Cal. Civ. Code § 8412

Current through the 2023 Legislative Session.
Section 8412 - Recording claim of lien after contractor completes direct contract

A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:

(a) Ninety days after completion of the work of improvement.
(b) Sixty days after the owner records a notice of completion or cessation.

Ca. Civ. Code § 8412

Added by Stats 2010 ch 697 (SB 189),s 20, eff. 1/1/2011, op. 7/1/2012.