Duke Power; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests

Download PDF
Federal RegisterJul 15, 2004
69 Fed. Reg. 42436 (Jul. 15, 2004)
July 9, 2004.

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

a. Type of Application: New major license.

b. Project No.: 2692-032.

c. Date Filed: February 20, 2004.

d. Applicant: Duke Power (Nantahala Area).

e. Name of Project: Nantahala Hydroelectric Project.

f. Location: On the Nantahala River and its tributaries, in Macon and Clay Counties, North Carolina. There are 41 acres of USFS managed land (Nantahala National Forest) within the Nantahala Project boundary.

g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

h. Applicant Contact: John C. Wishon, Nantahala Area Relicensing Project Manager, Duke Power, 301 NP&L Loop, Franklin, NC 28734, (828) 369-4604, jcwishon@duke-energy.com.

i. FERC Contact: Carolyn Holsopple at (202) 502-6407 or carolyn.holsopple@ferc.gov.

j. Deadline for Filing Motions to Intervene and Protests: 60 days from the issuance date of this notice.

All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

Motions to intervene and protests may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site ( http://www.ferc.gov ) under the “e-Filing” link.

k. This application has been accepted for filing, but is not ready for environmental analysis at this time.

l. The existing Nantahala Project operates in a peaking mode and consists of the following features: (1) A 1,042-foot-long, 250-foot-tall earth and rockfill dam; (2) a spillway for the dam located at the east abutment; (3) a 1,605 acre reservoir, with a normal reservoir elevation of 3,012.2 feet National Geodetic Vertical Datum and a storage capacity of 38,336 acre-feet; (4) a reinforced concrete powerhouse containing one generating unit having an installed capacity of 42 megawatts (MW); (5) two diversions (Dicks Creek and Whiteoak Creek) that provide additional flow into the project; and (6) appurtenant facilities.

m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

n. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, or prescriptions.

All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE”; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

Magalie R. Salas,

Secretary.

[FR Doc. E4-1571 Filed 7-14-04; 8:45 am]