Information Collection Request Submitted to OMB for Review and Approval; Comment Request; NESHAP for Perchloroethylene Dry Cleaning Facilities (Renewal)

Download PDF
Federal RegisterApr 26, 2016
81 Fed. Reg. 24607 (Apr. 26, 2016)

AGENCY:

Environmental Protection Agency (EPA).

ACTION:

Notice.

SUMMARY:

The Environmental Protection Agency has submitted an information collection request (ICR), “NESHAP for Perchloroethylene Dry Cleaning Facilities (40 CFR part 63, subpart M) (Renewal)” (EPA ICR No. 1415.11, OMB Control No. 2060-0659), to the Office of Management and Budget (OMB) for review and approval in accordance with the Paperwork Reduction Act (44 U.S.C. 3501 et seq.). This is a proposed extension of the ICR, which is currently approved through April 30, 2016. Public comments were previously requested via the Federal Register (80 FR 32116) on June 5, 2015 during a 60-day comment period. This notice allows for an additional 30 days for public comments. A fuller description of the ICR is given below, including its estimated burden and cost to the public. An Agency may neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

DATES:

Additional comments may be submitted on or before May 26, 2016.

ADDRESSES:

Submit your comments, referencing Docket ID Number EPA-HQ-OECA-2012-0659, to: (1) EPA online using www.regulations.gov (our preferred method), or by email to docket.oeca@epa.gov, or by mail to: EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 1200 Pennsylvania Ave. NW., Washington, DC 20460; and (2) OMB via email to oira_submission@omb.eop.gov. Address comments to OMB Desk Officer for EPA.

EPA's policy is that all comments received will be included in the public docket without change including any personal information provided, unless the comment includes profanity, threats, information claimed to be Confidential Business Information (CBI), or other information whose disclosure is restricted by statute.

FOR FURTHER INFORMATION CONTACT:

Patrick Yellin, Monitoring, Assistance, and Media Programs Division, Office of Compliance, Mail Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. NW., Washington, DC 20460; telephone number: (202) 564-2970; fax number: (202) 564-0050; email address: yellin.patrick@epa.gov.

SUPPLEMENTARY INFORMATION:

Supporting documents which explain in detail the information that the EPA will be collecting are available in the public docket for this ICR. The docket can be viewed online at www.regulations.gov or in person at the EPA Docket Center, WJC West, Room 3334, 1301 Constitution Ave. NW., Washington, DC. The telephone number for the Docket Center is 202-566-1744. For additional information about EPA's public docket, visit: http://www.epa.gov/dockets.

Abstract: Owners and operators of perchloroethylene dry cleaning facilities are required to comply with reporting and record keeping requirements for the general provisions of 40 CFR part 63, subpart A, as well as the applicable standards in 40 CFR part 63, subpart M. This includes submitting initial notifications, performance tests and periodic reports and results, and maintaining records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. These reports are used by EPA to determine compliance with these standards.

Form Numbers: None.

Respondents/affected entities: Dry cleaning facilities that use perchloroethylene.

Respondent's obligation to respond: Mandatory (40 CFR part 63, subpart M).

Estimated number of respondents: 28,012 (total).

Frequency of response: Initially and occasionally.

Total estimated burden: 1,590,000 hours (per year). Burden is defined at 5 CFR 1320.3(b).

Total estimated cost: $167,000,000 (per year), which includes $947,000 in both annualized capital/startup and operation & maintenance costs.

Changes in the Estimates: There is an adjustment increase in respondent labor hours in this ICR from the most-recently approved ICR. This is due to assuming all existing sources will have to re-familiarize with the regulatory requirements each year. Additionally, there is an increase in the total capital and O&M cost due to the rounding of all calculated values to three significant digits.

Courtney Kerwin,

Acting Director, Collection Strategies Division.

[FR Doc. 2016-09548 Filed 4-25-16; 8:45 am]