From Casetext: Smarter Legal Research

Peter Scalamandre & Sons, Inc. v. FC 80 Dekalb Associates, LLC

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Jun 10, 2015
129 A.D.3d 807 (N.Y. App. Div. 2015)

Summary

holding that, where contractual provision was not a condition precedent setting forth the consequences of a failure to strictly comply, substantial compliance with the provision will suffice

Summary of this case from Danco Elec. Contractors, Inc. v. Dormitory Auth. of State

Opinion

2013-09200

06-10-2015

PETER SCALAMANDRE & SONS, INC., respondent-appellant, v. FC 80 DEKALB ASSOCIATES, LLC, et al., appellants-respondents.

Olshan Frome Wolosky LLP, New York, N.Y. (Alexander Ferrini III and Peter M. Sartorius of counsel), for appellants-respondents. Goetz Fitzpatrick LLP, New York, N.Y. (Peter Goetz and Bernard Kobroff of counsel), for respondent-appellant.


Olshan Frome Wolosky LLP, New York, N.Y. (Alexander Ferrini III and Peter M. Sartorius of counsel), for appellants-respondents.

Goetz Fitzpatrick LLP, New York, N.Y. (Peter Goetz and Bernard Kobroff of counsel), for respondent-appellant.

RANDALL T. ENG, P.J., L. PRISCILLA HALL, JEFFREY A. COHEN, and BETSY BARROS, JJ.

Opinion In an action, inter alia, to recover damages for breach of contract, the defendants appeal, as limited by their brief, from so much of an order of the Supreme Court, Kings County (Schmidt, J.), dated June 11, 2013, as denied those branches of their cross motion which were for summary judgment dismissing the second and third causes of action of the second amended complaint, and the fourth cause of action of the second amended complaint to the extent of reducing the amount of a mechanic's lien dated June 21, 2010, and the plaintiff cross-appeals from so much of the same order as denied its motion for summary judgment on the second and fourth causes of action of the second amended complaint.

ORDERED that the order is affirmed insofar as appealed and cross-appealed from, without costs or disbursements.

The defendant FC 80 Dekalb Associates, LLC (hereinafter Dekalb), is the owner of a 34–story residential tower in Brooklyn. Pursuant to a trade contract dated May 13, 2008, the plaintiff, Peter Scalamandre & Sons, Inc., agreed to furnish and install the concrete superstructure for the project. The plaintiff commenced this action against Dekalb to recover damages for breach of contract, and filed a mechanic's lien on the subject property in the sum of $3,494,555. Dekalb's surety filed a bond discharging the lien, and the plaintiff amended the complaint to add the surety as a defendant. The second and third causes of action of the second amended complaint, which are relevant here, sought recovery for certain additional work allegedly directed by Dekalb and for expenses occasioned by delays attendant to that work. The fourth cause of action of the second amended complaint sought foreclosure of the mechanic's lien.

The plaintiff moved for summary judgment on the second and fourth causes of action of the second amended complaint in the sum of $639,110.40, relying on the contractual unit price fixed for additional reinforcing steel bars (hereinafter rebar) and a document prepared by a structural engineer which calculated the amount of extra rebar required on the project. The defendants cross-moved, inter alia, for summary judgment dismissing the second and third causes of action of the second amended complaint, and the fourth cause of action of the second amended complaint to the extent of reducing the mechanic's lien to the amount sought by the plaintiff in the first cause of action of the second amended complaint. The defendants contended that the plaintiff waived recovery pursuant to the second and third causes of action of the second amended complaint, and full recovery pursuant to the fourth cause of action of the second amended complaint, by failing to comply with the notice of claim procedures set forth in Article 8 of the General Conditions of the contract and by executing a mechanic's lien waiver dated July 6, 2010. The Supreme Court denied the motion and the cross motion. The defendants appeal and the plaintiff cross-appeals.

Where a construction contract contains “a condition precedent-type notice provision setting forth the consequences of a failure to strictly comply,” strict compliance will be required (Northgate Elec. Corp. v. Barr & Barr, Inc., 61 A.D.3d 467, 468–469, 877 N.Y.S.2d 36 ; see A.H.A. Gen. Constr. v. New York City Hous. Auth., 92 N.Y.2d 20, 677 N.Y.S.2d 9, 699 N.E.2d 368 ; Phoenix Signal & Elec. Corp. v. New York State Thruway Auth., 90 A.D.3d 1394, 1396–1397, 935 N.Y.S.2d 201 ; Kingsley Arms, Inc. v. Sano Rubin Constr. Co., 16 A.D.3d 813, 791 N.Y.S.2d 196 ; Promo–Pro Ltd. v. Lehrer McGovern Bovis, 306 A.D.2d 221, 761 N.Y.S.2d 655 ; Morelli Masons, Inc. v. Peter Scalamandre & Sons, Inc., 294 A.D.2d 113, 742 N.Y.S.2d 6 ). Here, Article 8 of the General Conditions of the contract contains such a condition-precedent type notice provision, providing that the plaintiff's failure to give written notice of a claim and detailed statements of the claim within the time specified shall constitute a waiver of such claim. The plaintiff concedes that it did not strictly comply with the notice provisions of Article 8. It contends, however, that its claims for extra work and delay damages asserted in the second and third causes of action are claims for “work ordered pursuant to Article 4” and, thus, are not subject to the specific notice requirements and waiver provisions of Article 8.

Although the contract required that changes to the work be authorized by the owner by written change order, “ ‘[u]nder New York law, oral directions to perform extra work, or the general course of conduct between the parties, may modify or eliminate contract provisions requiring written authorization or notice of claims' ” (Barsotti's, Inc. v. Consolidated Edison Co. of N.Y., 254 A.D.2d 211, 212, 680 N.Y.S.2d 88, quoting United States v. Merritt–Meridian Constr. Corp., 890 F.Supp. 1213, 1220 [S.D.N.Y.], aff'd in relevant part 95 F.3d 153 [2nd Cir.] ; see Penava Mech. Corp. v. Afgo Mech. Servs., Inc., 71 A.D.3d 493, 896 N.Y.S.2d 349 ). Provisions requiring written authorization for extra work are waived where “the conduct of the parties demonstrates an indisputable mutual departure from the written agreement and the changes were clearly requested by [the owner] and executed by [the contractor]” (Austin v. Barber, 227 A.D.2d 826, 828, 642 N.Y.S.2d 972 ; see DHE Homes, Ltd. v. Jamnik, 121 A.D.3d 744, 994 N.Y.S.2d 349 ; CNP Mech., Inc. v. Allied Bldrs., Inc., 84 A.D.3d 1748, 922 N.Y.S.2d 688 ; Spectrum Painting Contr., Inc. v. Kreisler Borg Florman Gen. Constr. Co., Inc., 64 A.D.3d 565, 575, 883 N.Y.S.2d 262 ; Tridee Assoc. v. New York City School Constr. Auth., 292 A.D.2d 444, 739 N.Y.S.2d 179 ). Here, the defendants failed to submit evidence concerning the parties' course of conduct pertaining to written work change orders. Accordingly, they failed to meet their prima facie burden of establishing that the strict notice of claim provisions of Article 8 applied to the subject claims (see Winegrad v. New York Univ. Med. Ctr., 64 N.Y.2d 851, 853, 487 N.Y.S.2d 316, 476 N.E.2d 642 ).

Alternatively, the defendants contend that, even if Article 4, referable to work change orders, applied to these claims, the plaintiff waived them by failing to comply with the notice of claim provision in Article 4. However, the notice of claim provision in Article 4 is not a condition-precedent type notice provision setting forth the consequences of a failure to strictly comply. Thus, substantial compliance with the notice provision will suffice (see Southeast Mech. Corp. v. Board of Educ. of Carmel Cent. School Dist., 49 A.D.3d 858, 854 N.Y.S.2d 481 ; Trataros

Constr., Inc. v. New York City Hous. Auth., 34 A.D.3d 451, 823 N.Y.S.2d 534 ; Abax, Inc. v. Lehrer McGovern Bovis, Inc., 8 A.D.3d 92, 778 N.Y.S.2d 149 ; G. De Vincentis & Son Constr. v. City of Oneonta, 304 A.D.2d 1006, 759 N.Y.S.2d 216 ; Clifford R. Gray Inc. v. City School Dist. of Albany, 277 A.D.2d 843, 846, 716 N.Y.S.2d 795 ). Substantial compliance will be found where there is sufficient correspondence between the parties to give the owner actual notice of the claims (see Abax, Inc. v. Lehrer McGovern Bovis, Inc., 8 A.D.3d 92, 778 N.Y.S.2d 149 ; G. De Vincentis & Son Constr. v. City of Oneonta, 304 A.D.2d 1006, 759 N.Y.S.2d 216 ; Clifford R. Gray, Inc. v. City School Dist. of Albany, 277 A.D.2d at 846, 716 N.Y.S.2d 795 ). The defendants failed to meet their prima facie burden of establishing that Dekalb did not have timely actual notice of the plaintiff's claims sufficient to satisfy the notice of claim provision in Article 4 (see Winegrad v. New York Univ. Med. Ctr., 64 N.Y.2d at 853, 487 N.Y.S.2d 316, 476 N.E.2d 642 ).

Additionally, the record reflects that the mechanic's lien waiver dated July 6, 2010, was treated by the parties as a mere receipt of the amounts stated, and that the waiver was not intended to encompass or preclude claims that the plaintiff subsequently presented to the defendants for additional work. The defendants, on their motion, failed to demonstrate that the parties treated the waiver otherwise (see Global Precast, Inc. v. Stonewall Contr. Corp., 78 A.D.3d 432, 911 N.Y.S.2d 292 ; Penava Mech. Corp. v. Afgo Mech. Servs., Inc., 71 A.D.3d at 495, 896 N.Y.S.2d 349 ; Spectrum Painting Contrs., Inc. v. Kreisler Borg Florman Gen. Constr. Co., Inc., 64 A.D.3d at 578, 883 N.Y.S.2d 262 ; E–J Elec. Installation Co. v. Brooklyn Historical Socy., 43 A.D.3d 642, 841 N.Y.S.2d 294 ; West End Interiors v. Aim Constr. & Contr. Corp., 286 A.D.2d 250, 252, 729 N.Y.S.2d 112 ; Orange Steel Erectors v. Newburgh Steel Prods., 225 A.D.2d 1010, 640 N.Y.S.2d 283 ). Accordingly, the Supreme Court properly denied those branches of the defendants' cross motion which were for summary judgment dismissing the second and third causes of action of the second amended complaint, and the fourth cause of action of the second amended complaint to the extent of reducing the mechanic's lien.

In light of the existence of triable issues of fact regarding the plaintiff's waiver of its claims, the Supreme Court also properly denied the plaintiff's motion for summary judgment on the second and fourth causes of action of the second amended complaint. Moreover, the plaintiff failed to demonstrate that Dekalb should be bound by the structural engineer's calculation of the amount of rebar required on the project (see generally Loschiavo v. Port Auth. of N.Y. & N.J., 58 N.Y.2d 1040, 1041, 462 N.Y.S.2d 440, 448 N.E.2d 1351 ).

Finally, since the defendants have viable counterclaims to recover damages for the plaintiff's alleged breach of contract arising from the same transaction, the award of summary judgment to the plaintiff on the second and fourth causes of action of the second amended complaint would be improper (see Hayward Baker, Inc. v. C.O. Falter Constr. Corp., 104 A.D.3d 1253, 960 N.Y.S.2d 764 ; Yoi–Lee Realty Corp. v. 177th St. Realty Assoc., 208 A.D.2d 185, 189, 626 N.Y.S.2d 61 ).


Summaries of

Peter Scalamandre & Sons, Inc. v. FC 80 Dekalb Associates, LLC

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Jun 10, 2015
129 A.D.3d 807 (N.Y. App. Div. 2015)

holding that, where contractual provision was not a condition precedent setting forth the consequences of a failure to strictly comply, substantial compliance with the provision will suffice

Summary of this case from Danco Elec. Contractors, Inc. v. Dormitory Auth. of State
Case details for

Peter Scalamandre & Sons, Inc. v. FC 80 Dekalb Associates, LLC

Case Details

Full title:Peter Scalamandre & Sons, Inc., respondent-appellant, v. FC 80 Dekalb…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department

Date published: Jun 10, 2015

Citations

129 A.D.3d 807 (N.Y. App. Div. 2015)
12 N.Y.S.3d 133
2015 N.Y. Slip Op. 4829

Citing Cases

Misty Cleaning Servs. v. Indep. Grp. Home Living Program

Misty Cleaning established its prima facie entitlement to judgment as a matter of law dismissing the…

Schindler Elevator Corp. v. Tully Constr. Co.

"Where a construction contract contains a condition precedent-type notice provision setting forth the…