From Casetext: Smarter Legal Research

Spiniello Const. Co. v. Manchester

Supreme Court of Connecticut
Mar 22, 1983
189 Conn. 539 (Conn. 1983)

Summary

upholding the district court's grant of a permanent injunction restraining a municipality and a bidder from entering into a public works contract where the bidding statute had been violated

Summary of this case from Orion Technical Res., LLC v. Los Alamos Nat'l Sec., LLC

Opinion

(10439)

The defendant R Co. appealed to this court from the trial court's judgment granting to the plaintiff, S Co., a permanent injunction restraining R Co. and the defendant town of Manchester from entering into or performing two public works contracts. In response to a solicitation by the town, three companies, including S Co. and R Co., had submitted bids on the two contracts. Thereafter, the town, without notice to the other bidders, allowed R Co. to submit a combined bid on both contracts. Although S Co.'s bid was lower than R Co.'s on one of the contracts, both were awarded to R Co. Held: 1. S Co., although it was an unsuccessful bidder and although it was not a Manchester taxpayer, had standing to bring the action here. 2. Under all of the circumstances, there was adequate support for the trial court's conclusion that the bidding was invalid. 3. Because R Co. failed to demonstrate that its challenge to one of the trial court's findings, if successful, would affect the final result, any error in that finding was harmless. 4. The allegations of favoritism in the bidding process in S Co.'s complaint were sufficient to permit the introduction of evidence on that issue. 5. The town's argument that the matter had become moot because a third party had been awarded and had completed work under the contracts was without merit; where, as here, a permanent injunction has been granted, an appeal on the merits will be saved from mootness by the injunction bond.

Argued November 10, 1982

Decision released March 22, 1983

Action for an injunction restraining the defendants from entering into certain public works contracts awarded by the named defendant to the defendant Raymond International Builders, Inc., brought to the Superior Court in the judicial district of Hartford-New Britain at Hartford and tried to the court, Bernstein, J.; judgment granting injunctive relief, from which the defendant Raymond International Builders, Inc., appealed to this court. No error.

Aaron Slitt, with whom were Susan Kloct, and, on the brief, William Gerace, for the appellant (defendant Raymond International Builders, Inc.).

William J. Shea, for the appellee (named defendant).

Emanuel N. Psarakis, with whom, on the brief, was Charles B. Spadoni, for the appellee (plaintiff).


The plaintiff obtained a permanent injunction restraining the defendants, the town of Manchester (hereinafter Manchester) and Raymond International Builders, Inc. (hereinafter Raymond), from entering into or performing certain public works contracts. Raymond alone has appealed although Manchester has raised the issue of mootness.

Manchester was engaged in an extensive program of cleaning and lining water pipes to improve its water system. This program was divided into approximately twenty components. The town charter, 5-22, mandated competitive bidding for construction contracts costing in excess of $2500. In May, 1980, Manchester publicly invited two separate bids on contracts known as #2 and #3. In its "Instructions to Bidders," Manchester reserved to itself the right to reject any or all bids. In addition, the instructions set forth certain requirements and guidelines such as (a) the prohibition of oral addenda to or interpretations of any bidding documents, (b) the necessity that all requests for such interpretations be in writing with the resultant interpretations issued as written addenda and mailed to prospective bidders, and (c) the prohibition of conditional bids.

Section 5-22 of the Manchester Code is set forth fully below: "Before any department, commission, officer or employee of the Town or the Board of Education shall make any purchase of or contract for any construction, supplies, materials, equipment or service, except personal services, provided by Town employees and officers and professional services, involving an expenditure of more than twenty-five hundred dollars, opportunity shall be given for competitive bidding in writing by at least three bona fide bidders under such rules and regulations as the Board of Directors or the Board of Education, as the case may be, may establish. Before any department, commission, board, officer or employee of the Town shall sell any real or personal property of the Town, opportunity shall be given for competitive bidding in writing by at least three bona fide bidders under such rules and regulations as the Board of Directors or the Board of Education, as the case may be, may establish; and all moneys received from such sales shall be paid to the Collector of Revenue. Either of said Boards may waive the requirement for competitive bidding when the circumstances of a particular case do not permit a sufficient amount of time to fulfill the rules and regulations of that Board concerning competitive bids; or when a competitive bid is inappropriate; or when a competitive bid is impractical in that the Boards are unable to obtain competitive bids within the rules and regulations adopted by said Boards, which may provide for a limitation on the number of waivers in favor of any one firm, person or corporation. Any such waiver shall be in writing, certified by the appropriate Board, and shall set forth a specific substantial reason for such waiver and shall be filed in the Town Clerk's office as a public record."

Section 7 of the instructions addresses oral addenda to pre-bid documents as follows: "No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally. All information given to bidders other than by means of the plans, specifications, or by addenda, as described below [in footnote 3 infra], is given informally and shall not be used as the basis of a claim against the owner or the Engineer."

The requirement of written requests and written interpretations is also set forth in section 7 of the instructions and reads: "Every request for such interpretation should be in writing addressed to Weston Sampson Engineers, Inc., 10 High Street Boston, Massachusetts and to be given consideration must be received at least five days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be mailed by certified mail with return receipt requested to all prospective bidders (at the respective address furnished for such purposes), not later than three days prior to the date fined for the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the Contract Documents."

Section 4 of the instructions prohibits conditional bids as set forth below: "The owner may make such investigations as he deems necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the owner all such information and data for this purpose as the owner may request. The owner reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy the owner that such bidder is properly qualified to carry out the obligations of the Contract and to complete the work contemplated therein. Conditional bids will not be accepted."

Three construction firms, including the plaintiff and Raymond, submitted separate bids on July 14, 1980. On contract #3 the plaintiff's bid ($268,450) was the lowest and Raymond's bid ($272,200) was next lowest. On contract #2 Raymond submitted the lowest bid ($397,860) and the plaintiff's bid ($399,160) was the next lowest. Unknown to the other bidders, a representative of Raymond contacted officials of Manchester on July 11, 1980, and inquired whether, in addition to the separate bids, it could file a reduced combined bid conditioned on both contracts being awarded to Raymond. The Manchester officials advised Raymond that it could submit such a proposal in addition to the separate bids. Despite the bid instructions which required written notice to all prospective bidders of interpretations of the bidding documents, no such notice was mailed to the plaintiff or to others.

On July 14, 1980, when the bids were opened publicly and in the presence of the plaintiff, the Raymond bid contained an additional provision that it would deduct the sum of $35,000 if both contracts were awarded to it. Since the plaintiff was not aware of this change in the bidding process, it had not submitted a discount proposal conditioned on the award of both contracts. The plaintiff filed a written protest which was denied. Also, the plaintiff requested permission to file a combined bid but this request was denied by Manchester on the ground that the bids had already been opened. On August 1, 1980, the plaintiff was notified that both contracts were awarded to Raymond.

The trial court found that the officials of Manchester acted out of the highest motives to do what Was best for Manchester, namely, to save approximately $31,000 by awarding both contracts to the same bidder. The court also found that there was no corruption involved in the bidding process. The court did find, however, that the Raymond bid was conditional and prohibited by the bidding instructions and, under all the circumstances, the process amounted to favoritism toward Raymond. Finally, the court found that the plaintiff, a New Jersey corporation, was not a taxpayer in the defendant town.

In its appeal Raymond has raised the following two main issues: (1) the plaintiff, as an unsuccessful bidder and a nontaxpayer, has no standing to bring this action in the absence of fraud or corruption, and (2) if the plaintiff did have standing, the court erred in finding that the bidding was invalid.

It is a well established principle that "[m]unicipal competitive bidding laws are enacted to guard against such evils as favoritism, fraud or corruption in the award of contracts, to secure the best product at the lowest price, and to benefit the taxpayers, not the bidders; they should be construed to accomplish these purposes fairly and reasonably with sole reference to the public interest." John J. Brennan Construction Corporation, Inc. v. Shelton, 187 Conn. 695, 702, 448 A.2d 180 (1982); Austin v. Housing Authority, 143 Conn. 338, 345, 122 A.2d 399 (1956); 10 McQuillin, Municipal Corporations (3d Ed. Rev.) 29.29. Where the municipality "reserves the right to reject any and all bids, no bidder can claim any contractual rights until he has been awarded the contract." 10 McQuillin, supra, 29.77. An honest exercise of discretion by a municipality which has reserved such a right will not be disturbed by the courts so long as its officials observe good faith and accord all bidders just consideration in accordance with the purpose of competitive bidding. Courts will intervene to prevent the exercise of that discretion to deny a bid, therefore, only where fraud, corruption or favoritism has influenced the conduct of the bidding officials or when the very object and integrity of the competitive bidding process is defeated by the conduct of municipal officials. John J. Brennan Construction Corporation, Inc. v. Shelton, supra, 703; Joseph Rugo, Inc. v. Henson, 148 Conn. 430, 434, 171 A.2d 409 (1961); 10 McQuillin, supra.

Although Manchester reserved the right to reject any or all bids, it violated its bidding instructions by accepting a conditional combined discount bid based on an oral addendum known only to Manchester and Raymond. No written notice of the interpretation of a bidding instruction was mailed to prospective bidders, including the plaintiff. By permitting Raymond to submit a conditional bid when other bidders were not afforded the same opportunity, Manchester precluded the other bidders from competing on equal terms. It defeated the object and integrity of the competitive bidding by unintentionally exhibiting favoritism to Raymond. While Manchester's actions were taken in good faith in an effort to obtain the best contract for its residents, judicial relief is warranted where municipal action amounts to an erosion on the integrity of the bidding statute. 10 McQuillin, supra, 29.83. It is entirely possible that Manchester would have benefited financially if the other bidders had the same opportunity to submit a conditional or combined bid. Under the circumstances of this case the plaintiff had standing and there was ample support for the court's conclusion that the initial bidding was invalid. There is a growing trend for courts to permit one who has been aggrieved by a refusal to award a public contract pursuant to lowest responsible bidder provisions to also vindicate the public interest by challenging such arbitrary or capricious action by governmental officials. Merriam v. Kunzig, 476 F.2d 1233 (3d Cir.), cert. denied, 414 U.S. 911, 94 S.Ct. 233, 38 L.Ed.2d 149 (1973); Scanwell Laboratories, Inc. v. Shaffer, 424 F.2d 859 (D.C. Cir. 1970); see Data Processing Service Organizations, Inc. v. Camp, 397 U.S. 150, 90 S.Ct. 827, 25 L.Ed.2d 184 (1970); Barlow v. Collins, 397 U.S. 159, 90 S.Ct. 832, 25 L.Ed.2d 192 (1970).

There is no merit to another claim of error by Raymond to the effect that the trial court erred in finding that the discount amount of $35,000 was discussed by Raymond and Manchester officials prior to the submission of the bid. Although the record does not indicate a discussion of that sum prior to submission, Raymond has failed to demonstrate how that finding would affect the final result. It was, therefore, harmless error. Jones Destruction, Inc. v. Upjohn, 161 Conn. 191, 286 A.2d 308 (1971).

Finally, Raymond claims that there was a variance between the plaintiff's allegations in its complaint and the proof, sufficient to defeat the cause of action. Although the plaintiff did allege collusion, conspiracy, fraud and corruption, it also alleged favoritism to such an extent as to defeat the competitive bidding process. This allegation was adequate to permit the introduction of evidence in support of the trial court's conclusions.

Paragraph 20 of the complaint reads as follows: "In awarding said contracts to Raymond and rejecting plaintiff's bids under the foregoing circumstances, the Town failed to observe good faith or to accord plaintiff just consideration and engaged in a fraudulent and corrupt course of conduct in favor of Raymond and against plaintiff in violation of defendants charter, and bid documents so as to defeat the competitive bidding process."

In oral argument before this court, counsel for Manchester contended that this appeal is moot because Manchester readvertised for bids on several contracts, including contracts #2 and #3 These contracts were awarded to a third party who completed the work allegedly making ineffective any contractual rights which Raymond might assert against Manchester. Raymond countered with the argument that the plaintiff had posted a bond in the injunctive proceedings as ordered by the trial court. In effect, Raymond claims that its potential right upon the bond is a sufficient interest in the outcome of the appeal to require this court to accept jurisdiction.

Spiniello filed a bond in the amount of $25,000 as a prerequisite to the granting of its application for a temporary injunction and a permanent injunction. The purpose of the bond is to indemnify the defendants from any damages which they might sustain if the plaintiff failed to prosecute the action to effect. General Statutes 52-472. "Where a . . . court has granted a permanent injunction, the parties will already have had their trial on the merits, and, even if the case would otherwise be moot, a determination can be had on appeal of the correctness of the trial court's decision on the merits, since the case has been saved from mootness by injunction bond." Accurate Forging Corporation v. UAW Local No. 1012, 189 Conn. 24, 27-28 n. 5, 453 A.2d 769 (1983), quoting University of Texas v. Camenisch, 451 U.S. 390, 396, 101 S.Ct. 1830, 68 L.Ed.2d 175 (1981). Accordingly, Manchester's mootness claim is without merit.


Summaries of

Spiniello Const. Co. v. Manchester

Supreme Court of Connecticut
Mar 22, 1983
189 Conn. 539 (Conn. 1983)

upholding the district court's grant of a permanent injunction restraining a municipality and a bidder from entering into a public works contract where the bidding statute had been violated

Summary of this case from Orion Technical Res., LLC v. Los Alamos Nat'l Sec., LLC

upholding the district court's grant of a permanent injunction restraining a municipality and a bidder from entering into a public works contract where the bidding statute had been violated

Summary of this case from Orion Technical Res., LLC v. Los Alamos Nat'l Sec., LLC

In Spiniello Construction Co. v. Manchester, supra, 189 Conn. at 543–45, 456 A.2d 1199, this court held for the first time that even though public bidding laws create no cause of action for disappointed bidders, such a bidder had standing to pursue a claim that a town had violated these laws by accepting a conditional combined discount bid based on an oral addendum known only to one bidder, precluding other bidders from competing on equal terms.

Summary of this case from Elec. Contractors, Inc. v. Dep't of Educ.

In Spiniello Construction Co. v. Manchester, supra, 189 Conn. 543-45, this court held for the first time that even though public bidding laws create no cause of action for disappointed bidders, such a bidder had standing to pursue a claim that a town had violated these laws by accepting a conditional combined discount bid based on an oral addendum known only to one bidder, precluding other bidders from competing on equal terms.

Summary of this case from Elec. Contractors, Inc. v. Dept. of Educ.-Concurrence & Dissent

In Spiniello Construction Co. v. Manchester, supra, 189 Conn. 544-45, we substantially adopted the approach to unsuccessful bidder claims that was described by the Court of Appeals for the District of Columbia in Scanwell Laboratories, Inc. v. Shaffer, 424 F.2d 859, 864 (D.C. Cir. 1970).

Summary of this case from Lawrence Brunoli, Inc. v. Town of Branford

In Spiniello Construction Co. v. Manchester, 189 Conn. 539, 456 A.2d 1199 (1983), we recognized that our prior decisions had the effect of preventing judicial review of potentially meritorious claims concerning the implementation and execution of competitive bidding statutes.

Summary of this case from Ardmare Constr. Co., Inc. v. Freedman

In Spiniello Construction Co. v. Manchester, supra, 189 Conn. 542, construction firms submitted individual bids on a project.

Summary of this case from Mohawk Northeast, Inc. v. State, Department of Transportation

In Spiniello Constr. Co. v. Manchester, supra at 544-45, the court found that the bidding process was compromised where one bidder was allowed to submit a discounted, combined bid, precluding all bidders from bidding on equal terms.

Summary of this case from Metro. Dist. v. Resources Reco. Auth.

In Spiniello, supra, standing existed where the successful bidder was unilaterally afforded the chance to offer a combined bid on several projects, and that opportunity was unknown to the other bidders.

Summary of this case from AAIS CORP. v. DEPARTMENT OF ADMIN. SER.

In Spiniello, our Supreme Court discussed competitive bidding in a case in which a municipality provided information to one bidder that had not been provided to other bidders.

Summary of this case from The Hartford Rfg. Co. v. T. of Thompson

In Spiniello Construction Co. v. Manchester, 189 Conn. 539 (1983), however, the court created an exception to this standing rule.

Summary of this case from Hartford Fed. of Teachers v. Bd. of Ed.

In Spiniello, supra, the municipality had imparted certain information to one bidder that it had not provided to other [the] other.

Summary of this case from Rustad v. Unlimited Plumbing Heating

In Spiniello, the town was accepting bids for two separate contracts, Contract 2 and Contract 3. The determination to confer standing on the plaintiff therein was based on allegations indicating that one bidder was given special advantages and was privy to secret information.

Summary of this case from Rustad v. Unlimited Plumbing Heating

In Spiniello Construction Co., v. Manchester, 189 Conn. 539 (1983), the court noted that "[i]t is a well established principle that `[m]unicipal competitive bidding laws are enacted to guard against such evils as favoritism, fraud or corruption in the award of contracts, to secure the best product at the lowest price, and to benefit the taxpayers, not the bidders; they should be construed to accomplish these purposes fairly and reasonably with sole reference to the public interest."

Summary of this case from Premier Roofing v. Dep't of Pub. Works
Case details for

Spiniello Const. Co. v. Manchester

Case Details

Full title:SPINIELLO CONSTRUCTION COMPANY v. TOWN OF MANCHESTER ET AL

Court:Supreme Court of Connecticut

Date published: Mar 22, 1983

Citations

189 Conn. 539 (Conn. 1983)
456 A.2d 1199

Citing Cases

Elec. Contractors, Inc. v. Dep't of Educ.

Id., at 187, 740 A.2d 813. To the extent Justice Harper suggests otherwise, we emphasize that Associated…

Electrical Conrs. v. State Dept.

In this case, the defendants have challenged the plaintiffs' standing to bring this action under the…