W. Va. Code R. § 64-16-3

Current through Register Vol. XLI, No. 45, November 8, 2024
Section 64-16-3 - Construction Permit
3.1. A person shall not establish, construct or renovate a recreational water facility without first obtaining a construction permit from the Commissioner.
3.2. The applicant shall submit four (4) sets of completed applications, plans and specifications to the Commissioner for review and approval at least forty-five (45) days prior to the date on which he or she requests that the construction permit takes effect.
3.3. The applicant shall submit a written permit application on a form obtained from the Commissioner. The application, plans, and specifications shall include, but not be limited to:
3.3.a. Vicinity and site plans;
3.3.b. Detailed construction drawings;
3.3.c. Water source and treatment detail; and
3.3.d. Specifications for filtration, chlorination, testing equipment and other pertinent factors necessary for a complete operative system.
3.4. The Commissioner may suspend or revoke a construction permit if a person fails to comply with the provisions of the permit or this rule.
3.5. The Commissioner shall deny a construction permit if the information on the application form is incomplete, inaccurate, false or misleading, or indicates that the applicable provisions of this rule cannot be met.
3.6. A person whose application for a construction permit has been denied, or whose permit has been suspended or revoked, may submit a written petition to the Commissioner requesting a hearing on the matter, and the Commissioner shall grant a hearing on the matter within ten (10) days after he or she has received the petition.
3.7. The recreational water facility shall be constructed or renovated in accordance with the plans and specifications approved by the Commissioner, unless the Commissioner grants written approval for a deviation from the approved plans and specifications.

W. Va. Code R. § 64-16-3