Okla. Admin. Code § 252:100-8-55

Current through Vol. 42, No. 1, September 16, 2024
Section 252:100-8-55 - Source obligation
(a)Construction permits required. An owner or operator shall obtain a construction permit prior to commencing construction of a new major stationary source or major modification.
(b)Responsibility to comply and the consequences of relaxation of permit conditions. The requirements in 40 CFR 51.165(a)(5) regarding the responsibility to comply with applicable local State or Federal law and the consequences of becoming a major source by virtue of a relaxation in any enforcement limitation are hereby incorporated by reference as they exist on July 2, 2007.
(c)Requirements when using projected actual emissions.
(1) The specific provisions in 40 CFR 51.165(a)(6)(i) through (v) (as they exist on July 2, 2007) shall apply to projects at existing emissions units at a major stationary source (other than projects at a source with a PAL) when the owner or operator elects to use the methods specified in the definition of "projected actual emissions" at 40 CFR 51.165(a)(1)(xxviii)(B)(1) through (3) for calculating projected actual emissions.
(2) The requirements in 40 CFR 51.165(a)(6)(i) through (v) are hereby incorporated by reference as they exist on July 2, 2007.
(d)Availability of information. The requirements in 40 CFR 51.165(a)(7) regarding availability of information required to document the use of projected actual emissions for determining if a project is a major modification are hereby incorporated by reference as they exist on July 2, 2007.

Okla. Admin. Code § 252:100-8-55

Added at 23 Ok Reg 1699, eff 6-15-06; Amended at 26 Ok Reg 1146, eff 7-1-09