Section 252:100-8-54 - Requirements for sources located in nonattainment areas

In the event a major source or modification would be constructed in an area designated as nonattainment for a pollutant for which the source or modification is major, approval shall be granted only if the following conditions are met:

(1) The new source must demonstrate that it has applied control technology which the Director, on a case-by-case basis, determines is achievable for a source based on the lowest achievable emission rate (LAER) achieved in practice by such category of source (i.e., lowest achievable emission rate as defined in the Act).
(2) If the Director determines that imposition of an enforceable numerical emission standard is infeasible due to technological or economic limitations on measurement methodology, a design, equipment, work practice or operational standard, or combination thereof, may be prescribed as the emission limitation rate.
(3) The owner or operator of the new source must demonstrate that all other major sources owned or operated by such person in Oklahoma are in compliance, or are meeting all steps on a schedule for compliance, with all applicable limitations and standards under Oklahoma and Federal Clean Air Acts.
(4) The owner or operator of the new source must demonstrate that upon commencing operations:
(A) The emissions from the proposed source and all other sources permitted in the area do not exceed the planned growth allowable for the area designated in the State Implementation Plan; or,
(B) The total allowable emissions from existing sources in the region and the emissions from the proposed source will be sufficiently less than the total emissions from existing sources allowed under the State Implementation Plan at the date of construction permit application so as to represent further progress toward attainment or maintenance of the ambient air quality standards in the problem area.
(5) The owner or operator may present with the application an analysis of alternate sites, sizes and production processes for such proposed source.