hours per week Restructured and rehabilitated primary and secondary pipelines (kilometers) Network water consumption per capita (residential and non-residential); liters/capita/day Operating cost coverage—Water Authority Jordan Zarqa Non-Revenue Water (percent) Continuity of Supply time; hours per week Restructured and rehabilitated primary and secondary pipelines (kilometers) Network water consumption per capita (residential and non-residential); liters/capita/day. Operating cost coverage—Water Authority Jordan Zarqa. Non-Revenue Water (percent). Continuity of Supply time; hours per week. Restructured and rehabilitated primary and secondary pipelines (kilometers).
Restructured and rehabilitated tertiary pipelines (kilometers) Restructured and rehabilitated tertiary pipelines (kilometers) Restructured and rehabilitated tertiary pipelines (kilometers) Restructured and rehabilitated tertiary pipelines (kilometers) Restructured and rehabilitated tertiary pipelines (kilometers).
Value disbursed of water construction contracts—Infrastructure Activity and Water Smart Homes Activity Value disbursed of water construction contracts—Infrastructure Activity and Water Smart Homes Activity Value disbursed of water construction contracts—Infrastructure Activity and Water Smart Homes Activity Value disbursed of water construction contracts—Infrastructure Activity and Water Smart Homes Activity Value disbursed of water construction contracts—Water Network Project.
National Aid Fund households with improved water and wastewater network National Aid Fund households with improved water and wastewater network National Aid Fund households with improved water and wastewater network National Aid Fund households with improved water and wastewater network National Aid Fund households with improved water and wastewater network.
National Aid Fund households connected to the wastewater network as a result of the Water Smart Homes Activity National Aid Fund households connected to the wastewater network as a result of the Water Smart Homes Activity National Aid Fund households connected to the wastewater network as a result of the Water Smart Homes Activity National Aid Fund households connected to the wastewater network as a result of the Water Smart Homes Activity National Aid Fund households connected to the wastewater network as a result of the Water Smart Homes Activity.
Lesotho Health Sector Project Objectives: Increase access to life-extending anti-retroviral treatment and essential health services by providing a sustainable delivery platform Deliveries conducted in health centers (percent) People with HIV still alive 12 months after initiation of treatment (percent) Tuberculosis notifications (per 100,000 population) Health centers equipped (percent) Physical completion of health center facilities (percent) Compact closed Compact closed Compact closed Compact closed.
Physical completion of Outpatient Departments (percent)
Physical completion of the Botsabelo facilities (percent)
Private Sector Development Project Objectives: Stimulate investment by improving access to credit, reducing transaction costs and increasing the participation of women in the economy Debit/smart cards issued Bonds registered Change in time for property transactions (percent) Urban land parcels regularized and registered Stakeholders trained Time required to resolve commercial disputes (days) Compact closed Compact closed Compact closed Compact closed.
Cases filed at the commercial court
Women holding titles to land
People trained
Water Sector Project Objectives: Improve the water supply for industrial and domestic needs, and enhance rural livelihoods through improved watershed management Physical completion of Metolong water treatment works contract (percent) Households with provisions to connect to water networks Non-revenue water (percent) Physical completion of Urban Water supply works contracts (percent) Compact closed Compact closed Compact closed Compact closed.
Ventilated improved pit latrines built
Water points constructed
Malawi Natural Resource Management Project Objectives: Increase efficiency of hydropower generation Value of signed weed and sediment management activity contracts Distribution of invasive aquatic species (cubic kilometers) Value of signed weed and sediment management activity contracts Distribution of invasive aquatic species (cubic kilometers) Value of signed weed and sediment management activity contracts Distribution of invasive aquatic species (cubic kilometers) Value of signed weed and sediment management activity contracts Distribution of invasive aquatic species (cubic kilometers) Value of signed weed and sediment management activity contracts.
Amount of weed harvested at Liwonde barrage (metric tons) Amount of weed harvested at Liwonde barrage (metric tons) Amount of weed harvested at Liwonde barrage (metric tons) Amount of weed harvested at Liwonde barrage (metric tons)
Grant agreements in place with civil society and private sector service providers.
Value of signed Environmental and Natural Resource Management & Social and Gender Assessment project contracts.
Power Project Objectives: Improve the availability, reliability and quality of the power supply by increasing the throughput capacity and stability of the national electricity grid Percent disbursed of feasibility and design contracts Average duration of outages/interruptions (hours) Average frequency of forced outages/Interruptions (ratio) Percent disbursed of feasibility and design contracts Average duration of outages/interruptions (hours) Average frequency of forced outages/Interruptions (ratio) Percent disbursed of feasibility and design contracts Average duration of outages/interruptions (hours) Average frequency of forced outages/Interruptions (ratio) Percent disbursed of feasibility and design contracts Average duration of outages/interruptions (hours) Average frequency of forced outages/Interruptions (ratio) Percent disbursed of feasibility and design contracts.
Average frequency of forced outages/Interruptions (ratio) Average frequency of forced outages/Interruptions (ratio) Average frequency of forced outages/Interruptions (ratio)
Value of signed power infrastructure construction contracts.
Power Sector Reform Project Objectives: Create an enabling environment for future expansion by strengthening sector institutions and enhancing regulation and governance of the sector Cost recovery ratio—operating expenses (percent) Debt- equity ratio Average creditor days Cost recovery ratio—operating expenses (percent) Debt- equity ratio Average collections period (days) Cost recovery ratio—operating expenses (percent) Debt- equity ratio Average collections period (days) Cost recovery ratio—operating expenses (percent) Debt- equity ratio Average collections period (days)
Electricity Supply Corporation of Malawi Maintenance Expenditures ratio to planned maintenance budget.
Bad Debt.
Approved tariff levels and schedules (actual) (U.S. cents/kilowatt hour).
Tariff levels and schedules (U.S. cents/kilowatt hour) Tariff levels and schedules (U.S. cents/kilowatt hour) Tariff levels and schedules (U.S. cents/kilowatt hour) Tariff levels and schedules (U.S. cents/kilowatt hour)
Moldova Road Rehabilitation Project Objectives: Enhance transportation conditions Reduced cost for road users Average annual daily traffic Road maintenance expenditure Reduced cost for road users Average annual daily traffic Road maintenance expenditure Reduced cost for road users Average annual daily traffic Road maintenance expenditure Reduced cost for road users Average annual daily traffic Road maintenance expenditure Reduced cost for road users. Average annual daily traffic. Road maintenance expenditure.
Kilometers of roads completed Kilometers of roads completed Kilometers of roads completed Kilometers of roads completed Kilometers of roads completed.
Percent of contracted roads works disbursed Percent of contracted roads works disbursed Percent of contracted roads works disbursed Percent of contracted roads works disbursed Percent of contracted roads works disbursed.
Road safety training for children (number of children) Road safety training for children (number of children) Road safety training for children (number of children) Road safety training for children (number of children) Road safety training for children (number of children).
Date Resettlement Action Plan completed Date Resettlement Action Plan completed Date Resettlement Action Plan completed Date Resettlement Action Plan completed Date Resettlement Action Plan completed.
Trafficking in persons training participants Trafficking in persons training participants Trafficking in persons training participants Trafficking in persons training participants Trafficking in persons training participants.
Roughness (meters per kilometer).
Temporary employment generated in road construction (number employed).
Hectares under improved or new irrigation Hectares under improved or new irrigation Hectares under improved or new irrigation Hectares under improved or new irrigation Hectares under improved or new irrigation.
Centralized irrigation systems rehabilitated Centralized irrigation systems rehabilitated Centralized irrigation systems rehabilitated Centralized irrigation systems rehabilitated Centralized irrigation systems rehabilitated.
Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts.
Management transfer agreements signed Management transfer agreements signed Management transfer agreements signed Management transfer agreements signed Management transfer agreements signed.
New high value agriculture infrastructure in place (metric tons) New high value agriculture infrastructure in place (metric tons) New high value agriculture infrastructure in place (metric tons) New high value agriculture infrastructure in place (metric tons) New high value agriculture infrastructure in place (metric tons).
Loans past due Loans past due Loans past due Loans past due Loans past due.
Value of agricultural and rural loans Value of agricultural and rural loans Value of agricultural and rural loans Value of agricultural and rural loans Value of agricultural and rural loans.
Loan borrowers Loan borrowers Loan borrowers Loan borrowers Loan borrowers.
Loan borrowers (female) Loan borrowers (female) Loan borrowers (female) Loan borrowers (female) Loan borrowers (female).
Value of sales facilitated Value of sales facilitated Value of sales facilitated Value of sales facilitated Value of sales facilitated.
Farmers who have applied improved practices as a result of training Farmers who have applied improved practices as a result of training Farmers who have applied improved practices as a result of training Farmers who have applied improved practices as a result of training Farmers who have applied improved practices as a result of training.
Farmers trained Farmers trained Farmers trained Farmers trained Farmers trained.
Farmers trained (female) Farmers trained (female) Farmers trained (female) Farmers trained (female) Farmers trained (female).
Enterprises assisted Enterprises assisted Enterprises assisted Enterprises assisted Enterprises assisted.
Enterprises assisted (female) Enterprises assisted (female) Enterprises assisted (female) Enterprises assisted (female) Enterprises assisted (female).
Water user associations achieving financial sustainability Water user associations achieving financial sustainability Water user associations achieving financial sustainability Water user associations achieving financial sustainability
Transition To High Value Agriculture Project Objectives: Increase incomes in the agricultural sector; Create models for transition to high value agriculture (HVA) in CIS areas and an enabling environment (legal, financial and market) for replication. Value of signed irrigation construction contracts Date Revised Legal Water Management Framework passed Water user associations with active and representative governance Water user associations with gender-balanced management and governance Value of signed irrigation construction contracts Date Revised Legal Water Management Framework passed Water user associations with active and representative governance Water user associations with gender-balanced management and governance Value of signed irrigation construction contracts Date Revised Legal Water Management Framework passed Water user associations with active and representative governance Water user associations with gender-balanced management and governance Value of signed irrigation construction contracts Date Revised Legal Water Management Framework passed Water user associations with active and representative governance Water user associations with gender-balanced management and governance Value of signed irrigation construction contracts. Date Revised Legal Water Management Framework passed. Water user associations with active and representative governance. Water user associations with gender-balanced management and governance.
Enterprises that have applied improved techniques Enterprises that have applied improved techniques Enterprises that have applied improved techniques Enterprises that have applied improved techniques Enterprises that have applied improved techniques.
Percent disbursed of irrigation feasibility and design contracts Percent disbursed of irrigation feasibility and design contracts Percent disbursed of irrigation feasibility and design contracts Percent disbursed of irrigation feasibility and design contracts Percent disbursed of irrigation feasibility and design contracts.
Value of signed irrigation feasibility and design contracts Value of signed irrigation feasibility and design contracts Value of signed irrigation feasibility and design contracts Value of signed irrigation feasibility and design contracts Value of signed irrigation feasibility and design contracts.
Temporary employment generated in irrigation.
The Central Phytosanitary Lab is certified.
Mongolia Energy and Environmental Project Objectives: Increased wealth and productivity through greater fuel use efficiency and decreasing health costs from air pollution in Ulaanbaatar Heat-only boilers sites upgraded Subsidized stoves sold. Power dispatched from substation (millions of kilowatt hours). Compact closed Compact closed Compact closed Compact closed.
Health Project Objectives: Reduce the risk of premature death and disability from NCDs and traffic injuries Amount of civil society grants (U.S. dollars) Cervical cancer cases detected early (percent) Screening for hypertension (percent) School teachers trained Health staff trained Compact closed Compact closed Compact closed Compact closed.
Primary healthcare facilities with non-communicable disease services (percent)
Property Rights Project Objectives: Increase the security and capitalization of land assets held by lower-income Mongolians, and increase peri-urban herder productivity and incomes Wells completed
Stakeholders trained Leases awarded Project herder groups limiting their livestock population to the carrying capacity of their leases on farms in 3 central aimags (Ulaanbaatar, Darkhan and Erdenet) (percent) Compact closed Compact closed Compact closed Compact closed.
Official cost prescribed for property transactions (first-time) (U.S. dollars)
Household with land rights formalized
Legal and regulatory reforms adopted
Stakeholders trained
Roads Project Objectives: More efficient transport for trade and access to services Kilometers of roads completed Kilometers of roads under design Compact closed Compact closed Compact closed Compact closed.
Percent disbursed of road construction contracts
Technical Vocational Education Project Objectives: Increase employment and income among unemployed and underemployed Mongolians Students participating in MCC-supported education activities Public-private partnership funding contributed to Technical Vocational Education and Training (TVET) schools (percent) Compact closed Compact closed Compact closed Compact closed.
Educational facilities constructed or rehabilitated
Instructors trained
Morocco Artisan and Fez Medina Project Objectives: Increase revenue from cultural and artisan activities, and improve educational and professional qualifications of compact beneficiaries Total receiving literacy training Graduates of MCC-supported functional literacy program (female) Graduates of MCC-supported functional literacy program (male) Total receiving professional training Compact closed Compact closed Compact closed Compact closed.
Females receiving professional training
Graduates of vocational training program (residential, apprenticeship and continuing education)
Drop-out rates of participants of residential and apprenticeship programs (percent)
Potters trained
MCC-subsidized gas kilns bought by artisans
Adoption rate of improved production practices promoted by the project (percent)
Tourist circuits improved or created
Small and medium enterprises (SMEs) that append the label on their products
SMEs participating in promotion events
Sites constructed or rehabilitated (4 foundouks, Place Lalla Ydouna, Ain Nokbi)
Beneficiaries of Ain Nokbi construction and artisan resettlement program
Enterprise Support Project Objectives: Improve the outcomes of the Moukawalati and National Initiative for Human Development programs by increasing the viability of young enterprises created through these programs Reduction in SME mortality (treatment firms with respect to control firms) one year after support completion (percent) Days of individual coaching Beneficiaries trained Compact closed Compact closed Compact closed Compact closed.
Financial Services Project Objectives: Improve micro-enterprise services and remove most severe constraints to the development of the microfinance sector based on market principals Value of loan agreements between microcredit associations and Jaida (millions of Moroccan dirhams) Microfinance institutions' portfolio at risk at 30 days (percent) Value of loans granted through mobile branches (U.S. dollars) Compact closed Compact closed Compact closed Compact closed.
Clients reached through mobile branches
Value of loan disbursements to Jaida (U.S. dollars)
Fruit Tree Productivity Project Objectives: Stimulate growth in the agricultural sector and reduce the volatility of agricultural production by restructuring farming from grains towards fruit tree cultivation Area planted and delivered to farmers (hectares) Area in expansion perimeters for which water and soil conservation measures have been implemented (hectares) Cumulative area of irrigated perimeters rehabilitated (hectares) Compact closed Compact closed Compact closed Compact closed.
Yield of rehabilitated olive trees in irrigated areas (metric tons per hectare)
Average agricultural revenue per farm in oasis areas (U.S. dollars)
Hectares under improved irrigation
Yield of rehabilitated date palms in oasis areas (metric tons per hectare)
In vitro seedlings successfully planted
Farmers trained (in all areas targeted by the project)
Catalyst Fund proposals approved
Disbursements under the catalyst fund (U.S. dollars)
Small-Scale Fisheries Project Objectives: Supported by modern landing-site infrastructure, equipment and storage facilities, develop value-chain activities related to the fishing industry encouraging greater access to national and international markets, while improving the fish quality and preserving resources Boats benefitting from landing sites and ports Artisan fishers who received a training certificate Average price of fish at auction markets (Moroccan dirhams per kilogram) Work days created for construction jobs in landing sites, ports, and wholesale market sites Active mobile fish vendors trained and equipped by the project Compact closed Compact closed Compact closed Compact closed.
Net annual income of mobile fish vendors (U.S. dollars)
Mozambique Farmer Income Support Project Objectives: To protect and restore income from coconuts and their derivatives and expand farmers' productive capacity through income diversification. Survival rate of coconut seedlings (percent) Coconut seedlings planted Farmers trained in surveillance and pest and disease control for coconuts Farmers trained in planting and post planting management of coconuts Compact closed Compact closed Compact closed Compact closed.
Hectares of alternative crops under production
Farmers trained in alternative crop production and productivity enhancing strategies
Farmers using alternative crop production and productivity enhancing strategies (percent)
Businesses receiving Business Development Fund grants
Land Tenure Project Objectives: Establish efficient and secure land access for households, communities, and investors People trained (paralegal courses at Legal and Judicial Training Centre, general training at National Directorate for Land and Forestry, etc.) Land administration offices established or upgraded Land tenure regularization (LTR) urban parcels mapped LTR land use property rights certificates (DUATs) delivered to the urban beneficiaries Compact closed Compact closed Compact closed Compact closed.
LTR rural hectares mapped
LTR DUATs delivered to the rural beneficiaries
Community Land Fund rural hectares formalized
Community Land Fund communities land areas mapped
Rehabilitation/Construction of Roads Project Objectives: To increase access to productive resources and markets while reducing associated transport costs Percent of roads works contracts disbursed Kilometers of roads issued take-over certificates Compact closed Compact closed Compact closed Compact closed.
Water Supply and Sanitation Project Objectives: To increase access to reliable sources of potable water supply in urban and rural areas and improved sanitation in urban and peri-urban areas Value of municipal sanitation and drainage systems construction contracts signed Amount disbursed for municipal sanitation and drainage construction contracts Value of contracts signed for construction of water systems Compact closed Compact closed Compact closed Compact closed.
Percent of revised construction contract disbursed for water systems
Rural water points constructed
Percent of rural population of the six intervention districts with access to improved water sources
Amount disbursed for rural water points construction contracts (U.S. dollars)
Persons trained in hygiene and sanitary best practices
Namibia Agriculture Project Objectives: Enhance the health and marketing efficiency of livestock in the Northern Communal Areas of Namibia and to increase income from indigenous natural products accruing to the poor nationwide Participating households registered in the Community-Based Rangeland and Livestock Management sub-activity Grazing areas with documented combined management plans Parcels corrected or incorporated in land system Participating households registered in the Community-Based Rangeland and Livestock Management sub-activity Grazing areas with documented combined management plans Parcels corrected or incorporated in land system Participating households registered in the Community-Based Rangeland and Livestock Management sub-activity Grazing areas with documented combined management plans Parcels corrected or incorporated in land system Participating households registered in the Community-Based Rangeland and Livestock Management sub-activity Grazing areas with documented combined management plans Parcels corrected or incorporated in land system Participating households registered in the Community-Based Rangeland and Livestock Management sub-activity. Grazing areas with documented combined management plans. Parcels corrected or incorporated in land system.
Stakeholders trained Stakeholders trained Stakeholders trained Stakeholders trained Stakeholders trained.
Cattle tagged with RFID tags Cattle tagged with RFID tags Cattle tagged with RFID tags Cattle tagged with RFID tags Cattle tagged with RFID tags.
Value of grant agreements signed under the Livestock Efficiency Fund Value of grant agreements signed under the Livestock Efficiency Fund Value of grant agreements signed under the Livestock Efficiency Fund Value of grant agreements signed under the Livestock Efficiency Fund Value of grant agreements signed under the Livestock Efficiency Fund.
Farmers trained Farmers trained Farmers trained Farmers trained Farmers trained.
Payment to producers from Indigenous Natural Products sales Payment to producers from Indigenous Natural Products sales Payment to producers from Indigenous Natural Products sales Payment to producers from Indigenous Natural Products sales Payment to producers from Indigenous Natural Products sales.
Grazing areas doing combined herding Grazing areas doing combined herding Grazing areas doing combined herding Grazing areas doing combined herding Grazing areas doing combined herding.
Legal and regulatory reforms adopted Legal and regulatory reforms adopted Legal and regulatory reforms adopted Legal and regulatory reforms adopted Legal and regulatory reforms adopted.
New state veterinary offices operational New state veterinary offices operational New state veterinary offices operational New state veterinary offices operational New state veterinary offices operational.
Education Project Objectives: Improve the quality of the workforce in Namibia by enhancing the equity and effectiveness of basic vocational, and tertiary education and of technical skills Learners (any level) participating in the 47 schools sub-activity Educational facilities constructed, rehabilitated, equipped in the 47 schools sub‐activity Textbooks delivered Learners (any level) participating in the 47 schools sub-activity Educational facilities constructed, rehabilitated, equipped in the 47 schools sub‐activity Textbooks delivered Learners (any level) participating in the 47 schools sub-activity Educational facilities constructed, rehabilitated, equipped in the 47 schools sub‐activity Textbooks delivered Learners (any level) participating in the 47 schools sub-activity Educational facilities constructed, rehabilitated, equipped in the 47 schools sub‐activity Textbooks delivered Learners (any level) participating in the 47 schools sub-activity. Educational facilities constructed, rehabilitated, equipped in the 47 schools sub‐activity. Textbooks delivered.
Educators trained to be textbook management trainers Educators trained to be textbook management trainers Educators trained to be textbook management trainers Educators trained to be textbook management trainers Educators trained to be textbook management trainers.
Educators trained to be textbook utilization trainers Educators trained to be textbook utilization trainers Educators trained to be textbook utilization trainers Educators trained to be textbook utilization trainers Educators trained to be textbook utilization trainers.
Visits to Namibia accountable entity assisted regional study and resource centers Visits to Namibia accountable entity assisted regional study and resource centers Visits to Namibia accountable entity assisted regional study and resource centers Visits to Namibia accountable entity assisted regional study and resource centers Visits to Namibia accountable entity assisted regional study and resource centers.
Compliance rate for National Training Fund levy Compliance rate for National Training Fund levy Compliance rate for National Training Fund levy Compliance rate for National Training Fund levy Compliance rate for National Training Fund levy.
Graduates from MCC-supported education activities Graduates from MCC-supported education activities Graduates from MCC-supported education activities Graduates from MCC-supported education activities Graduates from MCC-supported education activities.
Percent of schools with positions filled to teach information, communication and technology literacy Percent of schools with positions filled to teach information, communication and technology literacy Percent of schools with positions filled to teach information, communication and technology literacy Percent of schools with positions filled to teach information, communication and technology literacy Percent of schools with positions filled to teach information, communication and technology literacy.
Regional study and resource centers opened to visitors Regional study and resource centers opened to visitors Regional study and resource centers opened to visitors Regional study and resource centers opened to visitors Regional study and resource centers opened to visitors.
Percent of positions at regional study and resource centers staffed Percent of positions at regional study and resource centers staffed Percent of positions at regional study and resource centers staffed Percent of positions at regional study and resource centers staffed Percent of positions at regional study and resource centers staffed.
Community skills development centers and arts and crafts centers completed Community skills development centers and arts and crafts centers completed Community skills development centers and arts and crafts centers completed Community skills development centers and arts and crafts centers completed Community skills development centers and arts and crafts centers completed.
Modified National Student Financial Assistance Fund management information system completed Modified National Student Financial Assistance Fund management information system completed Modified National Student Financial Assistance Fund management information system completed Modified National Student Financial Assistance Fund management information system completed Modified National Student Financial Assistance Fund management information system completed.
Tourism Project Objectives: Grow the Namibian tourism industry with a focus on increasing income to households in communal conservancies Tourists to Etosha National Park Galton Gate Plan implemented Unique visits on Namibia Tourism Board website Leisure tourist arrivals North American tourism businesses (travel agencies and tour operators) that offer Namibian tours or tour packages Tourists to Etosha National Park Galton Gate Plan implemented Unique visits on Namibia Tourism Board website Leisure tourist arrivals North American tourism businesses (travel agencies and tour operators) that offer Namibian tours or tour packages Tourists to Etosha National Park Galton Gate Plan implemented Unique visits on Namibia Tourism Board website Leisure tourist arrivals North American tourism businesses (travel agencies and tour operators) that offer Namibian tours or tour packages Tourists to Etosha National Park Galton Gate Plan implemented Unique visits on Namibia Tourism Board website Leisure tourist arrivals North American tourism businesses (travel agencies and tour operators) that offer Namibian tours or tour packages Tourists to Etosha National Park Galton Gate Plan implemented. Unique visits on Namibia Tourism Board website. Leisure tourist arrivals. North American tourism businesses (travel agencies and tour operators) that offer Namibian tours or tour packages.
Annual gross revenue to conservancies receiving assistance from Namibia accountable entity (Namibian dollars) Annual gross revenue to conservancies receiving assistance from Namibia accountable entity (Namibian dollars) Annual gross revenue to conservancies receiving assistance from Namibia accountable entity (Namibian dollars) Annual gross revenue to conservancies receiving assistance from Namibia accountable entity (Namibian dollars) Annual gross revenue to conservancies receiving assistance from Namibia accountable entity (Namibian dollars).
Amount of new private sector investment secured by conservancies assisted by Namibia accountable entity (Namibian dollars) Amount of new private sector investment secured by conservancies assisted by Namibia accountable entity (Namibian dollars) Amount of new private sector investment secured by conservancies assisted by Namibia accountable entity (Namibian dollars) Amount of new private sector investment secured by conservancies assisted by Namibia accountable entity (Namibian dollars) Amount of new private sector investment secured by conservancies assisted by Namibia accountable entity (Namibian dollars).
Value of grants issued by the Conservancy Development Support Grant Fund (Namibian dollars) Value of grants issued by the Conservancy Development Support Grant Fund (Namibian dollars) Value of grants issued by the Conservancy Development Support Grant Fund (Namibian dollars) Value of grants issued by the Conservancy Development Support Grant Fund (Namibian dollars) Value of grants issued by the Conservancy Development Support Grant Fund (Namibian dollars).
Galton Gate construction: schedule performance index Galton Gate construction: schedule performance index Galton Gate construction: schedule performance index Galton Gate construction: schedule performance index Galton Gate construction: schedule performance index.
Ombika Gate construction: schedule performance index Ombika Gate construction: schedule performance index Ombika Gate construction: schedule performance index Ombika Gate construction: schedule performance index Ombika Gate construction: schedule performance index.
Philippines Community Development Grants Project New jobs in tourism created in conservancies New jobs in tourism created in conservancies New jobs in tourism created in conservancies New jobs in tourism created in conservancies New jobs in tourism created in conservancies.
Completed KALAHI-CIDSS (KC) sub-projects implemented in compliance with technical plans and within schedule and budget Completed KALAHI-CIDSS (KC) sub-projects implemented in compliance with technical plans and within schedule and budget Completed KALAHI-CIDSS (KC) sub-projects implemented in compliance with technical plans and within schedule and budget
Communities and/or barangays with KC sub-projects that have a sustainability evaluation rating of satisfactory or better (percent) Communities and/or barangays with KC sub-projects that have a sustainability evaluation rating of satisfactory or better (percent) Communities and/or barangays with KC sub-projects that have a sustainability evaluation rating of satisfactory or better (percent) Communities and/or barangays with KC sub-projects that have a sustainability evaluation rating of satisfactory or better (percent)
KALAHI-CIDSS Project Objectives: The KALAHI-CIDSS (KC) Project expects to improve the responsiveness of local governments to community needs, encourage communities to engage in development activities, and deliver benefits to barangay residents through the individual sub-projects Municipalities that provide their KC local counterpart contributions (LCC) based on their LCC delivery plan (percent) Municipalities that provide their KC local counterpart contributions(LCC) based on their LCC delivery plan (percent) Municipalities that provide their KC local counterpart contributions (LCC) based on their LCC delivery plan (percent) Percentage of municipalities that provide their KC local counterpart contributions (LCC) based on their LCC delivery plan Percentage of municipalities that provide their KC local counterpart contributions (LCC) based on their LCC delivery plan.
Sub-projects completed with 100 percent physical accomplishment Sub-projects completed with 100 percent physical accomplishment.
Barangays that have completed all the trainings during the social preparation stage.
Barangays that have completed Thematic Environment Management System TEMS Training.
Barangays that have completed gender-related training.
Roads Project Objectives: The Secondary National Roads Development Project expects to lower vehicle operating costs and save the time of those Filipinos living near the roads Kilometers of road sections completed Value of road construction contracts signed Value of road construction contracts signed Kilometers of road sections completed Value of road construction contracts signed Value of road construction contracts signed Kilometers of road sections completed Value of road construction contracts signed Value of road construction contracts signed Kilometers of road sections completed Value of road construction contracts signed Value of road construction contracts signed Value of road construction contracts disbursed.
Project-affected parties resettled Project-affected parties resettled Project-affected parties resettled Project-affected parties resettled Project-affected parties resettled.
Kilometers of roads with vehicle-passable (lanes).
Project-affected entities compensated (female).
Revenue Administration Reform Project Objectives: The Revenue Administration Reform Project expects to increase tax revenues over time and support the Department of Finance's initiatives to detect and deter corruption within its revenue agencies Successful case resolutions Successful case resolutions Successful case resolutions Successful case resolutions Successful case resolutions.
Personnel charged with graft, corruption, lifestyle and/or criminal cases Personnel charged with graft, corruption, lifestyle and/or criminal cases Personnel charged with graft, corruption, lifestyle and/or criminal cases Personnel charged with graft, corruption, lifestyle and/or criminal cases Personnel charged with graft, corruption, lifestyle and/or criminal cases.
Revenue District Offices using electronic tax information system (percent) Revenue District Offices using electronic tax information system (percent) Revenue District Offices using electronic tax information system (percent) Revenue District Offices using electronic tax information system (percent) Revenue District Offices using electronic tax information system (percent).
Audit cases performed using automated audit tools (percent) Audit cases performed using automated audit tools (percent) Audit cases performed using automated audit tools (percent) Percentage of audit cases performed using automated audit tools Percentage of audit cases performed using automated audit tools.
Average time taken to complete investigation (days) Average time taken to complete investigation (days) Average time taken to complete investigation (days) Average time taken to complete investigation (days)
Audits Audits Audits Percentage of automatically-generated audits
Audits completed in compliance with prescribed period of 120 days (percent) Audits completed in compliance with prescribed period of 120 days (percent) Audits completed in compliance with prescribed period of 120 days (percent)
Percentage of audits completed in compliance with prescribed period of 180 days
Revenue collection per audit (millions of Philippine pesos).
Revenue from new and existing business registrants.
Senegal Irrigation Objectives: Improve productivity of the agricultural sector Tons of irrigated rice production Hectares under production Tons of irrigated rice production Hectares under production Rice paddy production (tons) Hectares under production Rice paddy production (tons) Hectares under production across cropping seasons Rice paddy production (tons). Hectares under production across cropping season.
Percent of disbursement on the construction contracts signed for the irrigation infrastructures in the Delta and the Ngallenka Percent of disbursement on the construction contracts signed for the irrigation infrastructures in the Delta and the Ngallenka Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts Percent disbursed of irrigation construction contracts.
New conflicts resolved (percent) New conflicts resolved (percent) Conflicts successfully mediated Conflicts successfully mediated Conflicts successfully mediated.
People trained on land security tools People trained on land security tools Participants in the training modules on land tenure security tools Participants in the training modules on land tenure security tools Participants in the training modules on land tenure security tools.
Women trained on land security tools Women trained on land security tools Participants in the training modules on land tenure security tools (female) Participants in the training modules on land tenure security tools (female) Participants in the training modules on land tenure security tools (female).
Cropping intensity (hectares under production per year/cultivable hectares) (Delta Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Delta Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Delta Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Delta Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Delta Activity).
Cropping intensity (hectares under production per year/cultivable hectares) (Podor Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Podor Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Podor Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Podor Activity) Cropping intensity (hectares under production per year/cultivable hectares) (Podor Activity).
Value of the construction contracts signed for the irrigation infrastructure in the Delta Value of the construction contracts signed for the irrigation infrastructure in the Delta Value of the construction contracts signed for the irrigation infrastructure in the Delta Value of the construction contracts signed for the irrigation infrastructure in the Delta Value of the construction contracts signed for the irrigation infrastructure in the Delta.
Value of the construction contracts signed for the irrigation infrastructure in Ngallenka Value of the construction contracts signed for the irrigation infrastructure in Ngallenka Value of the construction contracts signed for the irrigation infrastructure in Ngallenka Value of the construction contracts signed for the irrigation infrastructure in Ngallenka Value of the construction contracts signed for the irrigation infrastructure in Ngallenka.
Potentially irrigable lands area (Delta and Ngallenka) (hectares) Potentially irrigable lands area (Delta and Ngallenka) (hectares)
Total area with improved irrigation infrastructure (Delta and Ngallenka) (hectares) Total area with improved irrigation infrastructure (Delta and Ngallenka) (hectares) Total area with improved irrigation infrastructure (Delta and Ngallenka) (hectares).
Temporary employment generated in irrigation (number employed).
Hectares formalized (having a land allocation title and registered).
Roads Project Objectives: Expand Access to Markets and Services Percent of disbursements for the contract signed for the constructions of the National Road (RN) #2 and National Road (RN) #6 Percent of disbursements for the contract signed for the constructions of the National Road (RN) #2 and National Road (RN) #6 Percent disbursed of road construction contracts Percent disbursed of road construction contracts Percent disbursed of road construction contracts.
Kilometers of roads rehabilitated on the RN#2 Kilometers of roads rehabilitated on the RN#2 Kilometers of roads rehabilitated on the RN#2 Kilometers of roads rehabilitated on the RN#2 Kilometers of roads rehabilitated on the RN#2.
International Roughness Index on the RN#2 International Roughness Index on the RN#2 Roughness (RN#2) Roughness (RN#2) Roughness (RN#2).
International Roughness Index on the RN#6 International Roughness Index on the RN#6 Roughness (RN#6) Roughness (RN#6) Roughness (RN#6).
Value of contracts signed for the construction of the RN#2 and the RN#6 Value of contracts signed for the construction of the RN#2 and the RN#6 Value of signed road construction contracts Value of signed road construction contracts Value of signed road construction contracts.
Kilometers of roads rehabilitated on the RN#6 Kilometers of roads rehabilitated on the RN#6 Kilometers of rehabilitated roads on RN#6 Kilometers of rehabilitated roads on RN#6 Kilometers of rehabilitated roads on RN#6.
Kilometers of roads covered by the contract for the studies, the supervision and management of the RN#2 Kilometers of roads covered by the contract for the studies, the supervision and management of the RN#2 Kilometers of roads under design of the RN#2 Kilometers of roads under design of the RN#2
Kilometers of roads covered by the contract for the studies, the supervision and management of the RN#6 Kilometers of roads covered by the contract for the studies, the supervision and management of the RN#6 Kilometers of roads under design of the RN#6 Kilometers of roads under design of the RN#6
Temporary employment generated in road construction (number employed).
Tanzania Energy Sector Project Objectives: Increased value added Current power customers (Zanzibar Interconnector Activity) Compact closed Compact closed Compact closed Compact closed.
Transmission and distribution substations capacity (megawatt peak) (Zanzibar Interconnector Activity)
Technical and non-technical losses (Zanzibar) (percent)
Kilometers of 132 kilovolt (kv) lines constructed
Percent disbursed on overhead lines contract
Current power customers (Malagarsi Hydropower and Kigoma Distribution Activity)
Capacity of photovoltaic (PV) systems installed (kilowatt peak)
Current power customers (all six project regions in Mainland)
Kilometers of 33/11 kV lines constructed
Transmission and distribution substations capacity (megavolt ampere) (all six project regions in Mainland)
Technical and non-technical losses (all six project regions in Mainland and Kigoma) (percent)
Cost recovery ratio
Transport Sector Project Objectives: Increased cash crop revenue; Increased aggregate visitor spending Percent disbursed on construction contracts Surfacing complete: Tunduma-Sumbawanga (percent) Compact closed Compact closed Compact closed Compact closed.
Surfacing complete: Tanga-Horohoro (percent)
Surfacing complete: Namtumbo-Songea (percent)
Surfacing complete: Peramiho-Mbinga (percent)
Kilometers of roads completed (taken over) (Mainland Roads Activity)
Pemba: Percent disbursed on construction contract
Surfacing complete: Pemba (percent)
Kilometers of roads completed (taken over) (Zanzibar Rural Roads Activity)
Road maintenance expenditures: Mainland Trunk Roads (percent)
Road maintenance expenditures: Zanzibar Rural Roads (percent)
Runway surfacing complete (percent)
Water Sector Project Objectives: Increased investment in human and physical capital; Reduced prevalence of water-related diseases Volume of water produced (millions of liters per day) (Lower Ruvu Plant Expansion Activity) Operations and maintenance cost recovery (percent) (Lower Ruvu Plant Expansion Activity) Compact closed Compact closed Compact closed Compact closed
Volume of water produced (millions of liters per day) (Morogoro Water Supply Activity)
Operations and Maintenance Cost Recovery (percent) (Morogoro Water Supply Activity)
Zambia Water Supply, Sanitation and Drainage Project Objectives: Increase access to clean water to generate time and cost savings for beneficiaries Measures pending Measures pending Percent disbursed of water and sanitation construction contracts Volume of water produced (cubic meters per day) Proposals received Grantees Percent disbursed of water and sanitation construction contracts Volume of water produced (cubic meters per day) Proposals received Grantees Percent disbursed of water and sanitation construction contracts. Volume of water produced (cubic meters per day). Proposals received. Grantees.
People trained in social and gender integration and social inclusion People trained in social and gender integration and social inclusion People trained in social and gender integration and social inclusion.
People trained in social and gender integration and social inclusion (female) People trained in social and gender integration and social inclusion (female) People trained in social and gender integration and social inclusion (female).
People trained in social and gender integration and social inclusion (male) People trained in social and gender integration and social inclusion (male) People trained in social and gender integration and social inclusion (male).
Meters installed or replaced Meters installed or replaced Meters installed or replaced.
Value of compensation for displaced businesses and households (U.S. dollars) Value of compensation for displaced businesses and households (U.S. dollars)
Value of water, sanitation and drainage construction contracts signed (U. S. dollars) Value of water, sanitation and drainage construction contracts signed (U. S. dollars)
Households and businesses displaced Households and businesses displaced
People trained in hygiene and sanitary best practices.
People trained in hygiene and sanitary best practices (female).
People trained in hygiene and sanitary best practices (male).

619(b)—Transfer or Allocation of Funds

United States agency to which funds were transferred or allocated Amount Description of program or project
None None None.

[FR Doc. 2016-24512 Filed 10-7-16; 8:45 am]

BILLING CODE 9211-03-P