1 N.C. Admin. Code 30F.0201

Current through Register Vol. 38, No. 20, April 15, 2024
Section 30F .0201 - PROJECT DESCRIPTION
(a) It shall be the responsibility of each Capital Projects Coordinator, for each Capital Improvements project as defined in G.S. 143-135.27 requiring professional services, to provide the State Construction Office with a written description of the professional services desired, the scope of work, schedule requirements, amount of authorized funds and other appropriate information. This phase of the project development is intended to convey project information.
(b) It shall be the joint responsibility of the Capital Projects Coordinator and Office of State Construction, to the best of their belief and knowledge, to ensure that the contract plans and specifications accurately reflect the description of the work to be performed by each prime contractor. This phase of the project development, intended to convey contract information, which is a sub-set of project information, is critical as the evaluation of the prime contractor's performance will depend in part on the contract requirements clearly delineating the work to be performed and establishing an appropriate time frame for contract completion.

01 N.C. Admin. Code 30F .0201

Authority G.S. 143-135.26(4);
Eff. December 1, 1991;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.
Authority G.S. 143-135.26(4);
Eff. December 1, 1991.