From Casetext: Smarter Legal Research

Tuxedo Contractors, Inc v. Swindell-Dressler

United States Court of Appeals, District of Columbia Circuit
Dec 26, 1979
613 F.2d 1159 (D.C. Cir. 1979)

Summary

In Tuxedo Contractors, the circuit court, applying District of Columbia law, held that "a party, when told by a prospective client that there is no conflicting contract, cannot be held to have knowledge that a binding agreement does in fact exist, at least in the absence of independent evidence of such knowledge."

Summary of this case from Major Computer Inc. v. Academy Life Ins. Co.

Opinion

No. 77-2114.

Submitted without Argument November 30, 1978.

Decided December 26, 1979.

Francis J. Pelland, Washington, D.C., was on brief, for appellant.

John H. Tracy, Vienna, Va., was on brief, for appellees.

Appeal from the United States District Court for the District of Columbia (D.C.Civil Action No. 76-0047).

Before TAMM and ROBINSON, Circuit Judges, and JOHN H. PRATT, United States District Judge for the District of Columbia.

Sitting by designation pursuant to 28 U.S.C. § 292(a) (1976).

Opinion for the Court filed by Circuit Judge SPOTTSWOOD W. ROBINSON, III.


Appellant, Tuxedo Contractors, Incorporated, brought suit in the District Court against appellees, Swindell-Dressler Company and Paul R. Jackson Construction Company, Incorporated, alleging tortious interference with a contract between appellant and Hartwick Construction Company (Hartwick). After a bench trial, the court held that appellant had failed to establish several essential elements of its cause of action, entered judgment for appellees and dismissed the case with prejudice. This appeal challenges the court's factual and legal conclusions on two principal grounds. We find the arguments advanced by appellant unpersuasive, and therefore affirm.

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., Civ. No. 76-0047 (D.D.C. Oct. 26, 1977), Joint Appendix (J.App.) 13.

Discussed in Parts II, III infra.

I

The undisputed facts may be briefly stated. Appellant and Hartwick negotiated an agreement pursuant to which appellant prepared a bid for an asphalt repair contract with the District of Columbia, and Hartwick then submitted the bid as potential prime contractor. The agreement stated that Hartwick, if successful, would subcontract with appellant for all work to be performed, thus confining Hartwick's obligation to provision of a performance bond and payment to appellant of a specified percentage of the receipts from the District.

At trial, appellees argued that the agreement was not enforceable. Just how much that might have helped their cause is unclear. See generally W. Prosser, Law of Torts, § 129 at 931-934 (4th ed. 1971). In any event, the District Court held that there was a valid compact, id. at 11 n. 9, and this ruling is not challenged here.

J.App. 5-6.

Appellees, as a joint venture, also tendered a bid, which proved to be lowest, and received notice that they had been awarded the repair contract. After discovering these facts, appellant, which through Hartwick had presented the second lowest proposal, entered in Hartwick's name a formal protest of the award on the ground that appellees' bid was nonresponsive. The protest was ultimately upheld, and thereupon the contract went to Hartwick.

J.App. 6.

J.App. 6.

J.App. 6.

J.App. 6.

J.App. 6.

In the interim, however, Hartwick had chosen to withdraw from its agreement with appellant and to give the subcontract to appellees. Appellant contends that appellees induced Hartwick to make this decision, and that in doing so they wrongfully interfered with appellant's contract with Hartwick. Appellees, on the other hand, assert that they did not cause Hartwick's repudiation and, moreover, that they had insufficient knowledge of the Tuxedo-Hartwick agreement to be charged with any tort respecting it.

J.App. 25-29.

Brief for Appellant at 5-6.

Brief for Appellees at 7-9.

II

The District Court's jurisdiction in this case rested solely on diversity of the parties' citizenship. Normally, then, we would first ascertain just whose local law is properly to be applied. But the parties have not briefed the choice-of-law issue, and have not questioned the District Court's apparent assumption that District of Columbia law controls. In similar situations in the past we have sustained that court's utilization of District law. We do so here as well.

As we stated in Lee v. Flintkote Co., 193 U.S.App.D.C. 121, 124 n. 14, 593 F.2d 1275, 1278 n. 14 (1979), when appropriate we apply the choice-of-law and substantive decisional rules of the District of Columbia courts although, because of the District's unique position, the Rules of Decision Act, 28 U.S.C. § 1652 (1976), does not bind us to that result. Compare, e. g., Erie R. R. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938); Klaxon Co. v. Stentor Elec. Mfg. Co., 313 U.S. 487, 61 S.Ct. 1020, 85 L.Ed. 1477 (1941). Instead, we do so out of deference to the authority of the District of Columbia Court of Appeals as the highest court of the District, and in order not to subvert the aims of Erie. Lee v. Flintkote, supra.

The District Court relied almost exclusively on District of Columbia cases in defining the elements of the tort. See J.App. 10-12. The parties themselves, both at trial and on appeal, have also referred primarily to District of Columbia caselaw.

Lee v. Flintkote Co., supra note 14, 193 U.S.App.D.C. at 125-126, 593 F.2d at 1279-1280; Jannenga v. Nationwide Life Ins. Co., 109 U.S.App.D.C. 385, 388, 288 F.2d 169, 172 (1961); accord, Young v. State Farm Mut. Auto. Ins. Co., 213 A.2d 890 (D.C.App. 1965).

To recover under District of Columbia law on a theory of wrongful inducement of a breach of contract, the plaintiff "must show (1) a contract; (2) knowledge of the contract; (3) intentional procurement of its breach by the defendant; and (4) damages resulting from the breach." The District Court held that appellant had failed to prove the second and third elements and thus had not made out a prima facie case. Appellant challenges these rulings, claiming that the court misapprehended the law and that its factual conclusions are without sufficient evidentiary support. Our review of the record satisfies us that the District Court correctly interpreted the applicable substantive law and that its findings of facts were not clearly erroneous.

Hunter Vending Co. v. D.C. Vending Co., 345 A.2d 142, 143 (D.C.App. 1975); accord, Alfred A. Altimont, Inc. v. Chatelain, Samperton Nolan, 374 A.2d 284, 288 (D.C.App. 1977); Bergman v. Gitelson Neff Assoc., 267 A.2d 360, 362 (D.C.App. 1970); Dunn v. Cox, 163 A.2d 609, 611 (D.C.Mun.App. 1960).

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 5-6, J.App. 11-12.

Brief for Appellant at 5-7.

See notes 43-46 infra and accompanying text.

See notes 26-42 infra and accompanying text. Since the court believed the prerequisites to recovery were not established, it did not reach the issue of damages. It did, however, suggest that appellant had not adequately shown the extent of any lost profits. Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 6 n. 11, J.App. 12 n. 11. We affirm the court's holdings on other elements of appellant's claim, and intimate no view on that question.

The District Court found, first, that appellant had not proven "intentional procurement of [the] breach" because it had failed to demonstrate that appellees' actions substantially contributed to Hartwick's decision to dishonor the agreement with appellant. This pertains to the issue of causation, and is a determination of fact which we may reverse only if the resolution is clearly erroneous. The record affords no basis for such a conclusion.

Quoting Hunter Vending Co. v. D.C. Vending Co., supra note 17, 345 A.2d at 143.

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 5, J.App. 11.

See Kassman v. American Univ., 178 U.S.App.D.C. 263, 266, 546 F.2d 1029, 1032 (1976); Alfred A. Altimont, Inc. v. Chatelain, Samperton Nolan, supra note 17, 374 A.2d at 288; Bergman v. Gitelson Neff Assoc., supra note 17, 267 A.2d at 362; see generally W. Prosser, supra note 3, § 129, at 935.

Prior to any contacts with appellees, Hartwick had begun to have second thoughts about undertaking the repair contract with appellant. Jack Y. Matthews, the chief executive officer of Hartwick, testified that he was concerned about appellant's ability to perform the construction work and about Hartwick's ability to obtain a performance bond in compliance with its side of the agreement with appellant. Moreover, when appellees later approached Matthews, he felt that Hartwick was no longer bound by its promise to subcontract to appellant. As a consequence of his misgivings, Matthews had even attempted to withdraw from the bid protest, though he was subsequently persuaded to continue it, and he further avowed that at that time he probably did not intend to enter into a subcontract with appellant. It was some three weeks after these events that appellees contacted Hartwick for the first time and sought to negotiate an agreement under which they, and not appellant, would execute the subcontract.

J.App. 26.

Supplemental Appendix (Supp.App.) 31.

J.App. 26-27, 28. By reason of appellees' bid and the protest against it, the bid period had expired. Matthews thought that, consequently, Hartwick was no longer required to accept the repair contract even if offered by the District of Columbia. We express no view respecting the question whether Hartwick's obligations to the District had, in fact, expired as Matthews supposed. The critical issue is Matthews' attitude toward the contract with appellant, not the validity of his assumptions.

J.App. 29.

Supp.App. 30-31.

See Supp.App. 30-31, J.App. 23.

On the other hand, there was also evidence tending to show that, despite Matthews' apprehensions, Hartwick would have kept its bargain with appellant had appellees not sown further doubts in Matthews' already receptive mind and at the same time offered him a more advantageous arrangement, under which Hartwick would not even have to provide a performance bond for the work. Then, too, Matthews testified that if Hartwick had not subsequently agreed to subcontract to appellees, it probably would have fulfilled its earlier obligation to appellant. Moreover, other than his aborted attempt to withdraw the bid protest, Matthews took no action to terminate the engagement with appellant until after appellees had offered to replace appellant as subcontractor.

J.App. 24-25, 27, 30.

J.App. 28.

J.App. 27. The statement is not free from ambiguity, however. Matthews testified that "[i]f I would have taken the contract at all from the District I would have probably done it with Tuxedo." J.App. 27. But, uncertain as to appellant's ability to perform, Hartwick might have refused the contract offer from the District of Columbia. See J.App. 27; note 28 supra and accompanying text.

This latter evidence, however, does not leave us with the "definite and firm conviction that a mistake has been committed." To be sure, the proofs clashed, but it was for the District Court to resolve the conflict, and we cannot say that its outcome was clearly erroneous. We must, then, abide by the court's finding that appellant failed to prove that appellees caused Hartwick's alleged breach of its contract with appellant.

United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746, 766 (1948).

Hodgson v. H. Morgan Daniel Seafoods, Inc., 433 F.2d 918, 920 (5th Cir. 1970); Thomas E. Snyder Sons Co. v. Industrial Molasses Corp., 270 F.2d 875, 876 (7th Cir. 1959); see United States v. United States Gypsum Co., supra note 35, 333 U.S. at 394, 68 S.Ct. at 542, 92 L.Ed. at 766.

See United States v. United States Gypsum Co., supra note 35, 333 U.S. at 394-395, 68 S.Ct. at 542, 92 L.Ed. at 766; Fed.R.Civ.P. 52(a).

III

A plaintiff claiming wrongful interference with a contractual relation must also demonstrate that the defendant had knowledge of the contract, for without such awareness the latter could not intentionally have induced the breach. The District Court found that appellees "suspected" that there was some kind of arrangement between appellant and Hartwick when they met with Matthews, the Hartwick representative, but that, in response to their questions at that time, they received assurances from Matthews that there was no problem of interference. Appellant contests the accuracy of the factual finding that appellees had no more than suspicion of the existence of a contract, pointing to a response to an interrogatory in which appellees allegedly admitted knowledge of the Tuxedo-Hartwick agreement shortly after the repair-contract bidding was first opened, and to testimony by Matthews and Eric W. Pye, Matthews' assistant, that Swindell-Dressler's representative manifested awareness of the agreement during the meetings to discuss a possible alliance between Hartwick and appellees.

Deoudes v. G. B. Macke Corp., 153 A.2d 309, 310 (D.C.Mun.App. 1959); see Meyer v. Washington Times Co., 64 App.D.C. 218, 222, 76 F.2d 988, 992, cert. denied, 295 U.S. 734, 55 S.Ct. 646, 79 L.Ed. 1682 (1935); Hunter Vending Co. v. D.C. Vending Co., supra note 17, 345 A.2d at 143.

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 5-6, J.App. 11-12.

Brief for Appellant at 20-22; J.App. 20.

J.App. 24-25, 29-30.

The difficulty in appellant's position is that the District Court's resolution was not premised on appellees' total ignorance of the Tuxedo-Hartwick contract. Rather, the court held that whether or not appellees knew that such an agreement had once existed, they were entitled to rely on Matthews' assertion that a subcontract with them would not interfere with any outstanding arrangement with appellant.

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 6, J.App. 12.

The court was correct both in its perception of relevant law in the District of Columbia and in its application of that law to the circumstances of this case. Twice in the last two decades the District of Columbia courts have declared that a party, when told by a prospective client that there is no conflicting contract, cannot be held to have knowledge that a binding agreement does in fact exist, at least in the absence of independent evidence of such knowledge. Moreover, one of these decisions indicates that awareness that a contract once existed is insufficient if reasonable assurances are received that there can no longer be any interference with it. And, despite appellant's insistence, this court's own Meyer v. Washington Times Co. is not to the contrary. There it was held that once a defendant has actual knowledge of conflicting contractual rights, he is not excused by his reliance on his counsel's erroneous legal conclusion that the contract is no longer valid. Meyer simply points out that misapprehension of the law will not excuse intermeddling with another's contract; in no wise does it impinge on the rule that knowledge of the facts must be demonstrated. The District Court found, on the basis of these precedents, that appellees were not shown to have had sufficient knowledge of an ongoing Tuxedo-Hartwick contract to support the action for wrongful interference, and we cannot say that this conclusion was clearly erroneous.

Hunter Vending Co. v. D.C. Vending Co., supra note 17, 345 A.2d at 144; Deoudes v. G. B. Macke Corp., supra note 38, 153 A.2d at 311.

Deoudes v. G. B. Macke Corp., supra note 38, 153 A.2d at 311.

Supra note 38.

Tuxedo Contractors, Inc. v. Swindell-Dressler Co., supra note 1, at 6, J.App. 12.

We are satisfied, then, that the District Court properly held that appellant failed to establish a prima facie case of tortious interference. The judgment appealed from is accordingly

Affirmed.


Summaries of

Tuxedo Contractors, Inc v. Swindell-Dressler

United States Court of Appeals, District of Columbia Circuit
Dec 26, 1979
613 F.2d 1159 (D.C. Cir. 1979)

In Tuxedo Contractors, the circuit court, applying District of Columbia law, held that "a party, when told by a prospective client that there is no conflicting contract, cannot be held to have knowledge that a binding agreement does in fact exist, at least in the absence of independent evidence of such knowledge."

Summary of this case from Major Computer Inc. v. Academy Life Ins. Co.
Case details for

Tuxedo Contractors, Inc v. Swindell-Dressler

Case Details

Full title:TUXEDO CONTRACTORS, INCORPORATED v. SWINDELL-DRESSLER COMPANY, A DIVISION…

Court:United States Court of Appeals, District of Columbia Circuit

Date published: Dec 26, 1979

Citations

613 F.2d 1159 (D.C. Cir. 1979)

Citing Cases

Anchorage-Hynning Co. v. Moringiello

Erie R.R. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938). See Steorts v. American Airlines,…

Legal Tech. Grp., Inc. v. Mukerji

HBR relies on Tuxedo Contractors, Inc. v. Swindell-Dressler Co. for the proposition that a defendant lacks…