40 C.F.R. § 93.114

Current through March 31, 2024
Section 93.114 - Criteria and procedures: Currently conforming transportation plan and TIP

There must be a currently conforming transportation plan and currently conforming TIP at the time of project approval, or a project must meet the requirements in § 93.104(f) during the 12-month lapse grace period.

(a) Only one conforming transportation plan or TIP may exist in an area at any time; conformity determinations of a previous transportation plan or TIP expire once the current plan or TIP is found to conform by DOT. The conformity determination on a transportation plan or TIP will also lapse if conformity is not determined according to the frequency requirements specified in § 93.104 .
(b) This criterion is not required to be satisfied at the time of project approval for a TCM specifically included in the applicable implementation plan, provided that all other relevant criteria of this subpart are satisfied.

40 C.F.R. §93.114

62 FR 43801, Aug. 15, 1997, as amended at 73 FR 4440, Jan. 24, 2008