From Casetext: Smarter Legal Research

Wright v. Schoharie Valley Railway Co. No. 11

Appellate Division of the Supreme Court of New York, Third Department
Dec 7, 1906
116 App. Div. 542 (N.Y. App. Div. 1906)

Opinion

December 7, 1906.

S.L. C.B. Mayham, for the appellant.

Jackson Strong, for the respondent.


The appellant's lien is filed for materials furnished a sub-contractor. The work was performed in the erection of a high school building in and for Union Free School District No. 1 of the town of Schoharie under a contract made between said school district as owner and Austin Simkins, the respondent herein, as contractor. On the trial it appeared that after the making of the contract between the school district and Simkins, he, by a contract in writing, sublet a portion of the work to one Sloan, who in his contract with Simkins agreed to perform said portion and furnish materials therefor. The appellant here furnished brick to said Sloan, the sub-contractor, to be used in the construction of said building. Upon the completion of the work there was owing from the contractor to the sub-contractor about $1,000, but there was owing from the owner to the contractor upwards of $3,000. The trial court has held that the liens for material furnished the sub-contractor can only be enforced to the extent of the moneys found to be due to him from the contractor. This holding is challenged by this appeal.

In the opinion at Special Term the decision was based mainly upon the case of Brainard v. County of Kings ( 155 N.Y. 538). The question was not discussed in that case and it was assumed that the lien could not be enforced beyond the amount due from the contractor to the sub-contractor. The rule, however, seems to have been squarely held in the case of Lumbard v. Syracuse, B. N.Y.R.R. Co. ( 55 N.Y. 491), and in the case of French v. Bauer ( 134 N.Y. 548). (See, also, Martin v. Flahive, 112 App. Div. 347.) The statutes construed in these cases were substantially similar to the statute construed in the case at bar, and these authorities are, I think, controlling. In the French case Judge HAIGHT, writing for the court, in part says: "It will be observed upon reading the two acts that, whilst they differ in phraseology, they are the same in substance. The policy, as disclosed in both, is to the effect that, except in cases of fraud and collusion, the owner cannot be compelled to pay any greater sum for the completion of his building than that which, by his contract, he had agreed to pay, and the same is true of a contractor who has in turn in good faith paid the sub-contractor the amount due him after the same has become due and payable. The effect of the statute is to take from the owner the money owing by him on his contract and to apply it in payment for the labor and materials furnished by others in the performance of the contract, and the same rule should be applied to the case of a contractor who has paid to a sub-contractor all that he is entitled to."

The judgment should, therefore, be affirmed, with costs.

All concurred, except KELLOGG, J., dissenting; COCHRANE, J., not sitting.

Judgment affirmed, with costs.


Summaries of

Wright v. Schoharie Valley Railway Co. No. 11

Appellate Division of the Supreme Court of New York, Third Department
Dec 7, 1906
116 App. Div. 542 (N.Y. App. Div. 1906)
Case details for

Wright v. Schoharie Valley Railway Co. No. 11

Case Details

Full title:LAWYER J. WRIGHT, Plaintiff, v . THE SCHOHARIE VALLEY RAILWAY COMPANY and…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Dec 7, 1906

Citations

116 App. Div. 542 (N.Y. App. Div. 1906)
101 N.Y.S. 801

Citing Cases

Staten Island Supply v. Beverly-Glenwood

After conducting a hearing, the referee concluded that Beverly was not entitled to the requested setoff,…

Philan Dept. of the Borden v. Foster-Lipkins

Defendant Mohawk-Homar, Inc., commenced work on the job in August of 1967 and abandoned the job site in the…