Current through Register Vol. 39, No. 9, November 1, 2024
Section 02D .0705 - REVIEW PROCEDURES(a) Upon receipt of a completed application, the Chief Engineer shall acknowledge the receipt and initiate a preliminary investigation and review.(b) In reviewing the application, the following factors shall be taken into consideration as a basis for approval or disapproval:(2) availability of an acceptable detour;(3) length of an acceptable detour;(4) type road surface (paved or unpaved);(5) school bus route - number of buses;(6) anticipated frequency of flooding;(7) anticipated duration of flooding;(8) cost estimates to raise the roadway above flood stage;(9) probability of future significant changes in traffic characteristics;(10) comments from affected utilities; and(11) comments from general public.(c) Under no condition shall a permit be issued to allow flooding which would isolate any home, business, or other commercial establishment.19A N.C. Admin. Code 02D .0705
Authority G.S. 136-64.1(d);
Eff. July 1, 1978;
Amended Eff. December 1, 2012;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. September 6, 2016.Authority G.S. 136-64.1(d);
Eff. July 1, 1978;
Amended Eff. December 1, 2012.