Current through May 31, 2024
Section 774.12 - Post-permit issuance information requirements for permittees(a) Within 30 days after the issuance of a cessation order under § 843.11 of this chapter, or its State regulatory program equivalent, you, the permittee, must provide or update all the information required under § 778.11 of this subchapter.(b) You do not have to submit information under paragraph (a) of this section if a court of competent jurisdiction grants a stay of the cessation order and the stay remains in effect.(c) Within 60 days of any addition, departure, or change in position of any person identified in § 778.11(c) of this subchapter, you must provide-(1) The information required under § 778.11(d) of this subchapter; and(2) The date of any departure.65 FR 79667, Dec. 19, 2000, as amended at 72 FR 68030, Dec. 3, 2007