40 C.F.R. § 63.7821

Current through May 31, 2024
Section 63.7821 - [Effective until 6/3/2024] When must I conduct subsequent performance tests?
(a) You must conduct subsequent performance tests to demonstrate compliance with all applicable emission and opacity limits in Table 1 to this subpart at the frequencies specified in paragraphs (b) through (e) of this section.
(b) For each sinter cooler at an existing sinter plant and each emissions unit equipped with a control device other than a baghouse, you must conduct subsequent performance tests no less frequently than twice (at mid-term and renewal) during each term of your title V operating permit.
(c) For each emissions unit equipped with a baghouse, you must conduct subsequent performance tests no less frequently than once during each term of your title V operating permit.
(d) For sources without a title V operating permit, you must conduct subsequent performance tests every 2.5 years.
(e) For each BOPF Group, if demonstrating compliance with the mercury emission limit in Table 1 to this subpart through performance testing under §§ 63.7825 and 63.7833 , you must conduct subsequent performance tests twice per permit cycle (i.e., mid-term and initial/final) for sources with title V operating permits, and every 2.5 years for sources without a title V operating permit, at the outlet of the control devices for the BOPF Group.

40 C.F.R. §63.7821

71 FR 39586, July 13, 2006, as amended at 85 FR 42116, July 13, 2020
85 FR 42116, 7/13/2020