UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF GEORGIA
ATLANTA DIVISION
IN RE TRANSCONTINENTAL GAS PIPE
LINE COMPANY, LLC
_____________________________________
LEAD FILE NO.
1:16-CV-02991-ELR
INDIVIDUAL FILE NOS.
1:16-CV-03211-ELR
1:16-CV-03212-ELR
1:16-CV-03224-ELR
1:16-CV-03228-ELR
1:16-CV-03231-ELR
1:16-CV-03234-ELR
1:16-CV-03242-ELR
1:16-CV-03258-ELR
FIRST CONSOLIDATED REPLY 1 IN SUPPORT OF TRANSCO’S
MOTIONS FOR PARTIAL SUMMARY JUDGMENT AND
PRELIMINARY INJUNCTION
INTRODUCTION
Transco filed these and other consolidated eminent domain actions in
September 2016 to condemn property that it needs to construct a pipeline project
called the Dalton Expansion. In an August 3, 2016 Order, the Federal Energy
1 Transco filed one reply on October 7, 2014 because of a deadline (Case No. 1:16-
CV-03249-ELR) but will consolidate further replies for the Court’s convenience.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 1 of 16
- 2 -
Regulatory Commission (FERC) authorized the Dalton Expansion, granting Transco
a certificate of public convenience and necessity to proceed with the project (“FERC
Certificate”). With that Certificate in hand, Transco has eminent-domain power. See
15 U.S.C. § 717f(h).
Accordingly, Transco moved for partial summary judgment on its right to
condemn the property and for a preliminary injunction granting Transco the right to
access the property immediately so that it can begin construction on the Dalton
Expansion. Certain Defendants, recognizing the merits of Transco’s motions, did not
oppose those motions. See, e.g., Brief of Defendants Bruce and Kenda Johnson in
Response to Plaintiff’s Motion for Preliminary Injuction, Transcon. Gas Pipeline
Co., LLC v. 1.84 acres, et al., No. 1:16-CV-03226-ELR, Dkt. No. 11, at 2
(“Defendants do not object to Plaintiff’s motion . . . Furthermore, Defendants
acknowledge that Plaintiff has met the requirements for the issuance of a preliminary
injunction to commence work on the pipeline.”); Conse t Order Granting Plaintiff’s
Motions for Partial Summary Judgment and Preliminary Injunction, Transcon. Gas
Pipeline Co., LLC., v. 9.37 acres, et al., No. 1:16-CV-03377-ELR, Dkt. No. 19, ¶ 6
(“Defendant . . . does not contest Transco’s authority under 15 U.S.C. § 717f(h) to
condemn the easement interests sought in its Complaint, nd does not oppose
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 2 of 16
- 3 -
Transco’s Motion for Partial Summary Judgment and Motion for Preliminary
Injunction . . . .”).
Not so with Defendants in the above-styled actions. They try to block
Transco’s efforts to build the pipeline. But Congress and the FERC have given
Transco authority to condemn easements over Defendants’ l nd. There is no arguing
with that point, so partial summary judgment and a preliminary injunction are
warranted.
ARGUMENT
Defendants have opposed Transco’s Motions for Partial Summary Judgment
and Preliminary Injunction on five grounds: (1) Transco’s clearly admissible
evidence is allegedly inadmissible; (2) Transco’s evid nce allegedly fails to
sufficiently identify the easements it seeks; (3) Transco’s negotiations with
landowners were insufficient; (4) discovery is inexplicably needed as to whether the
property Transco seeks to acquire is authorized by the FERC Certificate; and (5)
contrary to the weight of authority, Transco has not made a sufficient showing to
merit a preliminary injunction. None of those arguments is persuasive.
A. Transco’s Evidence in Support of Partial Summary Judgment is Clearly
Admissible.
Defendants attack the admissibility of Transco’s evid nce in support of its
Motion for Partial Summary Judgment, arguing that Transco’s FERC Certificate is
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 3 of 16
- 4 -
not authenticated under Federal Rule of Evidence 901 and that Transco’s 28 U.S.C.
§ 1746 declarants rely in part on business records in their declarations. Neither
argument has merit. Transco’s FERC Certificate, an order of the federal government
available on FERC’s website (and even through a simple Westlaw search),2 is clearly
self-authenticating. See Fed. R. Evid. 902(1), (5); Rizo v. Yovino, No. 1:14-CV-
0423-MJS, 2015 WL 9260587, at *5 (E.D. Cal. Dec. 18, 2015) (“Federal courts
routinely consider records from government websites to be self-authenticating.”);
Williams v. Long, 585 F. Supp. 2d 679, 689 (D. Md. 2008) (a printed w bpage from
a government website is self-authenticating). And declarants in support of summary
judgment motions may rely on business records; and that reliance constitutes
personal knowledge for purposes of Rule 56(c)(4). Stanley v. Kansas Counselors of
Kansas City, 639 F. App’x 589, 590 (11th Cir. 2016) (district court properly relied
on affidavit based on personal knowledge and review of business records in granting
summary judgment); Colonial Pac. Leasing Corp. v. N & N Partners, LLC, 981 F.
Supp. 2d 1345, 1355 (N.D. Ga. 2013) (“Affiants can h ve personal knowledge for
purposes of Rule 56(c)(4) based on their review of business records and files . . . .
2 Transcon. Gas Pipe Line Co., LLC, Docket No. CP15-117, 156 FERC ¶ 61,092
(August 3, 2016). The FERC Certificate is available at 2016 WL 4198689 and
through FERC’s website at
http://elibrary.ferc.gov/idmws/file_list.asp?document_id=14482654.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 4 of 16
- 5 -
This is because what affiants must have personal knowledge of is admissible facts.
See Fed. R. Civ. P. 56(c)(4). And business records or files are admissible under a
number of the Federal Rules of Evidence. E.g., Fed. R. Evid. 803(6).”).
B. Transco Sufficiently Identified the Easement Interests to be
Condemned.
Defendants also argue that Transco failed to identify the easement interests to
be condemned under Fed. R. Civ. P. 71.1 because the scope of the easement terms
sought by Transco allegedly exceeds the scope of its power under the FERC
Certificate and the Natural Gas Act. Even if Defenda ts were right, that would not
preclude partial summary judgment on Transco’s power to condemn.
The Parties agree that Transco’s condemnation authority is conclusively
determined by the terms of the Certificate. For that reason, Transco submitted
evidence in its Motion for Partial Summary Judgment that the “location of the
easements sought to be acquired by Transco on [Defendant’s property] substantially
conform to the alignment sheets submitted to FERC that depict the route approved
and deemed necessary by FERC.” [Declaration of David T. Wells, Exhibit B to
Motion for Partial Summary Judgment, ¶ 12].3 Defendants do not dispute that the
3 In each of the eight above-styled actions, Transco filed individual Exhibits C and
E to its Complaint, and Exhibit B to its Motion for Partial Summary Judgment (the
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 5 of 16
- 6 -
location of the easement interests depicted in Transco’s partial summary judgment
filings conform with the pipeline route as approved by the FERC. Instead, their
criticisms are aimed at the proposed Easement Terms attached to Transco’s
Complaint as Exhibit E.
Transco’s proposed Easement Terms are consistent with the scope of the
FERC Certificate, but this Court need not decide that issue to decide Transco’s
Motion for Partial Summary Judgment. Sabal Trail Transmission, LLC, No. 4:16-
CV-102, 2016 WL 3248367, at *3 (M.D. Ga. June 10, 216) (“This issue does not
preclude partial summary judgment on [the pipeline company’s] right to condemn;
at this stage in the litigation, the Court need not draft the final easement terms to be
recorded as a Grant of Easement. The Court will address this issue when it takes up
the compensation issue.”); Williston Basin Interstate Pipeline Co. v. Dolyniuk
Family Trust, No. A1-03-66, 2005 WL 1398692, at *4 (D.N.D. June 7, 2005) (“The
Court finds that the issue of pipeline capacity is an issue of compensation rather than
a limitation on the terms of the easement . . . Thus, the impact of the potential for
future expansion is a factor for the jury to consider in reaching a damage
determination.”).
Declaration of David T. Wells). References thereto apply to each action unless
otherwise noted.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 6 of 16
- 7 -
In either case, the plats and descriptions Transco submitted in connection with
its Motions for Partial Summary Judgment sufficiently identify the easements
interests sought. See Nat. Gas Co. v. Land, Cullman Cty., 197 F.3d 1368, 1375 (11th
Cir. 1999) (“Southern’s complaint for condemnation easily satisfied [Rule
71A(c)(2)’s] requirement by incorporating both a legal description and a plat map
showing the placement of the pipeline and relevant easements.”); Sabal Trail
Transmission, LLC v. 7.72 Acres in Lee Cty., Alabama, No. 3:16-CV-173-WKW,
2016 WL 3450827, at *3 (M.D. Ala. June 20, 2016) (A Certificate holder “is not
required to conduct a full survey with a metes and bounds description and plat drawn
by a registered land surveyor showing the property to be taken for purposes of
ordering condemnation.”).
The evidence is undisputed that Transco’s FERC Certificate gives it the
authority to condemn the easement interests depicted in Exhibit C to its Complaints
and Exhibit 2 to the Declarations of David T. Wells in support of Transco’s Motion
for Partial Summary Judgment: none of the opposing Defendants here have
submitted any evidence that Transco does not have the right to condemn those
easement interests depicted in Exhibit C to its Complaints. Because the Court need
not decide the terms of the easements to be condemned by Transco at this time, this
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 7 of 16
- 8 -
issue does not preclude granting Transco partial summary judgment on the issue of
whether Transco has the substantive power to condem.
C. Transco Satisfied 15 U.S.C. 717f(h) Because it Atempted to, and Could
Not, Acquire the Necessary Easements by Contract.
Defendants contend that Transco did not comply with 15 U.S.C. 717f(h)
because it did not attempt to acquire the easement rights by contract. That is so,
Defendants contend, because the terms of Transco’s easements during negotiations
varied from those that Transco attached to its Complaint as Exhibit E. Nothing in
that statute, however, requires Transco to offer specific easement terms to each
landowner before filing condemnation actions. Instead, the Natural Gas Act simply
provides that a holder of a FERC Certificate may file an eminent domain action if it
“cannot acquire by contract, or is unable to agree with the owner of property to the
compensation to be paid for, the necessary right-of-way to construct, operate, and
maintain a pipe line or pipe lines for the transportation of natural gas.” 15 U.S.C.
§ 717f. Transco satisfied that statute here by offering to purchase the easement rights
depicted in Exhibit C to its Complaints, and then by seeking to condemn those rights.
An investigation into the specific easement terms offered to each landowner
and attached to the permanent and temporary easements shown in Exhibit C is not
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 8 of 16
- 9 -
necessary and would not serve the interests of judicial efficiency. As a fellow district
court found,
[t]he Landowners suggest that the court must resolv these factual
disputes and determine whether Guardian has negotiated with each of
them in good faith before Guardian’s authority to condemn the portion
of their land needed for its easements can be confirmed. But to do so
would require the court to conduct a series of mini-trials over who said
what to whom and whether Guardian had a reasonable basis for the
amount it offered each Landowner. Obviously, such a requirement
could delay the project indefinitely. And to what end?
Guardian Pipeline, L.L.C. v. 295.49 Acres of Land, No. 08-C-0028, 2008 WL
1751358, at *17 (E.D. Wis. Apr. 11, 2008) (subsequent history omitted); see also
Sabal Trail Transmission, LLC, 2016 WL 3248367, at *3 (“[A]t this stage in the
litigation, the Court need not draft the final easement terms to be recorded as a Grant
of Easement.”).
D. Transco is Entitled to a Preliminary Injunction for Immediate
Possession.
Defendants oppose Transco’s Motion for Preliminary Injunction on certain of
the same grounds that they oppose its Motion for Partial Summary Judgment: that
Transco did not attempt to acquire certain easement rights sought to be condemned
by contract, and that Transco’s proposed Easement Terms allegedly do not comply
with the FERC Order. Transco incorporates its above arguments concerning those
issues.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 9 of 16
- 10 -
Defendants also argue that Transco’s harm is purely economic, allegedly
caused by its own actions, and a disruption of the s atus quo.4 That argument fails.
The Dalton Expansion is needed to meet the energy needs of roughly 2 million
homes and to prevent severe financial losses to Transco. Transco has no legal
remedy whatsoever to later recover those losses from Defendants. That alone would
suffice to meet Transco’s burden to show irreparable harm. See, e.g. Nw. Pipeline
Corp. v. The 20' x 1,430' Pipeline Right of Way Easement, 197 F. Supp. 2d 1241,
1246 (E.D. Wash. 2002) (granting preliminary injunction where pipeline showed
that it faced economic harm and that immediate possession was in the public
interest); Northern Border Pipeline Co. v. 127.79 Acres of Land, 520 F. Supp. 170,
172 (D.N.D. 1981) (holding that plaintiff would suffer economic harm from delay
and that national interest supported immediate possession); USG Pipeline Co. v. 1.74
Acres in Marion Cty., Tenn., 1 F. Supp. 2d 816, 825-26 (E.D. Tenn. 1998) (granting
4 Courts have granted preliminary injunctive relief in the Natural Gas Act context
over landowners’ objections that such a grant runs contrary to the status quo. See,
e.g., Tenn. Gas Pipeline v. 0.018 Acres of Land, No. 2:10-cv-4465-JLL (D.N.J.
Sept. 28, 2010) (granting preliminary injunction, noti g that “[f]or actions pursuant
to the Natural Gas Act where an order of condemnatio has issued [i.e., the court
has determined that a gas company has the substantive right to condemn property],
the question is not whether the status quo will change, but merely when-it is simply
an issue of timing.”).
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 10 of 16
- 11 -
immediate possession when pipeline company risked substantial financial losses and
potential job creation by plant reliant on gas linewould be delayed).
But Transco’s harm is not the only reason to grant injunctive relief here: not
only will Transco suffer immediate and irreparable harm to its reputation, goodwill,
and financial interests in the absence of a preliminary injunction, but its customers
and the public will also suffer if pipeline construction does not immediately begin.
The Dalton Expansion’s primary customers, two local gas distribution companies,
would be disserved by further delay. [See Exhibits 1 and 2 to the Declaration of
James Mathis, Exhibit A to Motion for Preliminary Injunction]. Landowner’s
purported harm can be addressed through a bond posted by Transco at the Court’s
direction. And most importantly, the public would be disserved by further delay
because its access to an additional supply of natural gas deemed in the public interest
by the federal government will be further delayed.
The weight of authority demonstrates that under facts similar to those here, a
pipeline company is entitled to a Preliminary Injunction granting it immediate
possession to the easements to-be-condemned. Sabal Trail Transmission, LLC,
2016 WL 3248367, at *5 (finding on June 10, 2016 that in a case with the same in-
service date as Transco’s here – May 1, 2017 – the “evidence [was] sufficient to
establish that [the pipeline company] will suffer irreparable harm if it is not granted
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 11 of 16
- 12 -
immediate possession of the easements.”); Gulf Crossing Pipeline Co. LLC v. 86.36
Acres of Land, More or Less, [], No. CIV.A. 08-689, 2008 WL 2465892, at *6 (W.D.
La. June 18, 2008) (collecting cases); Rockies Exp. Pipeline, LLC v. 4.895 Acres of
Land, No. 2:08-CV-554, 2008 WL 4758688, at *3 (S.D. Ohio Oct. 27, 2008) (even
though some of the Plaintiff’s harm was “self-inflicted,” granting immediate
possession of property).
E. No Discovery is Necessary to Issue a Limited Ruling on Transco’s
Motions for Partial Summary Judgment and Preliminary Injunction.
Transco’s Motions for Partial Summary Judgment and Preliminary Injunction
ultimately require two limited and uncontested determinations by the Court: (1)
Transco has authority to exercise eminent domain as a matter of law, which involves
no genuine issue of material fact; and (2) Transco and the public will face substantial
harm absent an injunction for immediate possession. O these issues, there is no
need for discovery. Indeed, in numerous eminent domain actions under the Natural
Gas Act, preliminary injunctions and motions for summary judgment that seek the
exact same relief Transco seeks here are routinely granted without discovery. See,
e.g., Alliance Pipeline, LP v. 4.360 Acres, 746 F.3d 362, 364-65 (8th Cir. 2014); E.
Tenn. Natural Gas Co. v. Sage, 361 F.3d 808, 828 (4th Cir. 2004); Columbia Gas
Trans., LLC, v. 1.092 Acres, No. 15-208, et al., 2015 WL 389402, at *2 n.5 (D.N.J.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 12 of 16
- 13 -
Jan. 28, 2015); Constitution Pipeline Co., LLC v. A Permanent Easement for 1.80
Acres and Temporary Easement for 2.09 Acres in Davenport, Delaware Cty., New
York, Tax Parcel Number 24.-1-41, No. 3:14-CV-2049 (NAM/RFT), 2015 WL
1638250 at *4 n.2 (N.D.N.Y. Feb. 23, 2015). The evid nce submitted by Transco
in each of these actions unambiguously demonstrates that the easement rights it
seeks were submitted to and approved by FERC. Discovery apparently sought by
Defendants “as to whether the property [Transco] seek to acquire was authorized
by the August 3, 2016 FERC Order” is wholly unnecessary.5
F. Transco Will Post a Bond in Accordance with the Court’s Direction.
Finally, Defendants argue that they are due just and adequate compensation
for Transco’s taking of an easement on their land. Transco agrees, and will post a
bond as directed by the Court.
5 In each of the above-styled actions, Transco has submitted a complete copy of
property-specific alignment sheet(s) submitted to FERC [Motion for Partial
Summary Judgment, Declaration of David T. Wells, Exhibit 1], the FERC
Certificate approving those alignment sheets [Complaint, Exhibit D], and a drawing,
survey plat, and/or written description sufficient to identify the easement rights
sought [Complaint, Exhibit C]. Those documents alone suffice to show that Transco
has the power to condemn the easements depicted in Exh bit C.
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 13 of 16
- 14 -
CONCLUSION
Transco respectfully respects that this Court grant its Motions for Partial
Summary Judgment and Preliminary Injunction.
Dated: October 11, 2016.
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff
Transcontinental Gas Pipe Line Company,
LLC
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 14 of 16
- 15 -
CERTIFICATE OF COMPLIANCE
Pursuant to LR 5.1C and 7.1, NDGa, I hereby certify that certify this
document has been prepared with Times New Roman 14-point font.
Dated: October 11, 2016.
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff
Transcontinental Gas Pipe Line Company,
LLC
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 15 of 16
- 16 -
CERTIFICATE OF SERVICE
I hereby certify that on October 11, 2016 I electronically filed the foregoing
FIRST CONSOLIDATED REPLY IN SUPPORT OF TRANSCO’S MOTIONS
FOR PARTIAL SUMMARY JUDGMENT AND PRELIMINARY INJUNCTION
with the Clerk of Court using the CM/ECF system, which will automatically send
email notification of such filing to any filing users who may have entered an
appearance in this action.
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff Transcontinental Gas
Pipe Line Company, LLC
Case 1:16-cv-03228-ELR Document 23 Filed 10/11/16 Page 16 of 16
UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF GEORGIA
ATLANTA DIVISION
IN RE TRANSCONTINENTAL GAS PIPE
LINE COMPANY, LLC
Individual File:
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
v.
6.84 acres, more or less, over parcel(s) of
land
of approximately 124.8 acres, more or less,
situated in Land Lots 452, 453, 454 and 485,
Seventeenth (17th) District, Third (3rd)
Section of Bartow County, Georgia and more
particularly described herein;
and
Thomas & Thomas, LLP,
Defendants.
_____________________________________
LEAD FILE NO.
1:16-CV-02991-ELR
INDIVIDUAL FILE NOS.
1:16-CV-03228-ELR
PLAINTIFF’S RESPONSE TO DEFENDANT’S STATEMENTS OF
MATERIAL FACTS IN SUPPORT OF RESPONSE IN OPPOSITION TO
PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 1 of 8
- 2 -
Pursuant to LR 56.1(B)(3), Transcontinental Gas Pipe Line Company, LLC
(“Transco”) files this Response to Defendant Thomas & Thomas, LLP’s
(“Defendant”) Statement of Additional Material Facts Presenting Issues for Trial
[Dkt. 22].
RESPONSE TO DEFENDANT’S STATEMENT
1. Plaintiff's ability to exercise the power of eminent domain under the Natural
Gas Act and Rule 71.1 is dependent upon the contents of the FERC
Certificate. The Document attached to Plaintiff's Complaint as Exhibit "D" is
hearsay and is not properly authenticated. The actual contents of the FERC
Certificate remain to be proven. (Complaint at Exhibit "D").
RESPONSE: Transco responds that this statement is a legal conclusion.
Transco further disputes this fact because the FERC Certificate is a self-
authenticating document.
2. Assuming, for the sake of argument that the document attached to Plaintiff's
Complaint as Exhibit "D" is a copy of the FERC Certificate, it references
Plaintiff's application, supplemental filings, and the Environmental
Assessment, as further documents governing the Defendant's ability to
exercise the right of eminent domain. These other documents are not
attached to the Complaint, nor provided by Plaintiff in support of its Motion
for Partial Summary Judgment. (Complaint, Exhibit "D," Doc. 1-4 at p. 40
of 52; Exhibit "D" at Appendix "C," Doc. 1-4 at p. 44 of 52). The contents of
these documents are material and remain to be proven.
RESPONSE: Transco responds that this statement is immaterial to a
determination of Transco’s Motion for Partial Summary Judgment. Transco has
submitted evidence sufficient to show it possesses the power of eminent domain
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 2 of 8
- 3 -
over Defendant’s property, and need not submit (and serve each landowner) with
the entire FERC docket in order to make that showing.
3. The actual easements approved by FERC to be taken, as set forth on
Alignment Sheets approved by FERC are material and remain to be proven.
The Declaration of Mr. David T. Wells is insufficient to establish that the
Documents attached to his Declaration have been approved by FERC, as the
statement lacks foundation, and is hearsay. (Plaintiff's Motion for Partial
Summary Judgment at Exhibit "B," Wells Declaration; Doc. 4-5, ¶¶ 6-7;
Doc. 4-6).
RESPONSE: Transco responds that this statement is a legal conclusion.
Transco further responds that the cited evidence is sufficient to establish that
Transco possesses the power of eminent domain over Defendant’s property.
4. Whether the Survey Plats attached to the Complaint reflect the actual path
for the pipeline that has been authorized by FERC is material and remains
unproven. The Declaration of Mr. David T. Wells is insufficient to establish
that the Documents attached to his Declaration have been approved by
FERC, as the statement refers to documents prepared by a survey expert, and
Wells has failed to establish a foundation for his statement. Furthermore, the
documents attached are hearsay. (Wells Declaration; Doc. 4-5, ¶¶ 8-9; Doc.
4-7).
RESPONSE: Transco responds that this statement is a legal conclusion.
Transco further responds that the cited evidence is sufficient to establish that
Transco possesses the power of eminent domain over Defendant’s property.
5. Whether the easements set forth in Exhibit "E" to Plaintiff's Complaint are
necessary is material to this action, and remains to be proven. August
Nicolaus declares inconsistently, stating first that the easements set forth in
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 3 of 8
- 4 -
the Final Offer Letter are necessary to complete the pipeline, and then
stating that the easements set forth in the Complaint are necessary.
(Plaintiff's Motion for Partial Summary Judgment at Exhibit "A," Nicolaus
Declaration, Doc. 4-3 at ¶¶ 14 and 15; Exhibit "1" thereto, Doc. 4-4).
RESPONSE: Transco responds that the final easement terms applicable to
the easements condemned by Transco need not be determined in order to decide
Transco’s Motion for Partial Summary Judgment. Transco further responds that
the Federal Energy Regulatory Commission has determined the necessary
easements for Transco’s pipeline project and that Defendant cannot attack that
determination in this Court.
6. Whether Plaintiff was unable to acquire the "necessary right of way" by
contract from Defendant is material, and remains to be proven. The
easement sought to be acquired in Plaintiff's Final Offer Letter varies in
terms from the "Easement Terms" Plaintiff's set forth in Exhibit "E" to
Plaintiff's Complaint, and reflect an attempt to acquire unnecessary right of
way from Defendant. (Complaint, Exhibit "E," Doc. 1-5; Nicolaus
Declaration, Doc. 4-3 at ¶ 14; Exhibit "A" thereto, Doc. 4-4, p. 8 and 9 of
17). Plaintiff has not made an offer to acquire by contract the easement set
forth in Exhibit "E" of Plaintiff's Complaint.
RESPONSE: Transco responds that the final easement terms applicable to
the easements condemned by Transco need not be determined in order to decide
Transco’s Motion for Partial Summary Judgment. Transco further responds that
the Federal Energy Regulatory Commission has determined the necessary
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 4 of 8
- 5 -
easements for Transco’s pipeline project and that Defendant cannot attack that
determination in this Court.
7. Whether the easements identified in Plaintiff's Complaint are so vague that
they do not sufficiently identify the property to be taken is material and
remains to be proven. (Complaint, Exhibit "E").
RESPONSE: Transco responds that the final easement terms applicable to
the easements condemned by Transco need not be determined in order to decide
Transco’s Motion for Partial Summary Judgment. Transco further responds that
the depiction attached to Transco’s Complaint as Exhibit C clearly identifies the
property sought to be condemned in this action.
8. Due to Plaintiff serving Defendant with its Motion for Partial Summary
Judgment at the same time it served its Complaint, Defendant has not had
the opportunity to adequately research the material issues set forth herein,
nor to conduct discovery in this action. For that reason, Defendant is not able
at this time to provide sufficient further facts in opposition to Plaintiff's
Motion for Partial Summary Judgment. (Declaration of Michael P. Bain,
Esq., Exhibit "A" hereto).
RESPONSE: Transco admits it served Defendant with Transco’s Motion
for Partial Summary Judgment at the same time it served its Complaint, but
responds that Defendant has had sufficient time to determine that Transco
possesses the power of eminent domain over Defendant’s property.
Dated: October 11, 2016.
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 5 of 8
- 6 -
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff
Transcontinental Gas Pipe Line Company,
LLC
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 6 of 8
- 7 -
CERTIFICATE OF COMPLIANCE
Pursuant to LR 5.1C and 7.1, NDGa, I hereby certify that certify this
document has been prepared with Times New Roman 14-point font.
Dated: October 11, 2016.
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff
Transcontinental Gas Pipe Line Company,
LLC
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 7 of 8
- 8 -
CERTIFICATE OF SERVICE
I hereby certify that on October 11, 2016 I electronically filed the foregoing
PLAINTIFF’S RESPONSE TO DEFENDANT’S STATEMENTS OF
MATERIAL FACTS IN SUPPORT OF RESPONSE IN OPPOSITION TO
PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT with the
Clerk of Court using the CM/ECF system, which will automatically send email
notification of such filing to any filing users who may have entered an appearance
in this action.
By: /s/ Nowell D. Berreth
ALSTON & BIRD LLP
One Atlantic Center
1201 West Peachtree St NW
Suite 4200
Atlanta, GA 30309
Telephone: 404-881-7000
Facsimile: 404-881-7777
Nowell D. Berreth
Georgia Bar No. 055099
W. Clay Massey
Georgia Bar No. 476133
Counsel for Plaintiff Transcontinental Gas
Pipe Line Company, LLC
Case 1:16-cv-03228-ELR Document 23-1 Filed 10/11/16 Page 8 of 8