From Casetext: Smarter Legal Research

R/S Associates v. New York Job Development Authority

Court of Appeals of the State of New York
Apr 30, 2002
98 N.Y.2d 29 (N.Y. 2002)

Summary

holding that unless the court finds ambiguity, evidence outside the four corners of the contract is generally inadmissible

Summary of this case from Fluor Corp. v. Citadel Equity Fund Ltd.

Opinion

54

Decided April 30, 2002.

APPEAL, by permission of the Court of Appeals, from an order of the Appellate Division of the Supreme Court in the Second Judicial Department, entered March 26, 2001, which, to the extent appealed from, affirmed an order of the Supreme Court (Howard Berler, J.), entered in Suffolk County, granting a motion by defendant for summary judgment dismissing the complaint, and dismissing the complaint.

R/S Assoc. v. New York Job Dev. Auth, 281 A.D.2d 608, affirmed.

Sanford F. Young, for appellants.

David A. Schulz, for respondent.

Chief Judge Kaye and Judges Smith, Levine, Ciparick, Rosenblatt and Graffeo concur.


Order affirmed, with costs.

At issue here is the interpretation of the term "effective cost of funds" in a loan agreement between R/S Associates and the New York Job Development Authority. Because the term is not ambiguous as used in this agreement, we affirm.

The New York Job Development Authority (JDA) is a public benefit corporation created by constitutional amendment in 1961 (L 1961, ch 443, § 2). Its purpose is to "assist, promote, encourage, develop and advance the general prosperity and economic welfare of the people of the state and improve their standard of living" (Public Authorities Law § 1803). The JDA pursues this goal by providing loans and loan guarantees to help businesses expand or build facilities in New York or acquire equipment for use in this state (See id. at § 1803[2]). Borrowers from the JDA generally do not have access to more traditional funding sources.

Unlike a typical commercial lender, the JDA operates as a conduit funding organization. It finances loans through the sale of either taxable or tax-exempt long-term bonds, guaranteed by the State (see Public Authorities Law § 1813). The JDA is self-supporting; all of its operating and administrative expenses — including any loan defaults — are funded through payments made by borrowers.

R/S Associates, a real estate holding company, and Ittco Sales Co., Inc., a manufacturer and distributor of automotive accessories (together "R/S"), have common ownership. With Ittco Sales Co. as guarantor, R/S Associates sought and obtained a commercial loan from the JDA to purchase land and construct a facility in Ronkonkoma, New York. In 1986, the JDA approved a $332,500 loan to R/S Associates, which closed two years later. The loan was funded, along with other loans to other borrowers, through the issuance of a variable rate, tax-exempt bond in the principal amount of $24,610,000. The loan agreement provided that "the rate to be charged by the JDA may be revised from time to time but will not exceed one and one half (1½%) percent over JDA's effective cost of funds."

After making regular payments on the loan for over a decade, R/S filed a putative class action complaint alleging breach of contract and fraud. R/S claimed that the JDA, in its calculation of the "effective cost of funds" under the loan agreement, improperly included the cost of defaults by other borrowers. In its view, that term includes only the interest rate on the bond sold to finance the loan and the direct costs of issuing that bond, such as the cost of bond counsel, underwriters and letters of credit. R/S sought class certification; the JDA cross-moved for summary judgment dismissing the complaint. R/S then countered with its own motion for partial summary judgment on the issue of liability.

Supreme Court dismissed the complaint. The court held that the JDA properly recovers its operating costs through the interest it charges to borrowers, and that the term "effective cost of funds" includes the interest rate on the bond, the cost of issuance and the cost of defaults by other borrowers. The Appellate Division affirmed, noting only that because the term "effective cost of funds" in this agreement is unambiguous "the rules governing the construction of ambiguous contracts were not triggered" ( 281 A.D.2d 608). We agree.

We have long adhered to the "sound rule in the construction of contracts, that where the language is clear, unequivocal and unambiguous, the contract is to be interpreted by its own language" (Springsteen v. Samson, 32 N.Y. 703, 706 [citing Rodgers v Kneeland, 10 Wend 218 (1833)]). We recently reaffirmed this principle, noting that "`when parties set down their agreement in a clear, complete document, their writing should as a rule be enforced according to its terms'" (Reiss v. Financial Performance Co., 97 N.Y.2d 195, 198 [quoting W.W.W. Assocs. Inc. v. Giancontieri, 77 N.Y.2d 157, 162 (1990)]).

In this loan agreement, the contract term "effective cost of funds" is unambiguous. Under its ordinary usage, the "effective" cost of the funds means the "actual" cost of securing such funds for a specific loan (see e.g. Oxford English Dictionary, Vol V at 80 [2d ed 1989] [defining "effective" as "actual" or "existing in fact"]). Regardless of borrower defaults, the JDA's funding mechanism required it to repay the underlying bond when due. Thus, the "actual" or "effective" cost of the funds loaned by the JDA necessarily included the interest it had to pay to bondholders, the cost of issuing the bond and the cost of defaults by the borrowers who received loans from bond proceeds. Any other interpretation of this agreement would ignore the import of "effective" in modifying "cost of funds." The "[l]oss engendered by defaulting borrowers is a readily perceivable risk for any lender, which [the JDA] was entitled to consider in calculating the interest rate charged to [R/S]" (B R Children's Overalls Co. v. New York Job Development Authority, 257 A.D.2d 368 [1st Dept], lv denied 93 N.Y.2d 810).

Because the contract term is unambiguous in this context we need not address R/S' remaining arguments, based on offers of extrinsic evidence. Unless the court finds ambiguity, the rules governing the interpretation of ambiguous contracts do not come into play (see Wallace v. 600 Partners Co., 86 N.Y.2d 543, 548; Breed v. Insurance Co. of North Am., 46 N.Y.2d 351, 355). Thus, when interpreting an unambiguous contract term "[e]vidence outside the four corners of the document * * * is generally inadmissible to add to or vary the writing" (W.W.W. Assocs. Inc., 77 N.Y.2d at 162). "'[E]xtrinsic and parol evidence is not admissible to create an ambiguity in a written agreement which is complete and clear and unambiguous upon its face" (id. [quoting Intercontinental Planning v. Daystrom, Inc., 24 N.Y.2d 372, 379;see Reiss, 97 N.Y.2d at 199).

Accordingly, the order of the Appellate Division should be affirmed, with costs.

Order affirmed, with costs.


Summaries of

R/S Associates v. New York Job Development Authority

Court of Appeals of the State of New York
Apr 30, 2002
98 N.Y.2d 29 (N.Y. 2002)

holding that unless the court finds ambiguity, evidence outside the four corners of the contract is generally inadmissible

Summary of this case from Fluor Corp. v. Citadel Equity Fund Ltd.

holding that unless the court finds ambiguity, evidence outside the four corners of the contract is generally inadmissible

Summary of this case from Wilmington Sav. Fund Soc'y v. iHeartcommunications, Inc. (In re iHeartmedia, Inc.)

finding that under New York law (which governs the agreements here), where a contract's "language is clear, unequivocal and unambiguous, the contract is to be interpreted by its own language"

Summary of this case from Jose Luis Pelaez, Inc. v. Pearson Educ., Inc.

affirming the "sound rule" that "when parties set down their agreement in a clear, complete document, their writing should . . . be enforced according to its terms"

Summary of this case from Volvo Grp. N. Am. v. Forja De Monterrey S.A. de C.V.

consulting the Oxford English Dictionary to determine the plain and ordinary meaning of a contract term

Summary of this case from Phila. Indem. Ins. Co. v. Indian Harbor Ins. Co.

consulting the Oxford English Dictionary to determine the plain and ordinary meaning of a contract term

Summary of this case from Read Prop. Grp. LLC v. Hamilton Ins. Co.

noting that "when parties set down their agreement in a clear, complete document, their writing should as a rule be enforced according to its terms"

Summary of this case from Union Cent. Life Ins. Co. v. Berger

relying on dictionary definition of "effective" in construing the contractual phrase "effective cost of funds"

Summary of this case from Citadel Equity Fund Ltd. v. Aquila, Inc.

reaffirming that where contract language is "clear, unequivocal and unambiguous" it should be interpreted to give effect to the language

Summary of this case from Branic Int'l. Rlty. Corp. v. 103 Broadway Corp.

In R/S Assoc. v. New York Job Dev. Auth. (98 NY2d 29) the issue was the interpretation of the term "effective cost of funds" in a loan agreement.

Summary of this case from YUE-SAI KAN v. COTY INC.
Case details for

R/S Associates v. New York Job Development Authority

Case Details

Full title:R/S ASSOCIATES et al., Appellants, v. NEW YORK JOB DEVELOPMENT AUTHORITY…

Court:Court of Appeals of the State of New York

Date published: Apr 30, 2002

Citations

98 N.Y.2d 29 (N.Y. 2002)
744 N.Y.S.2d 358
771 N.E.2d 240

Citing Cases

JA Apparel Corp. v. Abboud

Third, they apply the rule "that a court should not adopt an interpretation which will operate to leave a…

FASHION BUG No. 2100 v. 425 W. MAIN ASSOC.

W.W.W. Associates, Inc. v. Giancontieri, 77 NY2d 157, 162 (1990). See also R/S Assoc. v. New York Job…