Haw. Code R. § 13-170-42

Current through March, 2024
Section 13-170-42 - Guidelines for preparation of the plan
(a) In preparing the state water projects plan and for purposes of consistency, the agency shall utilize information from the master water inventory identified within the water resource protection plan. The plan shall also utilize the hydrologic units designated statewide by the commission for the presentation of data and analyses.
(b) The plan shall review current and future state water programs and projects to insure orderly authorization and development of the state's water resources. Study shall be made for all existing and contemplated water projects and shall be based upon, but not be limited to, the following information:
(1) Type of project;
(2) Source of water;
(3) Existing uses;
(4) Contemplated uses; and
(5) System capacity.
(c) The state water projects plan shall consider a twenty-year projection period for analysis purposes.

Haw. Code R. § 13-170-42

[Eff. MAY 27, 1988] (Auth: HRS § 174C-8) (Imp: HRS §§ 174C-5, 174C-31)