Plumbers and Steamfitters Local 342Download PDFNational Labor Relations Board - Board DecisionsSep 17, 1976225 N.L.R.B. 1364 (N.L.R.B. 1976) Copy Citation 1364 DECISIONS OF NATIONAL LABOR RELATIONS BOARD Plumbers and Steamfitters Local Union 342, United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada, AFL-CIO and Conduit Fabri- cators, Inc. Plumbers and Steamfitters Local Union 342, United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada , AFL-CIO and Conduit Fabri- cators Inc. and C. Overaa & Co., Party to the Con- tract . Cases 20-CC- 1518 and 20-CE- 109 September 17, 1976 DECISION AND ORDER BY CHAIRMAN MURPHY AND MEMBERS FANNING AND JENKINS On August 7, 1975,' Administrative Law Judge Richard J. Boyce issued the attached Decision in this proceeding. Thereafter, the Respondent and Charg- ing Party 2 filed exceptions and supporting briefs, and the General Counsel filed a brief to answer the Respondent's exceptions and to support the Decision of the Administrative Law Judge. Pursuant to the provisions of Section 3(b) of the National Labor Relations Act, as amended, the Na- tional Labor Relations Board has delegated its au- thority in this proceeding to a three-member panel. The Board has considered the record and the at- tached Decision in light of the exceptions and briefs and has decided to affirm the rulings, findings, and conclusions of the Administrative Law Judge, as modified below, and to adopt his recommended Or- der. We agree with the conclusion of the Administra- tive Law Judge that the Respondent (herein Steam- fitters) violated Section 8(e) and 8(b)(4)(ii)(B) of the Act by causing C. Overaa & Co. (herein Overaa) em- ployees to refuse to install certain pipe, which was prefabricated by Conduit, at the Moraga Pumping Plant project. However, we do not agree with the Administrative Law Judge that the "right-to-control" test is dispositive of the present issues, and therefore i All dates herein are 1974 unless otherwise specified 2 By letter dated October 8, 1975, the Charging Party withdrew its excep- tions to the Administrative Law Judge's Decision Also, by letter dated February 13, 1976, the Charging Party requested that the charge be with- drawn and all action on the case canceled The General Counsel and the Respondent filed separate oppositions to this request In our judgment it would not effectuate the purposes of the Act to permit the charges to be withdrawn at this late stage of the proceeding, nor could further action on the case be properly canceled when Respondent's exceptions are still before us Accordingly, the Charging Party's request that the charges he withdrawn and that all action on the case be canceled is hereby denied we rely on other grounds for finding the violations of the Act. The Administrative Law Judge concluded that the right-to-control test was applicable because Overaa had entered into a subcontract with Conduit for the fabrication of the pipe, thereby relinquishing its right to control the work involved. The Administrative Law Judge reasoned that by virtue of the subcontract Overaa was powerless to accede to Respondent's work claims; therefore, Overaa was a neutral em- ployer and Respondent's pressure against Overaa was secondary. We find that the Administrative Law Judge has misconstrued the right-to-control doctrine and, moreover, that this doctrine is inapposite to de- ciding the issues at hand.' Overaa, pressured by the Steamfitters refusal to in- stall the pipe, is not a neutral employer within the rubric of a right-to-control test because it possessed the authority to assign the fabrication of the pipe in question as it saw fit. In other words, Overaa was not bound by its contract with East Bay Municipal Utili- ties District (herein East Bay MUD), which financed the Moraga project, to assign the work to a specific subcontractor. Thus, Overaa's own act of subcon- tracting the fabrication work at issue did not divest Overaa of its control over the work; in fact, subcon- tracting the fabrication work at issue was a direct reflection of Overaa's right to control this work.4 Rather, we find that the Steamfitters did not have a valid claim to the work involved. Before we discuss the basis for this finding that the Steamfitters could not fairly claim the work, a review of the background events will be helpful. The Moraga Pumping Plant project is typical of many such plants commissioned by the East Bay MUD, which operates in the San Francisco, California, area. Overaa, one of several general contractors in the San Francisco Bay area, was the successful bidder on the Moraga project and was awarded the contract to construct the plant in accordance with MUD specifications. Overaa and the Steamfitters were signatory to a collective-bar- gaining agreement, extended by an interim agree- ment, which is identical to the basic labor agreement covering the craftwork of the United Association of Plumbers and Pipefitters (U.A.), with which the Steamfitters is affiliated. Overaa employed three members of the United Association for onsite pipe- fitting work.' J We note that the General Counsel also argued that the right-to-control test was at issue For the same reasons discussed above, we reject this con- tention of the General Counsel Cf Local Union No 438, United Association of Journeymen and Appren- tices of the Plumbing and Pipefitting Industry of the United States and Canada, AFL-CIO (George Koch Sons, Inc), 201 NLRB 59 (1973), enfd 490 F 2d 323 (C A 4, 1973) 5 When the Moraga project began, Local 159 of the Plumebers, another United Association affiliate had jurisdiction over the work However, as of 225 NLRB No. 195 PLUMBERS & STEAMFITTERS LOCAL 342 Overaa was required by MUD specifications to in- stall cement-lined and lead-paint-coated pipe, as well as vinyl-lined pump barrels, in the Moraga Plant.' According to the specifications, the pipe also had to be hydrostatically tested and stress-relieved upon the completion of certain stages of the fabrication.' Ove- raa subcontracted the fabrication of the pipe to Con- duit Fabricators, Inc., which is one of several fabri- cators in the San Francisco area engaged in this type of work. Conduit has a collective-bargaining agree- ment with Teamsters Local 490; thus, none of its em- ployees is represented by the Steamfitters or any other affiliate of the United Association. Conduit de- livered the completed pipe to the construction site in February 1974. It is undisputed that on July 15, the Steamfitters refused to handle and install the pipe from Conduit.' Three days later, the Steamfitters business manager directed the onsite employees to handle the pipe, but he informed Overaa that the Steamfitters would file a grievance. While the record does not indicate that the Steamfitters made a clear demand for the fabri- cation work, the Administrative Law Judge found that at the time of the hearing it claimed the work of cutting and welding the pipe.' It is well settled that Section 8(e) does not pro- scribe contact provisions which accomplish primary activity. Thus, it is not a violation of the Act for a contractual provision to preserve bargaining unit work from diminution as a result of technological changes 10 or to reclaim for the unit previously per- formed work or work which is otherwise "fairly claimable." 11 We are guided by the Board's decision July 15, 1974, Local 342 of the Steamfitters acquired jurisdiction over the project Charles Burgin , the onsite foreman , belonged to the Steamfitters, the two other onsite employees who were hired for pipe installation were members of Local 159 6 The pipe ranged from 17 inches to 72 inches in diameter with a mini- mum 1/2-inch thickness , individual lengths of the pipe weighed as much as 15 tons 7 The Administrative Law Judge has described the fabrication process of pipe in his Decision While the term " fabrication" was used as a term of art by the Steamfitters to mean the cutting and welding of the steel pipe, the record indicates that this is but one stage in the process of fabricating-or manufacturing-the type of pipe at issue 8 Previously , on or about June 4 , the business agent for Local 159 in- formed Overaa 's job superintendent that Conduit's pipe was "unsuitable" for handling Apparently Overaa delayed the pipe 's installation for several weeks , but by July 15 Overaa faced shutting down the entire project if the pi;e could not be installed When the grievance procedure was initiated , the Steamfitters asserted that Overaa "purchased fabrications to be installed by our members without the Union label ," and therefore Overaa had violated contractual provisions covering the manner in which pipe is to be fabricated 10 National Woodwork, supra 1 Retail Clerks Union Local 770, chartered by Retail Clerks International Association (Hughes Markets , Inc, and Saba Prescription Pharmacy), 218 NLRB 680 ( 1975), Local Union No 282, affiliated with the International Brotherhood of Teamsters, Chauffeurs, Warehousemen and Helpers of America (D Fortunato, Inc), 197 NLRB 673 ( 1972), Meat and Highway Drivers, Dockmen , Helpers and Miscellaneous Truck Terminal Employees, Local Union No 710, International Brotherhood of Teamsters, Chauffeurs, Warehousemen 1365 in Sheet Metal Workers Union, Local 162, Sheet Met- al Workers' International Association , AFL-CIO (As- sociated Pipe and Fittings Manufacturers), 12 which adopted decision of the Administrative Law Judge finding that contractual provisions proscribing the prefabrication of certain items, including round pipes, violated Section 8(e) of the Act. There, the Ad- ministrative Law Judge properly questioned whether it was the customary and traditional practice to pur- chase such pipes or fabricate them onsite. He further determined that The issue before us is not whether contractors are capable of fabricating round pipe or fittings, or whether facilities exist whereby this can be done on a reasonably efficient basis with ad- quate machinery and at a relatively small in- crease in cost. The legality of the contract re- strictions turns not on the capacities of the unit employers or employees to do the work, but on whether or not in fact work of this nature has customarily and traditionally been done by such unit employees. These cases establish that only where it is shown that the unit employees have done such fabrication with sufficient regularity to support a conclusion that such fabrication is industry custom and tradition, can it be found that a union is entitled to claim or recapture such work by use of contract restrictions. [207 NLRB at 749.] t3 The problem raised by the Steamfitters claim is that obviously its members are capable of performing the work, with proper tools and equipment. Thus, the and Helpers of America [Wilson & Co ] v N L R B, 335 F 2d 709 (C A D C, 1964) 12207 NLRB 741 (1973) 13 See also Sheet Metal Workers Union, Local 216, Sheet Metal Workers' international Association (Associated Pipe and Fitting Manufacturers), 172 NLRB 35 (1968) (Board adopted decision of Administrative Law Judge which stated that "whether employees have customarily and traditionally performed such work means that employers in the common course of business regularly assign such tasks to its employees "), Local Union No 26 of Sheet Metal Workers' International Association , AFL-CIO (Reno Employ- ers Council), 168 NLRB 893 (1967) (Board adopted decision of Administra- tive Law Judge which found that "while unit employees may have sufficient skills to fabricate [ at least some of the items ], it is significant that they have never been called upon to do so except on rare and sporadic occasions, and then only to meet unusual and emergency situations Prohibitive costs ren- der any other mode of operation impractical "), and Southern California Pipe Trades District Council No 16 of the United Association and Plumbing- Heating and Piping Employers Council of Southern California (Seefore Corpo- ration), 193 NLRB 796 ( 1971) (Board adopted decision of Administrative Law Judge which found that certain clauses banning prefabricated items violated Sec 8(e) of the Act , after noting, inter alias , that the members of the employers council regularly purchased the prefabricated item, and that the employers had not manufactured or fabricated the items in their shops or at the jobsite In addition , the Administrative Law Judge reasoned that "we are not treating merely the installation of pipe or its fabrication ," but that "the fabrication of the pipe is but one step in the preparation of the total product ") Cf Local 636, United Association of Journeyman and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada, AFL-CIO (Mechanical Contractors Association of Detroit, Inc ), 189 NLRB 661 (1971) 1366 DECISIONS OF NATIONAL LABOR RELATIONS BOARD ability of the employees to perform such work, which involves the very expertise possessed by this craft, is not at issue . The crucial question is whether or not the Steamfitters claim seeks to preserve "traditionally performed" work or seeks to acquire "fairly claim- able" work. The substantial evidence on the record as a whole discloses that the fabrication of cement-lined and coated pipe, including the cutting and the welding, is subcontracted to companies specializing in fabrica- tion of such pipes because general contractors do not have, as a matter of course, the capability or capacity for onsite fabrication of pipe, of which the cutting and welding is one stage .14 Moreover, the record evi- dence on the whole indicates that neither Overaa nor other contractors engaged in similar work regularly assign such fabrication work to their own employ- ees.15 The Administrative Law Judge found that "there has not been a single instance, involving a MUD project comparable to the present [Moraga plant], when any phase of the fabrication has occurred on site." Jack Freethy, general manager of the Elmer J. Freethy Company, testified that his company is a general contractor involved primarily in the con- struction of water sewage and treatment facilities for various municipal and utilities districts. They do most of their work for East Bay MUD and have con- structed plants similar to the one at Moraga. Freethy testified that the company never fabricates its own pipes but obtains such pipe from fabricating compa- nies such as Conduit or Ameron. Freethy Company, through its employers' council, Plumbing, Heating and Cooling Contractors Association of Northern California, has an agreement with the Steamfitters. William Gaffney, manager of Underground Con- struction, also a utility general contractor, testified that when they utilize lined pipe, such as that re- quired by MUD at Moraga, they never fabricate the 14 Overaa does not have a fabrication shop One witness for the Steamfit- ters speculated that it could be possible to erect a shop for fabrication, but this testimony revealed that Overaa would incur exorbitant costs and exten- sive time delays to do so, and that it was highly uncertain if such a shop could be erected in view of the limited available space at the Moraga site 15 Counsel for the Steamfitters has cited the fact that one general contrac- tor, Scott Co , has assigned the cutting and welding of the pipe to his onsite employees Our review of the record reveals that this is not an accurate depiction of the situation The record indicates that Ameron Co , a major fabricating company which, like Conduit, is a Teamsters shop. originally received an order from Scott Co for a completely fabricated pipe package, similar to the one Conduit produces for Overaa However, after the dispute arose in the present case , Scott Co , faced with similar demands from anoth- er United Association affiliate, agreed to have the onsite employees do some welding Thus , the arrangement is for Ameron Co to fabricate (cut) the pipe and the various fittings , and tack weld the fittings onto the pipe , while onsite employees will finish the welding The pipe will then be shipped back to Ameron for lining and coating We note that this arrangement was made after the instant dispute arose and that it also does not meet the Steamfitters demands pipe but use the services of Conduit or Ameron. Gaffney also averred that their common practice for facilities commissioned by MUD is to purchase from Ameron a completed package, which includes the necessary cuttings and weldings. It was also noted that Underground Construction has a collective-bar- gaining agreement with the Steamfitters for pipe in- stallation. Charles H. Burgin, who testified on behalf of the Steamfitters and was once employed by Overaa as the pipefitters general foreman at Moraga, related his previous experience at the C. Norman Peterson Company, a general utility contractor which has its own extensive fabrication shop. Although Burgin tes- tified to the capabilities of the Peterson shop to fabri- cate such pipe, Burgin conceded that the Peterson shop utilized a coal tar epoxy lining for its pipes, which necessitates handling different from that re- quired by the mortar-lined pipe at Moraga. Burgin also acknowledged that there were certain fabrica- tions, such as crotchplates (reinforced areas ), which Peterson did not have the capacity to produce. In addition, the projects cited by Burgin as examples of onsite fabrication did not involve the same type of mortar-lined and coated pipe used at Moraga. For -example, the pipe at the Contra Costa project had a coal tar epoxy lining, was not stress-relieved, and was not constructed for MUD; and the pipe used for the Sacramento Sewage Treatment Plant was already lined when it arrived at the Peterson shop. It did not have to be stress-relieved, and it was much smaller in size than the pipe used at the Moraga Plant . Burgin also testified that on numerous occasions Peterson contracted with a company, such as Ameron, for a completely fabricated pipe package. He agreed that many factors, such as the diameter of the pipe, the type of lining, and stress-relieving, would affect the decision whether or not to fabricate a pipe onsite. Burgin finally agreed, after considering his own expe- rience, that more pipe is purchased as a completely fabricated package than is fabricated in a general contractor's shop. Charles Gosney, a witness for the Steamfitters who has worked for both Overaa and Peterson, testified that he was not familiar with any contractor who totally fabricated the type of cement-lined and coat- ed pipe used at the Moraga Plant . Gosney further testified that it was his experience that when a job utilizes cement-lined and coated pipe the pipe is pur- chased already fabricated, which involved all the ne- cesary cuttings, fixtures, major welding, and any stress-relieving or hydrostatic testing. The manager of employee relations for Ameron Co., Edward R. Abram, testified that Ameron Co., a fabricating company similar to Conduit, generally PLUMBERS & STEAMFITTERS LOCAL 342 supplies to most of the contractors in the Bay Area a completely "engineered" (fabricated) package, espe- cially when the pipe is to be lined and coated.16 Upon our review of the record on the whole, we conclude that the work claimed by the Steamfitters, even assuming it made a narrow and specific claim to cutting and welding the pipe, has not been tradi- tionally or historically performed by the unit employ- ees. Thus, the situation presented here is quite differ- ent from the one in National Woodwork, supra, where the union's sole objective was the protection of tradi- tional unit work. Here, even if it be assumed that the contractual provisions relied on by the Respondent had a work-preservation purpose and that the unit employees were fully capable of performing the work in issue , the fact remains that this work has tradi- tionally been performed by employees outside the unit and not by the unit employees themselves. In the circumstances presented here, Respondent's refusal to install the pipe prefabricated by Conduit must re- alistically be viewed as either an attempt to acquire work which had not previously been performed by the unit employees or as an attempt to force Overaa to subcontract the work to a fabricator whose em- ployees are represented by locals affiliated with the Respondent. Both objectives are clearly secondary in effect and unlawful under our Act because they ex- ceed the legitimate interests of the unit employees vis-a-vis their own employer and therefore must be viewed as being tactically calculated to satisfy union objectives elsewhere." In its brief to the Board, the Steamfitters apparent- ly argues that the relevant unit has been misper- ceived throughout the proceedings, and that "the unit , for the purposes of the work-preservation provi- sions of the agreement, is comprised of all employers signatory to the Master Agreement. Dixie Mining Co., 179 NLRB 479." While the Steamfitters did not specifically indicate what is the scope of that unit, its brief asserted that "Overaa became bound to assign the fabrication work on fabrications which it in- stalled to its own employees; that Overaa had the right to fabricate the necessary piping at the fob site, 16 The record contained additional testimony about the practices of other contractors and fabricators in the area , but we find that it is not especially relevant For example , America Bridge , a fabricator whose employees are represented by the Boilermakers, stress -relieved at the jobsite due to the massiveness of the pipe which was also neither lined nor coated , so that a stress-relieving process (heat-coils ) could be used which was different from that required for Moraga Albay Construction Company is involved in oil refinery work and it did not fabricate any coated or lined pipe M F Lau- ritzer , a mechanical contractor , also constructs oil refineries, and does not use cement -lined and coated pipe H K Ferguson , also a contractor for the construction of refineries , does not utilize the same pipes required at Mora- ga 7 International Longshoremen 's Association , AFL-CIO (Consolidated Ex- press, Inc), 221 NLRB 956 (1975), International Longshoremen's Association, Local 1248, AFL-CIO (US Naval Supply Center), 195 NLRB 273 (1972) 1367 in its own shop," or in a shop with comparable terms and conditions of employment. We note that the Steamfitters contentions as to the relevant unit are based on the work at issue. The Board, with court approval, has considered whether the contractual clauses, or their maintenance are "germane to the economic integrity of the principal work unit" and seek "to protect and preserve the work and standards [the union] has bargained for." 18 Our examination of the collective-bargaining agreement between the Steamfitters and Overaa re- veals that jobsite work is the target of the subcon- tracting and work-preservation provisions. (See art. II, sec. 11; art. III, sec. 15 and 16, of the collective- bargaining agreement.) Second, as discussed above, the record discloses that the work claimed by the Steamfitters is not work which is traditionally or cus- tomarily performed at the jobsite. Since we have al- ready determined that the subcontracting provision only applied to work which is to be performed at the jobsite, and such work is not involved, the Steamfit- ters right to protect its work standards is not at stake. Thus, the Steamfitters unit claims result in either ac- quiring work which has not been customarily per- formed by the unit on the job or in the contractors' shop, or effectively making the clauses at issue func- tion as union signatory clauses. Both results are pro- scribed by Section 8(e) of the Act. Therefore, we are not dissuaded from our conclusion that the Steamfit- ters actions were calculated to satisfy union objec- tives elsewhere. Accordingly, in agreement with the Administrative Law Judge, we find that the Respon- dent Steamfitters has violated Section 8(e) of the Act. We also find that the Steamfitters violated Section 8(b)(4)(n)(B) of the Act, because an objective of its conduct was that Overaa cease doing business with Conduit or any other similarly situated subcontrac- tor. Overaa could only have met the Steamfitters de- mands by terminating its contract with Conduit, changing its subcontracting policies, or causing Con- duit to change its practices. Where the Steamfitters did not act to protect a lawful primary objective, such conduct is proscribed by the Act.19 In view of our findings herein that the Steamfitters violated Section 8(e) and 8(b)(4)(ii)(B) of the Act, the remedy remains the same as found in the Decision of the Administrative Law Judge. Accordingly, we shall adopt the recommended Order of the Administrative Law Judge. 1 8 Orange Belt District Council o f Painters No 48. AFL-CIO, et a! [Cal- houn Drywall Co ] v NLRB , 328 F 2d 534, 538 (C A D C, 1964) 19 N L R B v Local 825, international Union of Operating Engineers, AFL-CIO [Burns and Roe, Inc ], 400 U S 297 (1971) 1368 DECISIONS OF NATIONAL LABOR RELATIONS BOARD ORDER Pursuant to Section 10(c) of the National Labor Relations Act, as amended , the National Labor Re- lations Board adopts as its Order the recommended Order of the Administrative Law Judge and hereby orders that the Respondent , Plumbers and Steamfit- ters Local Union 342, United Association of Jour- neymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada, AFL-CIO, its officers , agents and representatives, shall take the action set forth in the said recommend- ed Order. DECISION STATEMENT OF THE CASE RICHARD J. BOYCE, Administrative Law Judge: This con- solidated matter was heard before me in San Francisco, California, on February 25, 26, and 28 and April 29, 1975 The charge in Case 20-CC-1518 was filed on July 19, 1974, and amended August 19, by Conduit Fabricators, Inc. (herein called Conduit). The charge in Case 20-CE-109 was filed by Conduit on July 24, 1974. A consolidated complaint issued against Plumbers and Steamfitters Local Union 342, United Association of Journeymen and Ap- prentices of the Plumbing and Pipe Fitting Industry of the United States and Canada, AFL-CIO (herein called Re- spondent) on August 23 Respondent thereafter entered into an agreement in at- tempted settlement of the issues raised by the complaint, which agreement was approved by the Regional Director for Region 20 on October 10. Conduit did not join in that agreement, instead appealing the Regional Director's ap- proval of it The appeal was sustained by the General Counsel; and, on December 19, the Regional Director withdrew approval of the settlement agreement and issued a new consolidated complaint. This complaint was amend- ed January 20, 1975, and alleges violations by Respondent of Section 8(b)(4)(n)(B) and 8(e) of the National Labor Relations Act The parties were given opportunity at the hearing to in- troduce relevant evidence, examine and cross-examine wit- nesses, and argue orally. Briefs were filed for the General Counsel and Respondent. 1. ISSUES The issues are whether Respondent's conduct vis-a-vis C. Overaa & Co. (herein called Overaa) during the construc- tion in 1974 of the Moraga Pumping Plant (herein called the Project), as described below, violated Section 8(b)(4)(n)(B) and 8(e) of the Act. II. JURISDICTION Overaa, the general contractor on the Project, is a Cali- fornia corporation, headquartered in Richmond, engaged as a contractor in the construction industry It annually purchases and receives in California directly from outside the State materials of a value exceeding $50,000. Conduit Fabricators, Inc., a subcontractor on the Proj- ect, is a California corporation engaged in Fairfield in the manufacture of pipe. It annually sells directly to customers outside California products of a value exceeding $50,000. Overaa and Conduit both are persons and employers en- gaged in and affecting commerce within the meaning of Sections 2(1), (2), (6), and (7), and 8(b)(4)(B) and 8(e) of the Act. 111. LABOR ORGANIZATION Respondent is a labor organization within Section 2(5) of the Act IV. THE ALLEGED UNFAIR LABOR PRACTICES A. Facts The East Bay Municipal Utilities District (herein called MUD) for many years has been a principal in the construc- tion of reservoirs, water and sewage treatment plants, wa- ter pumping plants, and related facilities in Alameda and Contra Costa Counties, California. The Project was one such undertaking. MUD contracted to have it built by Ov- eraa for about $2 million Overaa in turn subcontracted the fabrication of certain of the Project's pipe systems to Con- duit The value of this contract, entered into in September 1973, was $275,000. Conduit accomplished the fabrication away from the Project, delivering the finished product to the site in February 1974 Overaa at all relevant times was signatory to a labor agreement with Respondent concerning work within the craft lines of the United Association of Plumbers and Pipe Fitters (herein called UA) Jurisdiction over such work on the Project was vested in UA Local 159 until July 15, 1974, when it was ceded to Respondent. Unaffected by this change was Overaa's three-man complement of onsite em- ployees subject to the above agreement: Charles Burgin, a member of Respondent and pipefitter foreman with power to hire and fire, a welder named John Dunn, who belonged to UA Local 159; and an apprentice belonging to UA Lo- cal 159 None of Conduit's employees was represented by Re- spondent or any other affiliate of UA. Those participating in the fabrication in question were covered by an agree- ment between Conduit and Teamsters Local 490, the wage levels of which were below those in Overaa's agreement with Respondent. Included in Overaa's contract with Con- duit was a clause that the work was to be done in "confor- mance to Union regulation & acceptable for Union trade installation." Clifford McCormick, Conduit's president, credibly testified that the discussion between him and Jerry Overaa, Overaa's general manager, regarding this clause, during their negotiation of the subcontract, had to do with whether Conduit's employees had some kind of union rep- resentation. Paragraph 8 of Overaa's agreement with Respondent stated. PLUMBERS & STEAMFITTERS LOCAL 342 8. The terms and conditions of this Agreement insofar as they affect the Employer shall apply equally to any subcontractor under the control of, or working under contract with, such Employer on any work covered by this Agreement which is to be performed at the site of construction, alteration, building or repair of any building, or other work and said subcontractor with respect to such work shall be considered the same as the Employer covered hereby. Paragraph 13 provided that "pipe formation 2 inches in diameter and under shall be fabricated and assembled on job site"; and paragraph 15 stated: 15. Fabrication at Job Site or In Shop. To secure fab- rication work for employees working under this Agreement in the principal work unit at the job site and in order to protect wages and working conditions of such employees in the principal work unit at the Job site, the Employer may fabricate at job site or in a shop under the following terms and conditions- (1) Pipe formations over 2 inches in diameter, at the option of the Employer, may be fabricated on the job site or in a shop. (2) Piping formations requiring heat or other special treatment or the use of special tools and equipment may be fabricated on the job site or in the shop. (3) All pipe bends over 2 inches in diameter may be made up on the job site or in the shop. (4) All piping and assembling of panel boards shall be done on the job site or in the shop. Paragraph 16 stated- 16. When the word "shop" is used in this Section it shall be defined as a pipe fabricating shop where terms and conditions of employment for Journeymen Plumbers, Pipefitter-Steamfitters and their Appren- tices performing such shop fabrication compare favor- ably with the terms and conditions of employment of the employees covered by this Agreement who would have performed the fabrication at job site if the Em- ployer exercised his option to have it done at job site. The General Counsel does not contend that these work- preservation provisions, so-called, were unlawful on their face, but only that Respondent's manner of attempted en- forcement was improper. The Project became ready for installation of the pipe fabricated by Conduit on or about June 20, 1974. On or about June 4, however, Dennis Gifford, a business agent for UA Local 159, had told Foreman Burgin not to handle the pipe because it did not have a UA label. Gifford also told Overaa's Job superintendent, Howard Verrinder, that Conduit pipe was "unsuitable" for handling by his union Overaa accordingly "worked around" the pipe for sever- al weeks, but by July 15-the date Respondent assumed jurisdiction from UA Local 159-the stage had been reached where this was no longer tenable. A total Job shut- down was imminent were pipe installation not to begin On July 15, Doyle Williams, Respondent's business manager, told Burgin that Respondent's position concerning the pipe coincided with UA Local 159's, that it should not be han- 1369 dled. Burgin passed the word to Dunn and the apprentice, and the three refused to touch the pipe. This necessitated the termination of Dunn on July 15 for want of alternative tasks. On July 17, the situation becoming increasingly desper- ate, Verrinder dispatched Burgin to Respondent's hall in quest of some kind of dispensation. Williams being away Burgin spoke with Robert Beeson, an official of Respon- dent, who said that Williams as yet had not "cleared" the handling of the pipe. Later on the 17th, Verrinder reached Williams by telephone Williams told him that the pipe "was not in conformity with the contract," but that he would authorize the members to handle it and seek redress through the grievance procedure. Williams testified that, by "not in conformity," he meant that those engaged in the fabrication of the pipe had not worked under wages, hours, and working conditions customary to members of Respon- dent. Williams told Burgin early on July 18 that it would be all right to handle the pipe. Installation began July 18, being completed without further delay in January 1975. Respondent initiated grievance proceedings against Ove- raa on October 8, 1974, but had done nothing to move the proceedings along at the time of the present hearing. Wil- liams, in his October 8 grievance letter to Overaa, stated: I have been advised that on your Lafayette [Mora- gal Pumping Station job, your company has pur- chased fabrications to be installed by our members without the union label. Article III, Paragraphs 15 and 16 of the Agreement clearly indicate the procedure to be followed in fabri- cations It is obvious that you are in violation of Arti- cle III. Under Article 7 of the Joint Conference Board pro- cedures, we hereby notify you that we are filing a grievance in accordance with same. Conduit was not a party to the grievance proceeding. The pipe in question ranged in diameter from about 17 to 72 inches Individual lengths weighted up to nearly 30, 000 pounds Overaa was totally without facilities and equipment to perform the necessary fabrication, either at the site or in its shop The fabrication process used by Conduit consisted of these steps: (a) Obtaining from a supplier millrun lengths of steel, pipe of the requisite thicknesses and diameters, as well as assorted attachments-flanges, reducers, couplings, bolts, reinforcing pads, etc.-to be incorporated in the fin- ished product by welding, (b) cutting the pipe to size and shape at Conduit's shop in Vallejo, California, then per- forming the various welding tasks involved in making joints and affixing attachments-that is, converting the raw components into a unified system; (c) hydrostatically testing for watertightness of welds, (d) stress-relieving; i.e., placing the pipe in ovens to cure distortions of molecular alignment caused by uneven application of heat during welding. Conduit itself did not do this, instead having it done at a Kaiser facility 12 miles away; (e) upon return to the Conduit shop, sandblasting to remove oven scale; (f) lining the interior of the system with cement, followed by 7 days of curing in a controlled environment, in the case of 1370 DECISIONS OF NATIONAL LABOR RELATIONS BOARD pump barrels, which were components in the system, the lining was vinyl rather than cement; and (g) sandblasting the exterior of the pipe to remove rust created by curing, then applying an exterior coat of red lead paint. Respondent, although apparently never defining its con- cern to Overaa with such selectivity, took the position dur- ing the hearing and in its brief that it is interested only in those aspects of the fabrication process embodied in item (b), above; namely cutting and welding. Its members un- questionably are capable of onsite performance of those tasks, given proper equipment and facilities. Erection and outfitting of an onsite facility enabling this with pipe of the magnitude in question, however, would entail an outlay of several thousand dollars. Further, while hydrostatic testing, stress-relieving , and coating and lining are not beyond on- site capability, quality, economy, and overall efficiency are better served when those processes are done in permanent facilities designed for the purpose. The performance of these processes offsite, coupled with cutting and welding onsite, would translate into multiple handling, delays, and extra cost. Perhaps reflective of the considerations just raised, the overwhelming weight of tradition in the area favors the practice observed by Overaa in the present case More par- ticularly, there has not been a single instance, involving a MUD project comparable to the present, when any phase of fabrication has occurred onsite. Thus, Elmer J. Freethy Co., a competitor of Overaa's, has constructed over 90 fa- cilities for MUD since 1946, in every one subcontracting the piping system for offsite fabrication. The main subcon- tractor has been Ameron, Inc., whose employees have been Teamsters-represented. Those few instances cited in the record in which onsite fabrication occurred generally are distinguishable from that in question because either the pipe was materially smaller than the present, or the specifi- cations did not call for stress-relieving and/or coating and lining.' B. Analysis As mentioned earlier, the General Counsel does not con- tend that the agreement between Respondent and Overaa was violative of Section 8(e) on its face. Rather, the Gener- al Counsel argues that Respondent's interpretation of the agreement's "work preservation" provisions, in combina- tion with its methods to induce Overaa's adoption of that interpretation, violated Section 8(b)(4)(ii)(B) and 8(e). Re- spondent counters that it was only seeking work "fairly claimable" by it, therefore, that its conduct was permissi- ble. The threshold question is whether Respondent at any time "threatened, coerced, or restrained" Overaa as con- templated by clause (u) of Section 8(b)(4). If it did not, the complaint is devoid of merit without consideration of pri- mary-secondary and work-preservation issues. Southern California Pipe Trades District Council No 16 of the United Association. etc. (Associated General Contractors of Califor- 1 After emergence of the present dispute, in an effort to accommodate the wishes of a Bay Area UA-affiliate, Scott Co agreed to onsite cutting and welding, linings and coatings then to be applied offsite by a subcontractor ma, Inc.), 207 NLRB 698 (1973). It is concluded that Re- spondent did engage in Section 8(b)(4)(u) conduct when, on July 15 Business Manager Williams caused Overaa's employees to handle the disputed pipe, adhering to that approach until July 18, when he authorized Burgin to work with the pipe. Local 370, United Association of Journeymen and Apprentices of the Plumbing and Pipefitting Industry of the United States and Canada, AFL-CIO (Baughan Plumb- ing and Heating Company, Incorporated), 157 NLRB 20 (1966).2 The General Counsel makes the further argument that Respondent engaged in 8(b)(4)(u) conduct by initiating grievance action against Overaa concerning the disputed pipe. It is concluded, however, that Respondent did this in good faith to enforce a colorable contract right and not to restrain employees or employers in the exercise of statutory rights. This argument therefore is rejected for much the same policy reasons underlying Board holdings that resort to civil litigation is not an unfair labor practice. E.g., Retail Clerks Union Local 770, Chartered by Retail Clerks Interna- tional Association, AFL-CIO (Hughes Markets, Inc, and Saba Prescription Pharmacy), 218 NLRB 680 (1975); United Aircraft Corporation, 192 NLRB 382 (1971). See also AGC of California, supra, involving resort to a grievance proce- dure 3 That the Board perhaps would not defer to the re- sults of the grievance action, and indeed might find the results to comprise 8(b)(4)(ii) pressure,4 does not impair the legality of the action being invoked. See Associated General Contractors of California, Inc. v. N.L.R.B., 514 F.2d 433, 438-439 (C.A. 9, 1975). The next question is whether Respondent's imposition of 8(b)(4)(fi) pressure on Overaa was secondary rather than primary in nature. It is concluded that it was secondary, and thus proscribed by Section 8(b)(4)(B). The basis for this conclusion, simply, is that Overaa was powerless to accede to Respondent's wishes concerning fabrication of the pipe-to have it done under UA-sanctioned working conditions-without rejecting the fruits of its subcontract with Conduit and having the work done anew Implicit in Respondent's 8(b)(4)(ii) conduct, therefore, was a "cease doing business" object within subsection (b) of Section 8(b)(4). N.L.R.B. v. Local 825, International Union of Oper- ating Engineers, AFL-CIO [Burns and Roe, Inc], 400 U.S. 297, 304-305 (1971). From the time the subcontract was made, for that mat- ter, Overaa ceased having the power to satisfy Respondent's as yet unvoiced concerns, short of reneging on its deal with Conduit, or, alternatively, persuading Con- duit to abrogate its existing commitment to the Teamsters in favor of UA-prescribed conditions. That is, only Con- 2 Respondent's brief, by implication, concedes the commission of 8(b)(4)(ii) conduct The brief states "[Tlhe Union contends that the single issue upon which lawfulness or unlawfulness of respondent 's actions turns is whether or not the clauses in question, and the actions taken by the Union, were in furtherance of preserving and protecting `fairly claimable' work " I Vacated 514 F 2d 433 (C A 9, 1975) The concern of the Ninth Circuit seemingly centered on a work stoppage, the accompanied use of the griev- ance procedure , and a monetary assessment against the neutral as a result of its use Neither element accompanied Respondent's institution of the pres- ent grievance Cf International Union of Operating Engineers, Local Union No 12 (Acco Construction Equipment), 204 NLRB 742 (1973) PLUMBERS & STEAM FITTERS LOCAL 342 dust had the power to meet Respondent 's wishes absent a cessation by Overaa of its relationship with Conduit. Ap- plying the Board 's "right-of-control " test , 8(b)(4)(u) pres- sures on Overaa after entry into the subcontract conse- quently were secondary . International Brotherhood of Electrical Workers Local Union No 501 (Atlas Construction Company), 216 NLRB 417 (1975); Local Union No. 438, United Association of Journeymen and Apprentices of the Plumbing and Pipe Fitting Industry of the United States and Canada, AFL-CIO (George Koch Sons, Inc), 201 NLRB 59 (1973). See generally , National Woodwork Manufacturers Association, et al. v. N.L R.B., 386 U.S . 612 (1967).5 It is arguable in this connection that Overaa willingly forfeited its power over the situation by entering into the subcontract , and so should not be entitled to neutral status. As stated in Atlas Construction Co., supra, an employer can- not be considered neutral to a dispute when its re linquish- ment of control . .. was based on some affirmative conduct which the employer could reasonably conclude would conflict with his collective-bargaining obligations, coupled with the absence of any demand for such conduct by an independent third party . The circumstances of the present case, however, do not support this argument. The record, far from suggesting that Overaa's delegation of control to Conduit was gratuitously done with a foreseeable tendency to interfere with Overaa's obligations to Respondent, leaves no doubt that the delega- tion was prompted by valid considerations of technical and economic feasibility, reinforced by long-established past practice. The record, moreover, provides scant basis for Overaa to have had advance suspicions that its actions would offend Respondent.' In summary, Respondent violated Section 8(b)(4)(ii)(B) by causing Overaa's employees to refrain from handling pipe fabricated by Conduit. Respondent to the contrary, it does no violence to this conclusion that the cutting and welding done by Conduit's employees on the disputed pipe may have been work "fairly claimable" by Respondent. George Koch Sons, Inc., supra. Whether Respondent's conduct in addition violated Sec- tion 8(e), however, does turn on the issue of fair claimabili- ty. The test of fair claimability is whether work of the na- ture in question historically has been done by unit employees with a regularity amounting to custom and tra- dition in the industry. Capability of unit employees to do the work is irrelevant . Sheet Metal Workers Union, Local 162, Sheet Metal Worker's International Association, AFL- CIO (Associated Pipe and Fittings Manufacturers), 207 5 This is not to ignore those decisions of some circuit courts rejecting the right-of-control test, a recent example of which is Enterprise Assocation of Steam, Hot Water, Hydraulic Sprinkler, Pneumatic Tube, Ice Machine and General Pipefitters of New York and Vicinity, Plumbers Local Union 638 [Aus- tin Co, Inc ] v N L R B, 521 F 2d 885 (C A D C, 1975) Board law, not that of the circuit courts, is controlling at this juncture E g , Bricklayers, Masons and Plasterers' Union Local No / (Barr Floors, Inc), 209 NLRB 820, In I (1974) 6 Overaa obviously thought that Conduit's employees being union-repre- sented would preclude any problems in this regard, as witness the discussion between Jerry Overaa and Conduit's McCormick over the clause in the subcontract that work be "acceptable for Union trade installation " 1371 NLRB 741 (1973). The requisite custom and tradition lack- ing, the inference follows that the Union's claim was not intended to recapture work for the benefit of unit employ- ees, which is permissible under Section 8(e), but instead to expand work opportunities for members generally. Retail Clerks Union Local 770, Chartered by Retail Clerks Interna- tional Association, AFL-CIO (Hughes Markets, Inc., and Saba Prescription Pharmacy), 218 NLRB 680 (1975). Tradition in the present case overwhelmingly favors con- tracting out for offsite fabrication. The General Counsel thus has the better of the 8(e) argument. Respondent's ef- forts to impose an interpretation of the agreement preclud- ing Overaa's subcontracting to Conduit accordingly violat- ed Section 8(e) as well as 8(b)(4)(B). CONCLUSIONS OF LAW 1. By causing Overaa's employees to refrain from han- dling pipe fabricated by Conduit, as found herein , Respon- dent engaged in unfair labor practices within Section 8(b)(4)(ii)(B) and 8(e) of the Act. 2. These unfair labor practices affect commerce within Section 2(6) and (7) of the Act. 3. Respondent did not otherwise violate the Act as al- leged. Upon the basis of the foregoing findings of fact and con- clusions of law and the entire record in this proceeding, I make the following recommended- ORDER' Respondent Steamfitters ' Local Union 342, United As- sociation of Journeymen and Apprentices of the Plumbing and Pipefitting Industry of the United States and Canada, AFL-CIO, its officers, agents , and representatives, shall: 1. Cease and desist from: (a) Threatening , coercing , and restraining C. Overaa & Co. with an object of forcing or requiring Overaa to cease doing business with Conduit Fabricators, Inc. (b) Maintaining, enforcing , or giving effect to the work- preservation provisions of its agreement with C. Overaa & Co. in the manner herein found unlawful. 2. Take the following affirmative action: (a) Post at its business offices and meeting halls copies of the attached notice marked "Appendix ." 8 Copies of said notice, on forms provided by the Regional Director for Region 20, after being duly signed by Respondent's 7 All outstanding motions inconsistent with this recommended Order hereby are denied In the event no exceptions are filed as provided by Sec 102 46 of the Rules and Regulations of the National Labor Relations Board, the findings, conclusions, and recommended Order herein shall, as provided in Sec 102 48 of the Rules and Regulations, be adopted by the Board and become its findings, conclusions, and Order, and all objections thereto shall be deemed waived for all purposes 8 In the event that the Board's Order is enforced by a Judgment of the United States Court of Appeals, the words in the notice reading "Posted by Order of the National Labor Relations Board" shall read "Posted Pursuant to a Judgment of the United States Court of Appeals Enforcing an Order of the National Labor Relations Board " 1372 DECISIONS OF NATIONAL LABOR RELATIONS BOARD representative , shall be posted by Respondent immediately upon receipt thereof , and be maintained by it for 60 con- secutive days thereafter , in conspicuous places, including all places where notices to members are customarily post- ed. Reasonable steps shall be taken by Respondent to in- sure that said notices are not altered , defaced, or covered by any other material. (b) Furnish the Regional Director for Region 20 with signed copies of the aforesaid notice for posting by C Ove- raa & Co., should it be willing , at all places where notices to its employees are customarily posted. (c) Notify the Regional Director for Region 20, in writ- ing, within 20 days from the date of this Order , what steps Respondent has taken to comply herewith IT IS FURTHER ORDERED that the complaint be dismissed as to all allegations not found to be violations herein. APPENDIX NOTICE To MEMBERS POSTED BY ORDER OF THE NATIONAL LABOR RELATIONS BOARD An Agency of the United States Government The hearing held in San Francisco , California , on Febru- ary 25, 26 , and 28 , and April 29 , 1975, in which we partici- pated and had a chance to g've evidence , resulted in a decision that we had committed certain unfair labor prac- tices in violation of Section 8(b)(4)(ii)(B) and 8(e) of the National Labor Relations Act, and this notice is posted pursuant to that decision. WE WILL NOT threaten, coerce , or restrain C. Overaa & Co. with an object of forcing or requiring Overaa to cease doing business with Conduit Fabricators, Inc. WE WILL NOT maintain , enforce, or give effect to the work-preservation provisions of our agreement with C. Overaa & Co. in the manner found by the National Labor Relations Board to violate Section 8(e). STEAMFITTERS' LOCAL UNION 342, UNITED ASSOCIATION OF JOURNEYMEN AND APPRENTICES OF THE PLUMBING AND PIPEFITTING INDUSTRY OF THE UNITED STATES AND CANADA, AFL-CIO Copy with citationCopy as parenthetical citation