Okla. Stat. tit. 63 § 1-880.9

Current through Laws 2024, c. 9.
Section 1-880.9 - Term of validity of certificate - Time for submitting plans and specifications - Time for construction or modification of structure - Time for acquisition - Effective dates of deadlines
A. A certificate of need issued pursuant to the provisions of this act for the construction or establishment of a new psychiatric or chemical dependency service or the expansion or change of an existing service shall be valid for a period of six (6) months during which time the applicant shall submit to the State Department of Health the plans and specifications for the facility to be constructed or modified; however, the Department may extend such time by a period not to exceed six (6) months for extraordinary circumstances beyond the control of the applicant. If no such plans and specifications are submitted and approved within the time required by this section, then such certificate shall be null and void. If plans and specifications are submitted, the Department shall approve or disapprove such plans and specifications within forty-five (45) business days of the filing or such plans and specifications shall be presumed to be approved. If the Department disapproves the plans and specifications, such disapproval shall include a detailed statement of the corrections needed. The holder of the certificate must resubmit corrected plans and specifications within forty-five (45) business days of disapproval. Failure to resubmit shall render the certificate void. The applicant must begin construction or modification of the structure within two (2) months following the approval of the plans and specifications and must proceed to complete the structure or modifications within twelve (12) months of the approval or the certificate will be canceled. However, the Department may extend such completion day by a period not to exceed six (6) months for good cause, provided that such extension shall not apply to an applicant who has been previously granted a six (6) months' extension for completion of plans and specifications.
B. A certificate of need issued pursuant to the provisions of this act for the acquisition of a psychiatric or chemical dependency facility shall be valid for a period of six (6) months by which time the acquisition must be finalized, provided that the Department may extend such final date by a period not to exceed three (3) months for good cause.
C. Pending the appeal of an order granting a certificate of need in the district or Supreme Court, the effective dates of deadlines for submitting plans, filing reports, completion of the project and other requirements related to such project shall commence on the date of a final judicial determination of any such appeal, and any certificate of need which has been approved by the Department shall remain in effect pending such appeal. The effective date of the issuance of a certificate of need shall be the date of a final judicial determination of any such appeal. The provisions of this subsection shall have prospective and retrospective application.

Okla. Stat. tit. 63, § 1-880.9

Added by Laws 1989, c. 227, § 26.