Summary

holding that a contract provision constitutes a "conditions precedent" where it explicitly sets forth penalty for failure to comply

Summary of this case from Danco Elec. Contractors, Inc. v. Dormitory Auth. of State

Opinion

953

May 2, 2002.

Order, Supreme Court, New York County (Charles Ramos, J.), entered April 11, 2001, which, inter alia, granted defendants' motion for summary judgment dismissing the third and fourth causes of action, unanimously affirmed, with costs.

GREGORY MASON, for plaintiff-appellant.

SAYWARD MAZUR, for defendants-respondents.

Before: Andrias, J.P., Sullivan, Wallach, Rubin, Gonzalez, JJ.


In this action by a subcontractor seeking delay damages from its general contractor and payment on the bond with respect to such claim, the motion court properly held that plaintiff had failed to comply strictly with the notice provision in its subcontract, which, while not containing the conditional "unless" language found in the contract inA.H.A. Gen. Constr., Inc. v. New York City Hous. Auth. ( 92 N.Y.2d 20), specifically provided that the failure to comply with such provision would constitute a waiver of the subcontractor's claim for damages.Barsotti's, Inc. v. Consolidated Edison Co. of New York ( 254 A.D.2d 211), which involved a claim for extra work under a private contract, is distinguishable. In addition, contrary to plaintiff's argument, here there was no clear relinquishment of the right to rely on the contractual provision by an indisputable departure based on a course of conduct or oral agreement (cf., Austin v. Barber, 227 A.D.2d 826, 828).

We deem it significant, as did the motion court, that plaintiff did not comply in any manner with the separate contractual requirement to itemize the costs attributable to the alleged delays, and note that this was also a basis for dismissal.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

Masons, Inc. v. Scalamandre

Appellate Division of the Supreme Court of New York, First Department
May 2, 2002
294 A.D.2d 113 (N.Y. App. Div. 2002)

holding that a contract provision constitutes a "conditions precedent" where it explicitly sets forth penalty for failure to comply

Summary of this case from Danco Elec. Contractors, Inc. v. Dormitory Auth. of State

observing that the notice clause "specifically provided that the failure to comply with such provision would constitute a waiver of the subcontractor's claim for damages"

Summary of this case from Superior Site Work, Inc. v. Nasdi, LLC

observing that the notice clause "specifically provided that the failure to comply with such provision would constitute a waiver of the subcontractor's claim for damages"

Summary of this case from Mendelsohn v. Port Auth. Trans-Hudson Corp.

In Morelli Masons, Inc., the court stated that a notice requirement for extra work must be given effect because "there was no clear relinquishment of the right to rely on the contractual provision by an indisputable departure based on a course of conduct or oral agreement."

Summary of this case from Comm. Elec. Contrs., Inc. v. Pavarini Constr. Co.
Case details for

Masons, Inc. v. Scalamandre

Case Details

Full title:MORELLI MASONS, INC., PLAINTIFF-APPELLANT, v. PETER SCALAMANDRE SONS…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: May 2, 2002

Citations

294 A.D.2d 113 (N.Y. App. Div. 2002)
742 N.Y.S.2d 6

Citing Cases

Danco Elec. Contractors, Inc. v. Dormitory Auth. of State

A condition precedent may also be shown where the contract explicitly sets forth that a party's failure to…

Namasco Corp. v. N. Y. Hotel Trade Coun.

The court affirmed dismissal of the complaint for failure to comply with this provision (id. at 222). It…