Lockhart Power Company; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, and Terms and Conditions

Download PDF
Federal RegisterJan 4, 2010
75 Fed. Reg. 143 (Jan. 4, 2010)
December 23, 2009.

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:

a. Type of Application: Non-Capacity Amendment of License.

b. Project No.: 2620-042.

c. Date Filed: November 25, 2009.

d. Applicant: Lockhart Power Company.

e. Name of Project: Lockhart Project.

f. Location: The project is located on the Broad River in the Town of Lockhart, Chester, Union, Cherokee, and York Counties, South Carolina.

g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.

h. Applicant Contact: Mr. Bryan D. Stone, Chief Operating Officer, Lockhart Power Company, PO Box 10, 420 River Street, Lockhart, South Carolina 29364, (800) 368-1289.

i. FERC Contact: Mr. Jeremy Jessup (202) 502-6779 or Jeremy.Jessup@ferc.gov.

j. Deadline for filing motions to intervene and protests, comments, recommendations, and preliminary terms and conditions, is 60 days from the issuance of this notice; reply comments are due 105 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

k. Description of Request: The applicant proposes to install a single submersible turbine/generator unit in the hydro canal bank and provide for seasonal fluctuations of head pond levels up to 5 feet for the months of July and August when necessitated by peak power demands. The generating unit would have an installed capacity of 534 kW and an estimated hydraulic capacity of 280 cfs. The proposed unit will draw water from the existing hydro canal to provide minimum-flow releases to the bypassed reach. The installed capacity of the Project will increase to 18.5 megawatts (MW) with the installation of the new unit.

l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission's Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502-8371. This filing may also be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, call 1-866-208-3372 or e-mail FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at the address in item (h) above.

m. Individuals desiring to be included on the Commission's mailing list should so indicate by writing to the Secretary of the Commission.

n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

o. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the title “PROTEST,” “MOTION TO INTERVENE,” “COMMENTS,” “REPLY COMMENTS,” “RECOMMENDATIONS,” or ” TERMS AND CONDITIONS”; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene or protests should relate to project works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

p. As provided for in 18 CFR 4.34(b)(5)(i), a license applicant must file, no later than 60 days following the date of issuance of this notice of acceptance and ready for environmental analysis: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.

q. e-Filing: Comments, motions to intervene, protests, or terms and conditions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site at http://www.ferc.gov under the “eFiling” link.

Kimberly D. Bose,

Secretary.

[FR Doc. E9-31087 Filed 12-31-09; 8:45 am]

BILLING CODE 6717-01-P