Cal. R. 8.705

As amended through July 24, 2024
Rule 8.705 - Court of Appeal costs in leadership projects

In fulfillment of the provisions in Public Resources Code sections 21168.6.7, 21168.6.8, 21168.6.9, 21183, and 21189.82 regarding payment of the Court of Appeal's costs with respect to cases concerning environmental leadership development, environmental leadership transit, Oakland ballpark, Inglewood arena, energy infrastructure, semiconductor or microelectronic, or water-related projects:

(1) Within 10 days after service of the notice of appeal or petition in a case concerning an environmental leadership development project, the person or entity that applied for certification of the project as an environmental leadership development project must pay a fee of $215,000 to the Court of Appeal.
(2) Within 10 days after service of the petition or complaint in a case concerning an energy infrastructure project, a semiconductor or microelectronic project, or a water-related project, the project applicant, if the applicant is not the lead agency, must pay a fee of $215,000 to the court.
(3) Within 10 days after service of the notice of appeal or petition in a case concerning an environmental leadership transit project, the project applicant must pay a fee of $215,000 to the Court of Appeal.
(4) Within 10 days after service of the notice of appeal or petition in a case concerning an Oakland ballpark project or Inglewood arena project, the person or entity that applied for certification of the project as an Oakland ballpark project or Inglewood arena project must pay a fee of $140,000 to the Court of Appeal.
(5) If the Court of Appeal incurs the costs of any special master appointed by the Court of Appeal in the case or of any contract personnel retained by the Court of Appeal to work on the case, the person or entity that applied for certification of the project or the project applicant must also pay, within 10 days of being ordered by the court, those incurred or estimated costs.
(6) If the party fails to timely pay the fee or costs specified in this rule, the court may impose sanctions that the court finds appropriate after notifying the party and providing the party with an opportunity to pay the required fee or costs.
(7) Any fee or cost paid under this rule is not a recoverable cost.

Cal. R. Ct. 8.705

Rule 8.705 amended effective 12/31/2023; amended effective 1/1/2023; amended effective 3/11/2022; adopted effective 7/1/2014.

Advisory Committee Comment

Subdivision (b). It is very important to note that the time period to file a notice of appeal under this rule is the same time period for filing most postjudgment motions in a case regarding the Sacramento arena project, and in a case regarding a leadership project or capitol building annex project, the deadline for filing a notice of appeal may be earlier than the deadline for filing a motion for a new trial, a motion for reconsideration, or a motion to vacate the judgment.