From Casetext: Smarter Legal Research

KKMI Sausalito, LLC v. Vessel "Self Inflicted"

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA
Dec 20, 2019
428 F. Supp. 3d 200 (N.D. Cal. 2019)

Opinion

Case No. 19-cv-02850-KAW

2019-12-20

KKMI SAUSALITO, LLC, Plaintiff, v. The VESSEL "SELF INFLICTED", Defendant.

Richard John Alexander, Richard Alexander Law Offices, Point Richmond, CA, for Plaintiff.


Richard John Alexander, Richard Alexander Law Offices, Point Richmond, CA, for Plaintiff.

ORDER GRANTING MOTION FOR DEFAULT JUDGMENT

Re: Dkt. No. 24

KANDIS A. WESTMORE, United States Magistrate Judge

On May 23, 2019, Plaintiff KKMI Sausalito, LLC filed this admiralty and maritime action in rem against Defendant Vessel "Self Inflicted," Documentation No. 1064308. (Compl., Dkt. No. 1.) Plaintiff alleges that between June 29, 2017 and May 22, 2019, the Vessel incurred repairs, hull maintenance, and storage charges at Plaintiff's boatyard in Sausalito, California. (Compl. ¶¶ 6-9.) Plaintiff now seeks to foreclose a maritime lien against the Vessel, her engines, rigging, sails, boats, tackle, apparel, and furniture pursuant to the Federal Maritime Lien Act ("FMLA"), 46 U.S.C. § 31342, and seeks a judgment condemning the Vessel and an order for its sale to pay the outstanding amount owed.

On October 4, 2019, Plaintiff filed a motion for default judgment. (Mot., Dkt. No. 24.) On December 19, 2019, the Court held a hearing on Plaintiff's motion for default judgment, at which no potential claimants appeared. For the reasons set forth below, the Court GRANTS Plaintiff's motion for default judgment.

I. BACKGROUND

Defendant Vessel is a steel-hulled recreational sailing vessel, approximately 48' in length. (Compl. ¶ 3.) On June 29, 2017, the Vessel's owner, Daniel A. Morgan, entered into a Service Agreement with Plaintiff for repair and hull maintenance work at Plaintiff's Sausalito boatyard. (Compl. ¶ 5.)

Between June 29, 2017 and November 12, 2018, the Vessel incurred repair charges for labor and parts in the amount of $15,748.13. (Compl. ¶ 6; Kaplan Decl. ¶ 6, Dkt. No. 24-1.) Payments of $6,590.00 were made, leaving a balance due of $9,158.13 as of November 12, 2018. (Compl. ¶ 6; Kaplan Decl. ¶ 6.) No further payments were made, despite demands from Plaintiff. (Compl. ¶ 7; Kaplan Decl. ¶ 7.) Pursuant to the Service Agreement, a vessel storage charge was applied at the usual and customary daily storage rate of $3.00 per foot of boat length, or $144.00 per day. (Compl. ¶ 7; Kaplan Decl. ¶ 7.) Between November 13, 2018 and May 22, 2019 – the date the complaint was verified by Plaintiff – the Vessel incurred daily storage charges of $144.00 for 191 days, for a total unpaid storage charge of $27,504.00. (Compl. ¶ 7; Kaplan Decl. ¶ 8.)

Plaintiff then filed the instant in rem action, asserting a maritime lien against the Vessel, her engines, rigging, sails, boats, tackle, apparel, and furniture pursuant to 46 U.S.C. § 31341(a)(1) and general maritime law. (Compl. ¶ 13.)

On May 31, 2017, the Court approved Plaintiff's proposed warrant of arrest, ordering that the warrant be issued for the arrest of the Vessel, which the Clerk of the Court issued. (Dkt. Nos. 11, 12.) The Court also granted Plaintiff's Application for Appointment of a Substitute Custodian, appointing Paul Kaplan, Plaintiff's founding partner, custodian of the Vessel and authorizing the U.S. Marshal to surrender possession of the Vessel to him. (Dkt. No. 12.) The Marshal arrested and served the Vessel on June 18, 2019 at Plaintiff's boatyard in Sausalito, California. (Dkt. No. 15.) The Marshal filed the executed return of Arrest Warrant on July 23, 2019, and the executed return of the Summons on July 26, 2019. (Dkt. Nos. 15, 21.)

Plaintiff published a Notice of Action and Arrest in The Daily Journal, in compliance with Admiralty Local Rule 4-2(a), and Plaintiff filed the Proof of Publication pursuant to Admiralty Local Rule 4-2(b). (Dkt. No. 20.)

On July 24, 2019, Plaintiff requested entry of default. (Dkt. No. 18.) On July 26, 2019, the Clerk of the Court entered default. (Dkt. No. 22.) No one has appeared in this action or filed a verified statement of right of possession or ownership interest in the Vessel.

II. LEGAL STANDARD

Federal Rule of Civil Procedure 55(b)(2) permits a court to enter a final judgment in a case following a defendant's default. Shanghai Automation Instrument Co. v. Kuei , 194 F. Supp. 2d 995, 999 (N.D. Cal. 2001). Whether to enter a judgment lies within the court's discretion. Id. (citing Draper v. Coombs , 792 F.2d 915, 924-925 (9th Cir. 1986) ).

Before assessing the merits of a default judgment, a court must confirm that it has subject matter jurisdiction over the case and personal jurisdiction over the parties, as well as ensure the adequacy of service on the defendant. See In re Tuli , 172 F.3d 707, 712 (9th Cir. 1999). If the court finds these elements satisfied, it turns to the following factors ("the Eitel factors") to determine whether it should grant a default judgment:

(1) the possibility of prejudice to the plaintiff, (2) the merits of Plaintiff's substantive claim, (3) the sufficiency of the complaint, (4) the sum of money at stake in the action[,] (5) the possibility of a dispute concerning material facts[,] (6) whether the default was due to excusable neglect, and (7) the strong policy underlying the Federal Rules of Civil Procedure favoring a decision on the merits.

Eitel v. McCool , 782 F. 2d 1470, 1471-72 (9th Cir. 1986) (citation omitted).

Upon entry of default, all factual allegations in the complaint are accepted as true, except allegations relating to the amount of damages. TeleVideo Sys., Inc. v. Heidenthal , 826 F.2d 915, 917-18 (9th Cir. 1987). Where a default judgment is granted, the scope of relief "must not differ in kind from, or exceed in amount, what is demanded in the pleadings." Fed. R. Civ. P. 54(c). III. DISCUSSION

A. Magistrate Judge Jurisdiction to Enter Default Judgment

Section 636(c) confers magistrate judges the authority to enter judgment in a civil action "upon consent of the parties." Generally, the consent of all of the parties, including unserved defendants, is required for a valid judgment to be entered. Williams v. King , 875 F.3d 500, 504 (9th Cir. 2017). Here, however, the action is in rem against the Vessel. In in rem forfeiture proceedings, the Ninth Circuit has held that a putative claimant's failure to comply with the applicable filing requirements precludes standing as a party to the action, such that the property owner's consent to magistrate judge jurisdiction is not a prerequisite to the entry of default judgment against his interest in the subject property. United States v. Real Property , 135 F.3d 1312, 1316-17 (9th Cir. 1998). In Williams , the Ninth Circuit affirmed this narrow exception, such that the undersigned is vested with jurisdiction to enter judgment against the Vessel even absent the consent of the property owner. See 875 F.3d at 504. Accordingly, since the undersigned has obtained consent from the only party to the action – Plaintiff – the Court may enter default judgment.

B. Jurisdiction and Service of Process

In considering whether to enter default judgment, a district court must first determine whether it has jurisdiction over the subject matter and the parties to the case. In re Tuli , 172 F.3d 707, 712 (9th Cir. 1999) ("When the entry of judgment is sought against a party who has failed to plead or otherwise defend, a district court has an affirmative duty to look into its jurisdiction over both the subject matter and the parties.")

i. Jurisdiction

This Court has jurisdiction over this action under 28 U.S.C. § 1333, which vests district courts with original jurisdiction over "any civil case of admiralty or maritime jurisdiction." An in rem action may be brought to enforce any maritime lien, or whenever a statute of the United States provides for a maritime action to be brought in rem. Fed. R. Civ. P. Supp. C(1). Here, Plaintiff seeks to enforce a maritime lien under the Federal Maritime Lien Act ("FMLA"), 46 U.S.C. § 31342. Accordingly, the Court has subject matter jurisdiction over this action. See Ventura Packers, Inc. v. F/V Jeanine Kathleen , 305 F.3d 913, 918-23 (9th Cir. 2002) (holding that the Maritime Lien Act provides a statutory basis for the exercise of a district court's admiralty jurisdiction). The Court also has in rem jurisdiction over the Vessel because the Vessel is located within the Northern District of California, was "arrested pursuant to maritime process," and "the warrant w[as] successfully served." Ventura Packers, Inc. v. F/V Jeanine Kathleen , 424 F.3d 852, 858 (9th Cir. 2005) ; accord Fed. R. Civ. P. Supp. C(2)-(3).

ii. Venue

Venue is proper because the Court has jurisdiction over the parties, and the Vessel is located in the district. (Compl. ¶ 4.)

iii. Service of Process

The Court finds that Plaintiff has complied with the service requirements set forth in Federal Rule of Civil Procedure Supplemental Rule C(3)(b)(i). This rule provides: "If the property that is the subject of the action is a vessel or tangible property on board a vessel, the warrant and any supplemental process must be delivered to the marshal for service." Fed. R. Civ. P. Suppl. R. C(3)(b)(i). The Marshal's Process Receipt and Return shows that the Vessel's custodian was served when the Vessel was arrested on June 18, 2019. (Dkt. No. 16.)

Plaintiff has also complied with the notice requirements in Admiralty Local Rule 4-2(a) when it published notice in The Daily Journal. (Dkt. No. 20.) This rule provides:

(a) Publication. The public notice specified by Fed. R. Civ. P. Supp. C(4) shall be published once in a newspaper named in Civil L.R. 77-4, and plaintiff's attorney shall file a copy of the notice as it was published with the clerk.

The notice shall contain:

(1) The court, title, and number of the action;

(2) The date of the arrest;

(3) The identity of the property arrested;

(4) The name, address, and telephone number of the attorney for plaintiff;

(5) A statement that any person who asserts a right of possession of any ownership interest in the property pursuant to Fed. R. Civ. P. Supp. (C)(6) must file a verified statement of right or interest within 14 days of the execution of process or within the period specified by court order;

(6) A statement that any person required to file a verified statement of right or interest must also file and serve an answer to the complaint within 21 days after filing the statement of interest or right, and that otherwise, default may be entered and condemnation ordered;

(7) A statement that applications for intervention under Fed. R. Civ. P. 24 by persons claiming maritime liens or other interests against the property shall be filed within the time fixed by the court; and

(8) The name, address, and telephone number of the marshal.

The undersigned finds that the Proof of Publication conforms to Admiralty Local Rule 4-2(a)'s requirements. (See Dkt. No. 20-1.) Based upon the foregoing, the Court finds that personal service upon the Vessel was properly effected.

Pursuant to Admiralty Local Rule 6-2(b), after the entry of default, a default judgment may be entered pursuant to Federal Rule of Civil Procedure 55(b). The Court may enter default judgment upon a showing that: (1) notice has been given as required by Admir. L.R. 6-1(a)(2) and (b)(2); (2) the time to answer has expired; and (3) no one has filed a verified statement of right of possession or ownership interest in the property. Admir. L.R. 6-2(b)(1)-(3).

Admiralty Local Rule 6-1, in turn, provides in relevant part:

(a) Notice Required. A party seeking a default judgment in an action in rem must show that due notice of the action and arrest of the property has been given:

...

(2) In actions not subject to Fed. R. Civ. P. Supp. G:

(i) By publication as required in Fed. R. Civ. P. Supp. C(4);

(ii) By service upon the master or other person having custody of the property; and

(iii) By service under Fed. R. Civ. P. 5(b) upon every other person who has not appeared in the action and is known to have an interest in the property (Admir. L.R. 6-1(a)(2)).

First, Plaintiff has properly given notice in compliance with Admiralty Local Rule 6-1(a)(2)(i) by the publication of the Notice of Action and Arrest. (Dkt. No. 20.) The Notice expressly stated, in relevant part:

Any person who asserts a right to possession of any ownership interest in the foregoing vessel pursuant to Fed. R. Civ. P. Supp. C(6) must file a verified

statement of right or interest within 14 days of the last date of publication of this Notice or within the period specified by court order. Any person required to file a verified statement of right or interest must also file and serve an Answer to the Complaint within 21 days after filing the statement of interest or right, and that otherwise, default may be entered and condemnation ordered. Applications for intervention under Fed. R. Civ. P. 24 by persons claiming maritime liens or other interest against the vessel shall be filed within the time fixed by the court.

(Id. )

Plaintiff complied with Admiralty Local Rule 6-1(a)(2)(ii) by service upon Defendant Vessel and the Substitute Custodian by the Marshal. (Dkt. Nos. 16, 21.)

Plaintiff has also given notice as required under Admiralty Local Rule 6-1(a)(2)(iii) by service under Federal Rule of Civil Procedure 5(b) upon every other person who has not appeared in the action and is known to have an interest in the property. (Alexander Decl. ¶ 2, Dkt. No. 24-2.) Here, that person is Mr. Morgan. (See Kaplan Decl., Ex. 1; Alexander Decl. ¶¶ 2-3.)

Further, Admiralty Local Rule 6-1(b)(2)(i) provides that notice must be given in the case of a vessel documented under the laws of the United States, by the plaintiff attempting to notify all persons in the United States Coast Guard Certificate of Ownership. Plaintiff complied with this requirement by giving the notice as required by Admiralty Local Rule 6-1(b)(2)(i) for this documented vessel upon Mr. Morgan who has a recorded interest in the vessel (in addition to title), as well as by serving Mr. Morgan with the summons and complaint at his last known addresses, pursuant to Rule 5(b)(2)(C). (Alexander Decl. ¶¶ 2-3).

Finally, Plaintiff contends that no one has filed a verified statement of right of possession or ownership interest in the Vessel. (Mot. at 4.)

Thus, Plaintiff has satisfied each of the requirements set forth in Admiralty Local Rule 6-2(b) and has complied with the notice requirements of Admiralty Local Rule 6-1(a)(2). Further, no interested party has filed a timely verified statement asserting an interest in the Vessel. Accordingly, service was proper.

C. Application to the Case at Bar

Since the Court has jurisdiction in this matter, this Court must turn to the Eitel factors to determine whether the entering of a default judgment is appropriate in this matter.

i. Possibility of Prejudice to Plaintiff

Under the first factor, the Court must determine whether Plaintiff will be prejudiced if the Court denies its motion for default judgment. Eitel , 782 F.2d at 1471-72. Pursuant to the Service Agreement, Plaintiff provided necessaries to the Vessel, and despite demand for payment, Plaintiff has been unable to recover the outstanding amounts owed for repairs, parts, and storage charges. (Compl. ¶¶ 5-9, 12.) Thus, if the Court were to deny Plaintiff's motion, Plaintiff would be unable to recover the outstanding amounts, and further delay in securing a judgment would only increase the chances that Plaintiff will be unable to recover such amounts. Accordingly, this factor weighs in favor of default judgment. See United States v. Mare Island Sales, LLC , 2008 WL 4279406, at *2 (E.D. Cal. Sept. 16, 2008).

ii. Merits of Plaintiff's Substantive Claim and the Sufficiency of the Complaint

The second and third Eitel factors focus on the merits of Plaintiff's substantive claims and the sufficiency of the Complaint. Eitel , 782 F.2d at 1471-72. In order for these factors to weigh in Plaintiff's favor, Plaintiff must assert claims upon which it may recover. See PepsiCo, Inc. v. Cal. Sec. Cans , 238 F. Supp. 2d 1172, 1175 (C.D. Cal. 2002). Here, Plaintiff seeks to foreclose a maritime lien against the Vessel under 46 U.S.C. § 31342 based on unpaid fees for repair, hull maintenance, and storage that Plaintiff provided pursuant to the Service Agreement.

46 U.S.C. § 31342 provides:

(a) Except as provided in subsection (b) of this section, a person providing necessaries to a vessel on the order of the owner or a person authorized by the owner--

(1) has a maritime lien on the vessel;

(2) may bring a civil action in rem to enforce the lien; and

(3) is not required to allege or prove in the action that credit was given to the vessel.

(b) This section does not apply to a public vessel. 46 U.S.C. § 31342.

In order to establish a maritime lien for necessaries, a supplier must show: (1) that the goods or services were provided to the vessel; (2) that the goods or services were "necessaries"; (3) that the charges are reasonable in amount; and (4) that they were ordered by someone with the appropriate authority. Belcher Co. of Ala. v. M/V Maratha Mariner , 724 F.2d 1161, 1164 (5th Cir. 1984) ; see also Int'l Seafoods of Alaska, Inc. v. Park Ventures, Inc. , 829 F.2d 751, 753 (9th Cir. 1987) ; Farwest Steel Corp v. Barge Sea Span 241 , 769 F.2d 620, 623 (9th Cir. 1985). Plaintiff has made a sufficient showing as to each of these factors. Section 31301(4) states that " ‘necessaries’ includes repairs, supplies, towage, and the use of a dry dock or marine railway[.]" 46 U.S.C. § 31301(4). "The list is not exhaustive, and in fact, modern admiralty jurisprudence interprets ‘necessaries’ broadly, as anything that facilitates or enables a vessel to perform its mission or occupation." Ventura Packers , 305 F.3d at 923. "The term ‘necessaries’ includes most goods or services that are useful to the vessel to keep her out of danger." Id. Here, the Court finds that Plaintiff has made an adequate showing establishing the existence of a maritime lien under 46 U.S.C. § 31342.

First, Plaintiff provided repairs and hull maintenance to the Vessel pursuant to the Service Agreement from June 29, 2017 through November 12, 2018, in the amount of $15,748.13. (Compl. ¶ 6; Kaplan Decl. ¶¶ 1-6.) Of that amount, $6,590.00 was paid, leaving a balance due of $9,158.13. (Compl. ¶ 6; Kaplan Decl. ¶ 6.) The Vessel also incurred storage charges of $31,392.00 between November 13, 2018 and June 18, 2019, all of which were owed by the Owner as of the date of arrest of the Vessel. (Kaplan Decl. ¶¶ 8, 7(2) .) A total balance of $40,550.18 is now due. (Kaplan Decl. ¶ 8(2).)

There are two paragraphs 7, 8, and 9 in Mr. Kaplan's declaration.

Second, repairs and storage fees are "necessaries" under 46 U.S.C. § 31301(4). 46 U.S.C. § 31301(4) explicitly includes repairs as necessaries, and "[s]everal courts have imposed maritime liens for docking, wharfage, or storage fees...." Am. E. Dev. Corp. v. Everglades Marina, Inc. , 608 F.2d 123, 125 (5th Cir. 1979).

Third, the charges that Plaintiff seeks are reasonable and are of the type that can be expected by a boatyard providing services to a vessel over an extended period of years. See Crescent City Harbor Dist. v. M/V Intrepid , Case No. 08-cv-1007-JCS, 2008 WL 5211023, at *3 (N.D. Cal. Dec. 11, 2008). Finally, Mr. Morgan procured the services when he executed the Service Agreement. (Kaplan Decl., Exh. 2.) Thus, under 46 U.S.C. § 31341(a)(1), as the owner of the vessel, Mr. Morgan is statutorily presumed to have authority to procure necessaries for it. Taken together, the Court finds that Plaintiff has sufficiently established the existence of a maritime lien under 46 U.S.C. § 31342.

iii. Sum of Money at Stake

The fourth Eitel factor assesses the reasonableness of the potential award if a default judgment is entered. In making this assessment, the Court must take into account the amount of money at stake in relation to the seriousness of Defendant's conduct. Eitel , 782 F.2d at 1471. If the sum of money at issue is reasonably proportionate to the harm caused by Defendant's actions, properly documented, and contractually justified, then default judgment is warranted. Bd. of Trs. of Cal. Metal Trades v. Pitchometer Propeller , Case No. 97-cv-2661-VRW, 1997 WL 797922, at *2 (N.D. Cal. Dec. 15, 1997). A default judgment is only disfavored when a large amount of money is involved or is unreasonable in light of Defendant's actions. Truong Giang Corp. v. Twinstar Tea Corp. , Case No. 06-cv-3594-JSW, 2007 WL 1545173, at *12 (N.D. Cal. May 29, 2007). In determining if the amount at stake is reasonable, the Court may consider Plaintiff's declarations, calculations, and other documentation of damages. Id.

Here, Plaintiff seeks judgment against the Vessel in the amount of $40,550.18, the amounts owed for repairs, hull maintenance, and storage under the Service Agreement while at Plaintiff's boatyard. (Kaplan Decl. ¶ 9(2).) Plaintiff also seeks authorization to be allowed its "custodius legis " costs (pursuant to cost bill to be filed post-judgment). (Mot. at 7.) Thus, the sum Plaintiff seeks is directly related to the Vessel's repairs and storage and the amounts due pursuant to the parties' Service Agreement while the vessel was stored at Plaintiff's boatyard. This factor weighs in favor of default judgment.

iv. Possibility of a Material Factual Dispute

The fifth Eitel factor examines the likelihood of dispute between the parties regarding the material facts surrounding the case. Eitel , 782 F.2d at 1471-72. Upon defaulting, the defendant is "deemed to have admitted all well-pleaded factual allegations" in the complaint. DirecTV, Inc. v. Hoa Huynh , 503 F.3d 847, 851 (9th Cir. 2007) (citations omitted). Here, Plaintiff seeks to recover repairs, hull maintenance, and storage charges pursuant to the Service Agreement. (Kaplan Decl. ¶¶ 6, 8-9, 7(2)-8(2).) The amounts directly correlate to those agreed upon in the parties' Service Agreement, and Plaintiff has provided an itemized breakdown of the payments that remain outstanding. (See id. ) Thus, there is little likelihood of a dispute concerning the material facts in support of Plaintiff's complaint, such that this factor weighs in favor of default judgment.

v. Whether Default Was the Result of Excusable Neglect

The sixth Eitel factor examines whether any interested party's failure to respond to Plaintiff's allegations was the result of excusable neglect. Eitel , 782 F.2d at 1471-72. As set forth above, Plaintiff provided notice by publication pursuant to Admiralty Local Rule 6-1(a)(2). Mr. Morgan, the owner of the Vessel, was also served with the complaint and summons at three separate addresses, including addresses provided to the Coast Guard and Plaintiff. (Alexander Decl. ¶ 2.) Nevertheless, despite ample time and opportunity, neither Mr. Morgan nor any other interested person filed an answer or otherwise challenged the motion for default judgment. There is nothing in the record suggesting that any individual's failure to appear and litigate this matter is based on excusable neglect. Shanghai Automation Instrument Co. v. Kuei , 194 F. Supp. 2d 995, 1005 (N.D. Cal. 2001) (default after proper service was not excusable neglect). Thus, this factor weighs in favor of granting default judgment.

vi. Strong Public Policy Favoring Decisions on the Merits

The final Eitel factor examines whether the policy of deciding a case based on the merits precludes entry of default judgment. Eitel , 782 F.2d at 1471-72.

Notwithstanding, after an examination of these facts in the aggregate, the undersigned finds that Eitel factors one through six outweigh the Federal Rules of Civil Procedure's preference for a decision on the merits, thereby rendering the entry of default judgment proper.

IV. RELIEF SOUGHT

After entry of default, well-pleaded factual allegations in the complaint are taken as true, except as to the amount of damages. Fair Hous. of Marin v. Combs , 285 F.3d 899, 906 (9th Cir. 2002). To recover damages after securing a default judgment, a plaintiff must prove the relief it seeks through testimony or written affidavit. Bd. of Trs. of the Boilermaker Vacation Trust v. Skelly, Inc. , 389 F. Supp. 2d 1222, 1226 (N.D. Cal. 2005) ; see PepsiCo, Inc. , 238 F. Supp. 2d at 1175 (citing TeleVideo Sys., Inc. , 826 F.2d at 917-18 ).

A. Damages

Plaintiff seeks judgment against the Vessel in the amount of $40,550.13 to compensate it for unpaid repair and storage charges. (Mot. at 3; Kaplan Decl. ¶¶ 6-9, 7(2)-9(2).) Plaintiff further requests that the Vessel be condemned and ordered sold by the U.S. Marshal, and that such sale be conducted in accordance with general maritime law and local admiralty rules and procedures for the purposes of satisfying the default judgment requested. (Mot. at 7.)

For the reasons set forth above, the Court finds that Plaintiff is entitled to default judgment on its maritime lien in the amount of $40,550.13. Accordingly, Plaintiff's request to foreclose the lien is granted, and the Vessel shall be condemned and sold by the U.S. Marshal at public auction.

B. Costs

Plaintiff requests an award of its custodia legis costs and that it be permitted to "credit bid" up to its judgment amount at any subsequent U.S. Marshal-conducted auction. (Mot. at 7.) At the hearing, Plaintiff explained it intends to seek such costs by filing a separate bill of costs. With respect to Plaintiff's request to use its custodia legis costs, the Court finds that Plaintiff is entitled to such costs, provided Plaintiff substantiates the amount claimed. (See Mot. at 7.)

As to Plaintiff's request that it be allowed to credit bid, the local admiralty rules governing payment of bids at public auction sales, provide that, "a plaintiff ... foreclosing a properly recorded preferred mortgage on, or other valid security interest in the vessel may bid, without payment of cash, certified check or cashier's check, up to the total amount of the secured indebtedness as established by affidavit filed and served by that party on all other parties no later than 14 days prior to the date of sale." Admir. L. R. 9-2(b). Provided that Plaintiff complies with the notice requirements set forth in Admiralty Local Rule 9-2, the undersigned grants Plaintiff's request for an order permitting it to credit bid up to its judgment amount be granted. V. CONCLUSION

For the reasons set forth above, the Court:

1. GRANTS Plaintiff's Motion for Default Judgment against the Vessel "Self Inflicted" (U.S. Documentation No. 1064308), her engines, rigging, sails, boats, tackle, apparel, and furniture in the amount of $40,550.13, and custodia legis costs (pursuant to a cost bill to be filed post-judgment);

2. That Plaintiff shall recover the amount of its judgment from the foreclosure of its maritime lien against the Vessel "Self Inflicted," which the Court ORDERS be accomplished through a public sale, to be conducted by the United States Marshal pursuant to Admiralty Local Rule 9-2, and Plaintiff is permitted to credit bid up to its judgment amount at said public sale; and

3. The Court shall retain jurisdiction of this action through the completion of the sale of the Vessel "Self Inflicted," and any related proceedings.

IT IS SO ORDERED.


Summaries of

KKMI Sausalito, LLC v. Vessel "Self Inflicted"

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA
Dec 20, 2019
428 F. Supp. 3d 200 (N.D. Cal. 2019)
Case details for

KKMI Sausalito, LLC v. Vessel "Self Inflicted"

Case Details

Full title:KKMI SAUSALITO, LLC, Plaintiff, v. THE VESSEL "SELF INFLICTED," Defendant.

Court:UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA

Date published: Dec 20, 2019

Citations

428 F. Supp. 3d 200 (N.D. Cal. 2019)

Citing Cases

Garpo Marine Servs. v. Island Romance

” KKMI Sausalito, LLC v. The Vessel “Self Inflicted, ” 428 F.Supp.3d 200, 207 (N.D. Cal. 2019). “Necessaries”…

Khraibut v. Chahal

Under the fourth Eitel factor, courts consider "the amount of money at stake in relation to the seriousness…