Utah Admin. Code 307-401-6

Current through Bulletin 2024-09, May 1, 2024
Section R307-401-6 - Review Period
(1) Completeness Determination. Within 30 days after receipt of a notice of intent, or any additional information necessary to the review, the director will advise the applicant of any deficiency in the notice of intent or the information submitted.
(2) Within 90 days after the receipt of a complete application including all the information described in Section R307-401-5, the director will
(a) issue an approval order for the proposed construction, installation, modification, relocation, or establishment pursuant to the requirements of Section R307-401-8, or
(b) issue an order prohibiting the proposed construction, installation, modification, relocation or establishment if it is determined that any part of the proposal will not be in the accord with the requirements of Title R307.
(3) The review period under Subsection R307-401-6(2) may be extended by up to three 30-day extensions if more time is needed to review the proposal.

Utah Admin. Code R307-401-6

Amended by Utah State Bulletin Number 2016-1, effective 12/15/2015
Amended by Utah State Bulletin Number 2018-7, effective 3/5/2018
Amended by Utah State Bulletin Number 2020-18, effective 9/3/2020