30 C.F.R. § 817.122

Current through March 31, 2024
Section 817.122 - Subsidence control: Public notice

At least 6 months prior to mining, or within that period if approved by the regulatory authority, the underground mine operator shall mail a notification to all owners and occupants of surface property and structures above the underground workings. The notification shall include, at a minimum, identification of specific areas in which mining will take place, dates that specific areas will be undermined, and the location or locations where the operator's subsidence control plan may be examined.

30 C.F.R. §817.122

48 FR 24652, June 1, 1983, as amended at 81 FR 93418, Dec. 20, 2016; 82 FR 54999, Nov. 17, 2017
81 FR 93418, 1/19/2017