Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protest

Download PDF
Federal RegisterJun 28, 2004
69 Fed. Reg. 36083 (Jun. 28, 2004)
June 18, 2004.

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

a. Type of Application: Subsequent minor license.

b. Project No.: 632-009.

c. Date filed: February 13, 2004.

d. Applicant: Monroe City.

e. Name of Project: Lower Monroe Hydroelectric Project.

f. Location: On Monroe Creek, 2 miles east of Monroe City, Sevier County, Utah. The project affects about 1.36 acres of federal lands within the Fishlake National Forest.

g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).

h. Applicant Contact: R. Craig Mathie, Mayor, Monroe City, 10 North Main, Monroe, Utah 84754, (435) 527-4621; John Spendlove, Jones & DeMille Engineering, 1535 South 100 West, Richfield, Utah 84701, (435) 896-8266.

i. FERC Contact: Gaylord W. Hoisington, (202) 502-6032, or e-mail at: gaylord.hoisington@ferc.gov.

j. Cooperating agencies: We are asking federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues to cooperate with the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing comments described in item k below.

k. Deadline for filing comments and requests for cooperating agency status: August 24, 2004.

All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

Motions to intervene and protests and requests for cooperating agency status may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site ( http://www.ferc.gov ) under the “e-Filing” link.

l. This application has been accepted, but is not ready for environmental analysis at this time.

m. The proposed run-of-river project consists of: (1) A 10-foot-high, 13-foot-long concrete overflow-type diversion structure with an adjustable slide gate; (2) a concrete intake structure with a trash rack and a 21-inch-diameter, 100-foot-long cast iron pipeline; (3) a 8,400-foot-long, 16-inch-diameter to 20-inch diameter welded steel and ductile iron pipe penstock; (4) a 15-foot-wide, 26-foot-long reinforced concrete and concrete block power house containing a Pelton Wheel turbine with a 250-kilwatt generator and controls; (5) a 250-foot-long transmission line; and (6) appurtenant facilities.

n. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at (866) 208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

o. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

Magalie R. Salas,

Secretary.

[FR Doc. E4-1421 Filed 6-25-04; 8:45 a.m.]

BILLING CODE 6717-01-P