Section 7973 - Budget Changes
(a) After the award is made, the Department may approve changes to a project budget provided the requested budget change complies with either subsection (b) or (c).
(b) The proposed budget change:
(1) Does not substantially change the specific clients served by the approved project activities; and
(2) Continues to meet the priorities and criteria imposed during the respective grant selection process; and
(3) Results in a product, substantially the same as the originally-approved product, that costs the same as or less than the originally proposed product; and
(4) Will be completed by substantially the same date as allowed for the originally proposed product.
(5) In competitive regions, does not affect the list of awarded applications in a manner which would cause any application to be added to or removed from the list.
(c) The proposed budget change will result in a significant increase in benefits related to the local program.

Cal. Code Regs. Tit. 25, § 7973

1. New section filed 3-18-94 as an emergency; operative 3-18-94 (Register 94, No. 11). A Certificate of Compliance must be transmitted to OAL 7-18-94 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 7-8-94 as an emergency; operative 7-8-94 (Register 94, No. 27). A Certificate of Compliance must be transmitted to OAL by 11-7-94 or emergency language will be repealed by operation of law on the following day.
3. Repealer and new section refiled 10-31-94 as an emergency; operative 10-31-94 (Register 94, No. 44). A Certificate of Compliance must be transmitted to OAL by 2-28-95 or emergency language will be repealed by operation of law on the following day.
4. Repealer and new section refiled 2-15-95 as an emergency; operative 2-15-95 (Register 95, No. 7). A Certificate of Compliance must be transmitted to OAL by 6-15-95 or emergency language will be repealed by operation of law on the following day.
5. Repealer and new section refiled 6-15-95 as an emergency; operative 6-15-95 (Register 95, No. 24). A Certificate of Compliance must be transmitted to OAL by 10-13-95 or emergency language will be repealed by operation of law on the following day.
6. Certificate of Compliance as to 6-15-95 order including amendment of section transmitted to OAL 6-26-95 and filed 7-12-95 (Register 95, No. 28).

Note: Authority cited: Sections 50402, 50801.5 and 50806.5, Health and Safety Code. Reference: Sections 50802.5 and 50804.5, Health and Safety Code.

1. New section filed 3-18-94 as an emergency; operative 3-18-94 (Register 94, No. 11). A Certificate of Compliance must be transmitted to OAL 7-18-94 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 7-8-94 as an emergency; operative 7-8-94 (Register 94, No. 27). A Certificate of Compliance must be transmitted to OAL by 11-7-94 or emergency language will be repealed by operation of law on the following day.
3. Repealer and new section refiled 10-31-94 as an emergency; operative 10-31-94 (Register 94, No. 44). A Certificate of Compliance must be transmitted to OAL by 2-28-95 or emergency language will be repealed by operation of law on the following day.
4. Repealer and new section refiled 2-15-95 as an emergency; operative 2-15-95 (Register 95, No. 7). A Certificate of Compliance must be transmitted to OAL by 6-15-95 or emergency language will be repealed by operation of law on the following day.
5. Repealer and new section refiled 6-15-95 as an emergency; operative 6-15-95 (Register 95, No. 24). A Certificate of Compliance must be transmitted to OAL by 10-13-95 or emergency language will be repealed by operation of law on the following day.
6. Certificate of Compliance as to 6-15-95 order including amendment of section transmitted to OAL 6-26-95 and filed 7-12-95 (Register 95, No. 28).