25 Pa. Code § 78a.16

Current through Register Vol. 54, No. 21, May 25, 2024
Section 78a.16 - Accelerated permit review

In cases of hardship, an operator may request an accelerated review of a well permit application. For the purposes of this section, hardship includes cases where immediate action is necessary to protect public health or safety, to control pollution or to effect other environmental or safety measures, and extraordinary circumstances beyond the control of the operator. Permits issued shall be consistent with the requirements of the act.

25 Pa. Code § 78a.16