From Casetext: Smarter Legal Research

Henley v. Pacific Fruit Cooling and Vaporizing Co.

Court of Appeal of California, Third District
Sep 19, 1912
19 Cal.App. 728 (Cal. Ct. App. 1912)

Opinion

Civ. No. 914.

September 19, 1912.

APPEAL from a judgment of the Superior Court of Placer County, and from an order denying a new trial. J. E. Prewett, Judge.

The facts are stated in the opinion of the court.

J. Rollin Fitch, for Appellants.

Meredith Landis, for Respondent.


This is an action to recover judgment against the company above named for services rendered by plaintiff as "refrigerating and constructing engineer" in the erection of a precooling and refrigerating plant on certain described premises, situated in the town of Newcastle, Placer county, of which plant defendants are alleged to be the owners; also that plaintiff be declared to have a lien thereon and for the enforcement thereof. The court found that plaintiff was entitled to judgment against defendant company for the sum of $528.50 and costs, of which the sum of $495 was found to be a lien upon the buildings and plant of defendants, described in the complaint. Judgment passed accordingly, from which and from the order denying their motion for a new trial defendants appeal.

Quoting some advice given by the supreme court to trial courts, found in Green v. Soule, 145 Cal. 102, [ 78 P. 337], as to the duty of the trial court to grant a new trial where the decision is against the weight of the evidence, it is urged that "the decision in this case is clearly against the weight of evidence and against the law." It was said in the case cited: "The trial court cannot rest upon a conflict in the evidence, but must weigh and consider the evidence for both parties, and determine for itself the just conclusion to be drawn from it." We must assume that this is precisely what the learned trial judge did in arriving at a conclusion. And, unless, upon an examination of the entire record, we may be clearly satisfied that such conclusion was unwarranted, it is our duty to accept it and be governed by it.

There is no dispute as to the qualifications of plaintiff to perform the kind of services for which he was employed. With the exception of the testimony of the witness Jones as to the date of plaintiff's arrival at the hotel in Newcastle, a fact otherwise shown, there were but two witnesses called — plaintiff, on his own behalf, and witness Groom, the admitted agent of defendant company, in its behalf. Appellants seem to overlook the fact that "the weight of the evidence" is not dependent upon the number of witnesses. Trial courts are frequently called upon to solve questions of fact where the witnesses to its existence are equally divided numerically. But there are almost always some circumstances cropping out which enable the court to determine the truth of the matter. It appeared from the testimony of plaintiff that, in March or April, 1907, he received a letter "from the manager of the company, P. M. Groom," who was in Los Angeles, stating that he was organizing a company and wanted plaintiff to "take the position of refrigerating engineer," to which plaintiff replied that he would accept the position; that Groom answered him that he would give him $5 per day and expenses; that plaintiff was in business for himself in San Francisco, and went east, waiting orders to report; that, in the early part of November, plaintiff received a telegram from Groom to report at his office in Los Angeles, where plaintiff arrived November 10, 1907; that he immediately went to work for the company, helping to interest people in the enterprise, assisting in preparing plans, blue-prints and drawings and making estimates; that the company, after about two months, left Los Angeles and came to San Francisco, about January 14, 1908, "to commence building a plant." As to what he did for the company at San Francisco and at Newcastle he testified: "I was the engineer — I built the machine, this precooling plant that was put in at Newcastle. I was in the employ of this company all the time I was in San Francisco from about January 14th to some time in May. While in their employ in San Francisco, I superintended the building of a plant. I never done a minute's work for anybody else. Q. Now describe generally to the court the character of this plant you were engaged in, if any? A. It was a fifty-ton refrigerating plant — two machines, duplicates — two 25-tons, connecting with a belt wheel, the motor, and condenser, ammonia condenser, I made all that work, did the superintending and construction and building of these compressors and shipped them to Newcastle, and in a general way occupied about the plant as their engineer — that is, it was built under my supervision. Q. When you left San Francisco, where did you go? A. After we got the plant built came to Newcastle. The Pacific Fruit Cooling and Vaporizing Company directed me to go to Newcastle and put in the plant and said 'Rush — rush it.' That was the instructions I had. Q. When did you come to Newcastle? A. Came to Newcastle along in June, 1908, I think, as near as I recall now." (He arrived June 16th.) "Q. When you came to Newcastle what did you do? A. Went to work putting in the plant. I put the plant in the packing-house of Mr. Kelloo — George D. Kellogg. During all the time I was in Newcastle I was in the employment of that company. Q. What did you have to do for the company while at Newcastle? A. Erecting the plant — this refrigerating plant. Q. The Court: You mean you erected it with your own hands. A. Yes, sir, your Honor, please — I was the engineer and directed the work. I worked not only myself, but directed other men — I worked, physical labor, and had other men, too, working under my direction." He testified that he was discharged on October 10, 1908, and his notice of lien was filed on November 7th.

The court found that plaintiff performed forty days' work between November 10, 1907, and January 31, 1908, as refrigerating and construction engineer, for the company, at the agreed price of $5 per day, aggregating $200, which the company paid on or about January 31, 1908. Defendants attack this finding on two grounds: First, it is contended that the testimony of plaintiff was that he worked every day except Sundays and holidays during this period, making seventy-one days; that "it was either seventy-one days' work and labor, or no days' work and labor"; that "there was no 'middle of the road' proposition." Plaintiff testified to the character of the work done by him during this period, for some of which the court might well have disallowed pay, and no doubt did so, in arriving at a just conclusion. This action of the court was favorable to defendants and cannot be made the subject of complaint. The court could not have disallowed the claim for the entire time without wholly rejecting plaintiff's testimony, which it did not do. Second, it is claimed by defendants that this $200 payment, made January 31st, was an advance payment on wages yet to be earned, and Mr. Groom so testified. Plaintiff testified to the contrary, and that it was money owing him by the company at the time. We think the record shows that the court had sufficient ground for accepting plaintiff's testimony on this point.

The court next found that plaintiff, by virtue of said contract of employment, performed one hundred and fourteen days' work, at $5 per day, between February 1, 1908, and June 16, 1908 (the latter date being the day when plaintiff arrived at Newcastle to commence work in installing the machinery in defendants' building and the erection of said plant), for which defendant company had paid him on account $538 and no more, leaving due plaintiff the sum of $32 at that time. These one hundred and fourteen days represent all the working days in the months embraced by the period mentioned. Defendants claim that the $200 payment of January 31st should be added to the $538, making $738 as paid. But plaintiff's testimony was that this $200 payment was for work previously performed, and the court so found.

The next finding is that, after June 16th, and to October 9th, inclusive, plaintiff worked ninety-nine days, making $495, which has support in the evidence, although it is conflicting, and that plaintiff paid $1.50 for recording his lien. These items, to wit, $32, $495 and, $1.50, aggregated $528.50, for which judgment was entered against defendant company. The services of plaintiff were rendered at San Francisco, in supervising the work of constructing the machinery, and it was for this work the balance of $32 was found to be unpaid. The court, as we understand the findings and judgment, disallowed a lien for this $32. The lien, for the sum of $495, was declared upon the building in which the plant was erected and on the plant itself. This, we think, was a correct determination of the matter, although the court might properly have included in the lien the filing fee of $1.50.

It is further contended by defendants that the claim of lien, in the light of evidence, shows on its face a violation of section 1187, Code of Civil Procedure, which declares that "any person who shall willfully include in his claim, filed under section 1187, work or materials not performed upon or furnished for the property described in the claim, shall forfeit his lien." At the close of plaintiff's case defendants made a motion to strike plaintiff's exhibit "A," the claim of lien, "from the records in the case and as evidence, upon the ground that the lien is fatally defective, in that there is a fatal variance between the contract set out in the lien, its time and terms and conditions, and the proof as shown by plaintiff. The Court: My conviction is that the plaintiff has not willfully attempted to assert a lien for something he did not believe he was entitled to — as to the other points I do not think they constitute a fatal variance." The motion was denied. The alleged variance arises out of averments in the notice of the lien which, it is claimed, were not supported by the evidence, of which the following are the principal ones relied upon: That said Groom, as agent of said company during all the times mentioned, was agent of said company, and as such agent employed plaintiff to work upon said refrigerating and precooling plant about April 10, 1907; that plaintiff was to work and labor on said plant at the rate of $5 per day "and expenses for each and every day, commencing on November 10, 1907, on which latter day said work did commence; that by virtue of said agreement plaintiff did render service"; and then follows a statement of the number of days' labor performed in the several months, from November 10, 1907, to October 9, 1908, inclusive, aggregating two hundred and eighty-eight days and amounting to $1,440 for services and $385.50 for expenses, which $1,087.50 is claimed to be due for "labor and services rendered and performed upon, in and about said hereinbefore described refrigerating and precooling plant and said property under and by virtue of the terms of the hereinbefore set forth contract," after deducting all just credits and offsets. It is contended that plaintiff must have known that he was not working on said plant, which was erected at Newcastle after June 11, 1908, when he was employed at Los Angeles and at San Francisco prior to that date; that the court disallowed all claim for expenses, which shows that plaintiff must have known he was not entitled to such claim; that the court allowed plaintiff's claim for a less number of days than as claimed and found that plaintiff was entitled to a lien only for services after June 15, 1908.

Section 1203, Code of Civil Procedure, provides: "No mistake or errors in the statement or demand, or of the amount of credits or offsets . . . shall invalidate the lien, unless the court finds that such mistake or error in the statement of the demand, credits and offsets, or of the balance due, was made with the intent to defraud, or the court shall find that an innocent third party, without notice, direct or constructive, has, since the claim was filed, become the bona fide owner of the property levied upon, and that the notice of the claim was so deficient that it did not put the party upon further inquiry in any manner." Section 1203, as enacted in 1911 (Stats. 1911, p. 1319), is substantially the same as section 1203a, enacted in 1907 (Stats. 1907, p. 858), so that if it should be held that section 1203 is inapplicable because passed after the matters herein involved occurred, section 1203a, as enacted in 1907, was in force. Speaking of section 1202, before the enactment of section 1203a, the supreme court said, in Schallert-Ganahl L. Co. v. Neal, 91 Cal. 362, 365, [27 P. 743]: "This section of the statute . . . is penal in its character, and not only must be strictly construed, but the evidence under which it is invoked should, be clear and convincing that the violation was willful and intentional." When the motion for a nonsuit was made there was no evidence before the court bearing upon the question of fraud except the notice of plaintiff's claim and his testimony. Fraud is never to be presumed, and, before a party can be deprived of his right upon a claim of fraud, the facts must be clearly made out. ( McCarthy v. White, 21 Cal. 495, [82 Am. Dec. 754].) The court expressed its conviction that the plaintiff did not willfully attempt to assert a lien for something he did not believe he was entitled to. We cannot say that its conclusion was unwarranted. No fraud having been shown and none being clearly inferable from the facts, the lien cannot be defeated merely because it turns out on the trial that the claim as filed was for too much. ( Barber v. Reynolds, 44 Cal. 519; Harmon v. San Francisco etc. R. R. Co., 86 Cal. 617, [25 P. 124]; Continental etc. Assn. v. Hutton, 144 Cal. 609, [ 78 P. 21].)

It was not error to refuse to strike plaintiff's exhibit "A," the notice of lien, from the records.

The judgment and order are affirmed.

Hart, J., and Burnett, J., concurred.

A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on November 18, 1912.


Summaries of

Henley v. Pacific Fruit Cooling and Vaporizing Co.

Court of Appeal of California, Third District
Sep 19, 1912
19 Cal.App. 728 (Cal. Ct. App. 1912)
Case details for

Henley v. Pacific Fruit Cooling and Vaporizing Co.

Case Details

Full title:H. H. HENLEY, Respondent, v. PACIFIC FRUIT COOLING AND VAPORIZING COMPANY…

Court:Court of Appeal of California, Third District

Date published: Sep 19, 1912

Citations

19 Cal.App. 728 (Cal. Ct. App. 1912)
127 P. 800

Citing Cases

Guam Resorts, Inc. v. G.C. Corp

At first blush, it may appear that some California decisions have conflated section 1193.1(k) with section…

Pentecost v. Graham

Upon an appeal it will be presumed that the trial judge recognized and accounted for to his own satisfaction,…