From Casetext: Smarter Legal Research

Western Sur. Co. v. Bradford Elec. Co., Inc.

United States District Court, N.D. Alabama, Northeastern Division
Jan 8, 2007
483 F. Supp. 2d 1114 (N.D. Ala. 2007)

Summary

noting that hours spent on clerical work is not recoverable and time billed must not be excessive, redundant or otherwise unnecessary and allowing for reductions in time for various activities, including reductions of 1/3 of the time billed

Summary of this case from Ford v. Navika Capital Grp., LLC

Opinion

No. CV-06-J-183-NE.

January 8, 2007

Brian A. Dodd, L. Graves Stiff, III, Thomas L. Selden, Starnes Atchison LLP, Birmingham, AL, for Plaintiff.

Stacy Linn Moon, Allen L. Anderson, Michael L. Fees, Fees Burgess PC, Ashley E. Swink, G. Bartley Loftin, III, Balch Bingham, Huntsville, AL, David Wanhatalo, L. Griffin Tyndall, Burr Forman LLP, Michael J. Douglas, Friedman Leak Bloom PC, Christopher J. Zulanas, Friedman Leak Dazzio Zulanas Bowling PC, John M. Laney, Jr., Laney Foster PC, Birmingham, AL, Jefferson C. Orr, Vic L. McConnell, Smith Cashion Orr PLC, Nashville, TN, for Defendants.



MEMORANDUM OPINION


In accordance with the settlement agreement of the parties, plaintiff Western Surety Company ("Western") and defendants Bradford Electric Co., Inc., and Richard T. Bradford (collectively "Bradford") submitted briefs to the court on the issue of indemnification and attorney fees. The court held a hearing on that issue on December 12, 2006, at which the aforementioned parties were present by and through their respective counsel of record. Based on the briefs, the arguments of the parties, the pleadings in the record, and the applicable law, the court finds as follows:

Richard Bradford is the sole owner of Bradford Electric Co., Inc. Depo. of Richard Bradford (submitted as Consolidated's exhibit 4) at 12.

Western issued performance and payment bonds on behalf of Bradford for electrical work Consolidated Construction Company ("Consolidated") subcontracted to Bradford at the Columbia High School project in Huntsville, Alabama. The performance bond was issued in favor of Consolidated for $1,607,756.00, the full amount of the subcontract. Complaint, ¶ 4; Cross-Claim and Counterclaim, ¶¶ 8-9; Bradford Cross-Claim, ¶ 3; exhibit A to the Complaint. Bradford issued a General Agreement of Indemnity (GAI) in favor of Western, by which Bradford agreed to indemnify plaintiff from any and all loss or anticipated loss which might result from issuance of the performance bond. Affidavit of Joan Clements, ¶¶ 3-4. Due to disputes over the timeliness of the work being performed by Bradford, Consolidated terminated its contract with Bradford in August 2005 and notified Western it sought payment under the performance bond.

As of January 4, 2006, Western had paid $24,262.30 under the subcontractor payment bond based on claims from laborers and material suppliers. Affidavit of Clements, ¶ 11. No other sums have been paid under the payment bond. No amounts have been paid under the performance bond. On January 27, 2006, Western filed this action against Bradford, Consolidated, the architect who designed the school, and the electrical engineering company who designed the electrical plans for the school. All claims, cross-claims and counterclaims have been settled. The sole issue before the court is Western's claim for indemnification on attorney fees and related expenses it incurred in this suit. Western seeks a judgment in its favor for the amount paid under the payment bond as well as all attorney fees and costs incurred in this litigation. Bradford responds that the amount claimed by Western is simply not reasonable.

The court notes that in settlement of this litigation, Western did pay a sum under the performance bond. However, as part of that settlement agreement, Western does not seek indemnification of this amount.

At the hearing, Bradford asserted that any liability Western had was contingent solely on Bradford's liability. Bradford both hired construction counsel and had additional counsel from its insurance company to defend against Western's suit. Thus, Bradford argues that Western's attorney fees were vastly excessive, given the posture of this case.

The General Agreement of Indemnity ("GAI") states in relevant part as follows:

2. The Indemnitors will indemnify and save the Company harmless from and against every claim, demand, liability, cost, charge, suit, judgment and expense which the Company may pay or incur in consequence of having executed, or procured the execution of such bonds, or any renewals or continuations thereof or substitutes therefore, including, but not limited, to fees of attorneys, whether on salary, retainer or otherwise, and the expense of procuring, or attempting to procure, release from liability, or in bringing suit to enforce the obligation of any of the Indemnitors under this Agreement. In the event the Company deems it necessary to make an independent investigation of a claim, demand, or suit, the Indemnitors acknowledge and agree that all expense attendant to such investigation is included as an indemnified expense. In the event of payments by the Company, the Indemnitors agree to accept the voucher or other evidence of such payments as prima facie evidence of the propriety thereof, and of the Indemnitors' liability therefore to the Company.

Plaintiff's exhibit C to the Complaint, ¶ 2. Defendant Bradford, through its president, Richard T. Bradford, signed this agreement on January 31, 2003. Defendant Richard T. Bradford also signed this agreement as an individual indemnitor on this same date.

Western seeks indemnification for its attorney fees and the sole payment made under the payment bond pursuant to this agreement. The parties do not dispute that the only sum Western paid prior to filing this action was the Automatic Control Devices, Inc., claim of $24,262.30. Western seeks reimbursement for fees and expenses in the total amount of $324,861.11. Despite Western's repeated demands that Bradford provide collateralization based on potential claims under the two bonds, Western has not paid any sums other than the $24,262.30. Thus, the court is troubled by the open season on billing which thereafter apparently occurred.

Bradford actually agreed to pay the amount of $23,403.40 on this claim, because it disputed $889.00 of it. See exhibits A and B to Exhibit 1 to Bradford's opposition to Western Surety's motion for summary judgment (doc. 107).

The attorney fee and expense records provided to the court show a "Billed to Date" amount of $251, 620.65. Adding the $24,262.30 paid under the payment bond, the court finds the total sum to be $275,882.95. This is $48,978.16 less than the amount sought by Western.

These requests for collateralization were in spite of the Consent Order restraining Bradford from disposing of any assets worth more than $2,500.00 (doc. 11). Had Bradford deposited with Western $1,500,000.00, the restraints of the Consent Order would have terminated. Id.

Western cites Frontier Insurance Company v. International, Inc., 124 F.Supp.2d 1211 (N.D.Ala. 2000), for the proposition that Western is entitled to "reimbursement from defendants, separately and severally, of all losses, costs, attorney's fees and expenses incurred as a result of the Consolidated claim." Brief of Western Surety (doc. 146) at 8. Frontier Insurance states "a surety is entitled to reimbursement pursuant to an indemnity contract for any payments made by it in a good faith belief that it was required to pay, regardless of whether any liability actually existed." Id., at 1213 (citations omitted).

However, pursuant to a contract of indemnity for attorney fees, the concept of good faith must be applied. In every contract "there exists an implied covenant of good faith and fair dealing." See Hunter v. Wilshire Credit Corporation, 927 So.2d 810, 813 (Ala. 2005) (quoting Sellers v. Head, 261 Ala. 212, 73 So.2d 747, 751 (1954); Lloyd Nolan Foundation, Inc. v. City of Fairfield Healthcare Authority, 837 So.2d 253, 267 (Ala. 2002). An indemnitor can defeat a surety's right to recover under indemnity provisions by demonstrating lack of good faith on the part of the surety in discharging its obligations under the bond. Frontier Insurance Co., 124 F.Supp.2d at 1214; citing Fidelity and Deposit Co. of Maryland v. Bristol Steel and Iron Works, Inc., 722 F.2d 1160, 1163 (4th Cir. 1983).

Thus, although not explicitly stated by the GAI, the court finds that the concept of "reasonableness" must be applied to any claim for indemnification of attorney fees. See e.g., Ideal Electronic Security Co., Inc. v. International Fidelity Insurance Company, 129 F.3d 143, 148-149 (D.C. Cir. 1997) (courts in other jurisdictions have indicated that, as a general matter, a surety must show something akin to reasonable necessity when seeking attorney fees under an indemnity agreement (emphasis in original)); Neustrom v. Union Pacific Railroad Company, 156 F.3d 1057, 1068 (10th Cir. 1998) ("a duty to act reasonably must be read into every contract, including the terms of indemnification clauses). Olan Mills, Inc. v. Linn Photo Co., 23 F.3d 1345, 1348 (8th Cir. 1994) citing Quinto v.Legal Times of Washington, Inc., 506 F.Supp. 554, 562 (D.D.C. 1981) (good faith entails both honesty in fact and reasonableness).

The Alabama Supreme Court dealt with this issue directly, many years ago, stating:

In construing indemnity covenants like that before us, it is everywhere recognized that the indemnitee must act in good faith. He cannot needlessly, in utter disregard of the burdens he is imposing on his indemnitor, incur attorney's fees, and in no case such as are excessive and unreasonable in amount.
The rule is otherwise stated as requiring good faith and the exercise of a reasonable discretion. . . .
Good faith in such cases is that which obtains between persons standing in confidential or fiduciary relations; a good faith which carries a duty to have regard for the interests of his associate, an application of the principles of the golden rule.
Good faith implies the exercise of a reasonable discretion in the circumstances.
Kilgore v. Union Indemnity Co., 222 Ala. 375, 132 So. 901 (1931). See also Perkins v. Thompson, 551 So.2d 204, 209 (Miss. 1989). Following these principles, the Fifth Circuit Court of Appeals held:

In Perkins, the Court adopted the principles set forth by the Alabama Supreme Court in Kilgore. The Mississippi Supreme Court then concluded, "here the surety is entitled to reimbursement for legal costs only if it is necessary for the surety to retain separate legal counsel, if the amount of the fees claimed is reasonable, and if the surety has acted in good faith toward the principal." Id., at 210. After remand, the Court stated that "in Perkins I, we affirmed that the indemnity agreement was enforceable but held that it did not represent a blank check which enabled [Western] Surety to incur any expense and send the bill to [the indemnitor]." Perkins v. Thompson, 609 So.2d 390, 399 (Miss. 1992). The Court concluded that "[Western] Surety is entitled to recover only fees and expenses incurred `by reason of having been surety on this bond.' Such fees and expenses and the reasonableness and necessity of same are thus function's of Western Surety's interest in the case and the risks to which it was exposed." Id., at 400.

In sum, an indemnity agreement is not a blank check; it does not entitle the surety company to reimbursement for legal expenses which are unreasonable or unnecessary. To hold otherwise would allow bonding companies to retain counsel and to charge attorneys' fees against the indemnitor even when the surety company does not require a separate legal defense to protect its interests. The indemnity contract cannot reasonably be construed as requiring the indemnitee to bear the cost of such redundant representation. Thus, the weight of authority allows reimbursement for legal costs under the terms of an indemnity contract only if it is necessary for the surety to retain separate counsel, if the amount of the fees claimed is reasonable, and if the surety has acted in good faith toward the bond principal.
Jackson v. Hollowell, 685 F.2d 961, 966 (5th Cir. 1982). Western has repeatedly represented to this court that retention of separate counsel by Western was both necessary and reasonable. See e.g., Brief of Western Surety Company (doc. 146) at 2. In fact, Western asserts that "Western, BECI and Richard T. Bradford have always been adverse in this case." Id.

With these legal tenets in mind, the court considers the reasonableness of the attorney fees and expenses claimed by Western. The court has also considered that, with the exception of a bad faith claim against Western by Consolidated, all other claims against Western were contingent on liability being found against Bradford. Without that, Western could have no liability. However, unlike many surety situations, Western was not content to rely on Bradford's defense counsel to protect its interests as well.

The court also considers the basic caveats set forth by the Eleventh Circuit for reasonableness of attorneys fees, such as that time billed must not be "excessive, redundant, or otherwise unnecessary . . ." ACLU v. Barnes, 168 F.3d 423, 428 (11th Cir. 1999). Similarly, hours spent on purely clerical work or secretarial tasks are unrecoverable overhead expenses. Allen v. U.S. Steel Corp., 665 F.2d 689, 697 (5th Cir. 1982). Paralegal expenses are recoverable only to the extent that the paralegal performs work traditionally done by an attorney. Otherwise, paralegal expenses are unrecoverable overhead expenses. Id.

During the hearing held on this claim, counsel admitted the following sums were erroneously included in this claim, and are therefore withdrawn:

This time claim actually includes other activities, all of which were billed by other counsel as well. Therefore, the court deducts the entire amount.

7/25/2006 LGS Preparation for hearing on Temporary Restraining 2.80 560.00 Order request and response to inquiry from Judge Bowen. 11/28/2006 BAD . . . preparation of motion for summary judgment 4.40 814.00 11/29/2006 BAD Preparation and revision of Memorandum supporting 4.20 777.00 Motion for Summary Judgment 11/29/2006 LGS Review of correspondence from mediator . . . review 3.40 680.00 and revision of summary judgment motion (indemnity issue) 11/30/2006 EMF Strategic development with LGS and BAD 3.60 522.00 11/30/2006 BAD Research regarding reasonableness argument 4.10 758.50 in opposition to surety's rights . . . 11/30/2006 LGS Review and revision of Memorandum in Support 3.70 740.00 of Motion for Summary Judgment . . . 11/30/2006 JTW Researched previous memorandum Opinions in favor of .60 45.00 surety regarding indemnity claims. Thus, the court deducts $4,896.50 from the amount sought by Western.

The court finds the following claims for reimbursement unreasonable as overhead or clerical expenses:

11/22/2005 JKH Retrieval of documents, and assembling same .50 37.50 for review by LGS 11/22/2005 JKH Review and organization of documents from client. 2.80 210.00 12/2/2005 JKH Continued creation of files for materials received 2.30 172.50 from client. 12/5/2005 JKH Creation of index for files produced by client. .70 52.50 12/28/2005 JKH Confirming location of principal's office; report to .70 52.50 file regarding the same; reviewing contents of Bradford Electric Web page . . . 1/3/2006 JKH Retrieval of docuements (sic) from file for attorney 2.10 157.70 review . . . 1/4/2006 JKH Retrieval of documents from file for review by attorney 1.80 135.00 1/6/2006 JKH Creation of file for Summary of Report by Draper .30 22.50 Associates 1/12/2006 JKH Correspondence to opposing counsel enclosing revised .30 22.50 copy of Bradford Electric report. 3/7/2006 JKH Conference with Federal Court re: filings and non-service .30 22.50 to counsel for O S Enterprises . . . 3/10/2006 JKH Conference with copy service re: status of documents .40 30.00 3/23/2006 JKH Review of scheduling order and report to file . . . .50 37.50 4/14/2006 JKH Review and organization of file. . . . .50 37.50 4/27/2006 JKH Correspondence to copy service enclosing invoice .30 22.50 and payment . . . 6/13/2006 JKH Correspondence with client re: invoice for copy of .30 22.50 Architect project file 7/6/2006 JKH Conference with mediator's office re: invoices and .30 22.50 prior payment . . . 8/2/2006 JKH Review of scheduling order re: Expert disclosures .30 22.50 deadline; report to file. 8/3/2006 JKH Correspondence with counsel for general contractors .30 22.50 Enclosing payment for Western Surety's share of room rental for mediation 8/9/2006 JKH Conference with court re: Response to Motion to .30 22.50 Intervene; report to file 8/16/2006 JKH Correspondence with client enclosing invoice for .30 22.50 mediation services. 8/23/2006 JKH Correspondence with court reporters enclosing .20 15.00 payment for invoice 9/5/2006 JKH Review of scheduling order and report to file re: .90 67.50 compliance with same 9/18/2006 JKH Drafting of bill letters to opposing counsel for cost of .40 30.00 producing documents. 9/19/2006 JKH Converting deposition transcripts to portable document .50 37.50 format; correspondence with electrical engineer for review. 9/19/2006 JKH Correspondence with client enclosing deposition .40 30.00 transcript and errata sheet for review. 9/19/2006 JKH Conference with electrical engineering expert re: .30 22.50 deposition transcripts for review. 10/9/2006 JKH Correspondence with court reporter enclosing executed .30 22.50 Errata sheet for distribution to counsel. 10/13/2006 JKH Preparation of documents for transmittal to counsel for .50 37.50 defendants. 10/16/2006 JKH Correspondence with Preferred Title enclosing payment .30 22.50 for title search. 10/17/2006 JKH Correspondence with William Sealy enclosing documents .60 45.00 for review. 10/17/2006 JKH Correspondence with Ken McLaughlin re: documents for .50 37.50 review. 10/30/2006 JKH Correspondence with client enclosing invoice from .40 30.00 court reporter for payment. 11/9/2006 JKH Correspondence with Ken McLaughlin enclosing code .30 22.50 of professional conduct from Board of Registration of Architects. 11/9/2006 JKH Review of mail. 1.00 75.00 11/22/2006 JKH Correspondence with court reporter enclosing payment .30 22.50 for deposition transcript. Thus the court shall remove the amount of $1,665.20 from Western's claim.

The court finds the following claims for reimbursement duplicative:

1/4/2006 BAD Preparation of Complaint for Exoneration of Surety 5.80 928.00 1/4/2006 LGS Continued preparation of declaratory judgment . . . 6.50 1,300.00 1/4/2006 TLS Continued evaluation of grounds for termination. . . . 1.80 360.00 initial preparation of Declaratory Judgment/Exoneration action. 1/5/2006 BAD Revision of Complaint; Application for Injunctive 1.10 176.00 Relief . . . 1/5/2006 LGS Further review and revision of proposed declaratory 1.80 360.00 exoneration. 1/6/2006 LGS Further review and revision of proposed declaratory 3.70 740.00 action . . . 1/13/06 LGS Conference with Joan Clements and Ken McLaughlin; 3.30 660.00 review and revision of suit papers . . . 1/14/2006 TLS Confirmation of plans for site visit . . . further 1.60 320.00 preparation of complaint 1/16/06 LGS Further review and revision of exoneration/ 2.60 520.00 declaratory judgment action. . . . 1/17/06 LGS Confirmation of plans for inspection/observation . . . 1.80 360.00 further review and revision of revised declaratory judgment complaint . . . 1/24/2006 LGS Conference with Joan Clements and Ken McLaughlin; 5.50 1,100.00 final review and revision of Complaint for Declaratory Relief . . . 1/24/06 TLS Conference with Mr. McLauglin . . . revised complaint 3.80 760.00 for Declaratory Relief . . . 1/26/2006 BAD Final preparation of Complaint . . . 1.90 351.50 Because each of the attorneys involved in drafting the complaint "grouped" his hours, listing numerous activities in blocks, the court cannot ascertain with specificity how much of the above claimed time was actually spent drafting the complaint. Giving the attorneys the benefit of the doubt, the court deems one-third the claimed time to have been spent on other activities besides the drafting of the complaint. As the above hours total 41.20, the court deems 13.73 hours spent on other activities, leaving 27.47 hours drafting a complaint. The court finds 20.00 hours more than reasonable, and hence reduces the attorney fees recoverable under the GAI by 7.47 hours, which equals $1,456.65.

The court also finds that review of the contracts in question by multiple attorneys was duplicative and unnecessary. The following work by the fourth attorney to review those contracts is found unreasonably redundant:

1/9/2006 EMF Strategic Development with LGS re: status and .20 32.00 research issues and review contracts re: same. 1/10/2006 EMF Continue review of contracts. 3.0 480.00 1/12/2006 EMF Continue review of contracts and research re: 3.0 480.00 issues concerning wrongful termination 1/16/2006 EMF Research and prepare memorandum re: termination 5.0 800.00 issues and strategic development with LGS . . . 1/19/2006 EMF Continue research . . . review contracts re: latent 3.30 528.00 defects . . . 1/23/2006 EMF Strategic development with LGS re: research memo . . . 4.20 672.00 1/24/2006 EMF Strategic development with LGS re: termination .70 112.00 memo and revise memo . . . The court therefore deducts the amount of $3,104.00. 1/27/2006 BAD Final preparation for hearing on Application of 3.90 721.50 Temporary Restraining Order; attendance in Court for hearing . . . 1/31/2006 BAD Preparation for hearing on preliminary injunction, 1.10 203.50 conference with counsel for Bradford Electric Company regarding same. The court finds these two claims, taken together, are redundant. The court did not have a hearing in this case on January 27, 2006, thus the attorney could not have spent time attending one. However, having prepared for the hearing on January 27, 2006, the court would hope he was still prepared on January 31, 2006, when the hearing was rescheduled for February 7, 2006. As other activities are claimed, the court finds reasonable one-half the time claimed, or 2.50 of the 5.0 hours claimed, a reduction in the amount recoverable of $426.50. 2/6/2006 TLS Review of complaint; initial preparation of 2.30 460.00 Preliminary Injunction Order 2/7/2006 TLS Review of complaint; initial preparation of 2.30 460.00 Preliminary Injunction Order The court finds that the second identical entry Thomas L. Seldon, dated 2/7/2006, is surely in error, as the exact same entry was made the previous day, although the same appeared on the previous month's bill to Western. The court shall reduce the amount sought by $460.00. 1/20/2006 LGS Travel to and lodging expense in Mobile, AL for 334.20 meeting with new client lawyer The court is unable to decipher this expense claim. No lawyer in this case is in Mobile, nor does this case involve a lawyer-party. On this same date, Western's expert, Kenneth McLaughlin, submitted a charge, infra, for his expenses in traveling to Huntsville to meet with Attorney Stiff. In fact, on this same date, Attorney Stiff has billed $240.00 for meeting with Ken McLaughlin and Joan Clements. As Mr. McLaughlin claimed to be in Huntsville, and Attorney Stiff claimed to meet with him, the court concludes that the travel and lodging expenses for "meeting with new client lawyer" were erroneous, and deducts $334.20 from the amount sought. 2/16/2006 JKH . . . preparation of Alias Summons to SKT Architects 1.60 120.00 2/17/2006 BAD . . . preparation of alias summons to SKT Architects . . . 1.10 203.50 Preparation of an alias summons simply does not take two people two days to prepare. This is especially true given that the court docket the summons received back from the post office and marked "NOT DELIVERABLE AS ADDRESSED" until February 21, 2006, four days after Mr. Harred's claim of time spent preparing an alias summons. Thus, the claims of February 16 and 17, 2006, in the total amount of $323.50, shall be deducted from fees recoverable under the GAI. 3/9/2006 JKH Initial review of documents received from City of .50 37.50 Huntsville . . . 3/9/2006 BAD Review of documents produced by City of Huntsville . . . .80 148.00 These two claims are clearly redundant. The court finds reasonable one half of each claim, resulting in a total reduction of $92.75 in the amount sought by Western. 4/5/2006 JKH Review of order from court setting hearing on Motion .20 15.00 to Reconsider . . . 4/5/2006 BAD Review of order setting Motion to Reconsider for .20 37.00 hearing . . . These two claims are redundant. The court finds reasonable the time claimed by Mr. Harred only, resulting in a reduction of $37.00. 4/12/2006 LGS Final Preparation for and attendance in court on all 4.50 900.00 pending motions . . . 4/12/2006 LGS Preparation for and attendance at argument in Judge 4.80 960.00 Johnson's court . . . As the court held only one hearing on this date, only one of these entries is correct. As the second claim for the identical activity surely must have been charged by accident, the court will not allow Western to recover from Bradford the amount of $960.00. 4/4/2006 JKH Review of financial information submitted by defendant .50 37.50 Richard Bradford . . . 6/27/2006 JKH Initial review of Financial Information from Bradford . . . .40 30.00 As financial information documents from Bradford were first reviewed by Mr. Harred in April, his entry in June of an initial review of these documents must have been in error. The court reduced the amount recoverable under the GAI by $30.00. 5/11/2006 BAD Review and analysis of SKT Architect's project file . . . 6.60 1,221.00 5/12/2006 JKH Initial review of documents from project file . . . 1.40 105.00 5/12/2006 LGS Review of key documents obtained from SKT files . . . 2.30 460.00 5/15/2006 JKH Initial review and analysis of documents produced by 1.90 142.50 SKT Architects; report to file. 5/15/2006 JKH Correspondence with counsel for SKT Architects re: .20 15.00 cd-rom version of documents produced . . . 5/17/2006 LGS Further review of documents produced by SKT . . . 1.50 300.00 5/26/2006 JKH Review and analysis of pay applications from architects 1.40 105.00 (Sic) project file . . . Counsel and staff for Western spent 15.30 hours reviewing the same documents. The court finds that Mr. Harred could not have an initial review of the same documents two times. The court allows only Attorney Dodd's 6.60 hours reviewing this project file. The remainder of these charges, $1,127.50, are excessive. 6/7/2006 LGS Prepare for and attend depositions of CCC reps., 11.50 2,300.00 Halbrooks and Bradford rep. The court notes that the deposition of the "Bradford rep." would be Rick Bradford, whose deposition was attended by Attorney Dodd, but not Attorney Stiff, and which took place on June 8, 2006, and not June 7, 2006. The court therefore deducts one-half of the amount claimed, a reduction of $1,150.00. 7/11/2006 JKH Review and analysis of Motions to Compel filed by .90 67.50 defendant Consolidated . . . 7/11/2006 BAD Review of Motions to Compel filed by Consolidated . . . .70 129.50 7/12/2006 BAD Continued evaluation of Consolidated . . . Motions to .70 129.50 Compel 7/12/2006 JKH Review and revision of Response to Motions to Compel 1.10 82.50 and electronic filing of same with court. . . . 7/12/2006 LGS Review of Motions to Compel filed by CCC; preparation 3.30 660.00 of response . . . 7/13/2006 LGS Review of Motions to Compel . . . 3.50 700.00 These entries are highly redundant. The court finds the time spent by attorney Stiff on July 12, 2006, reviewing and responding to the motions to compel, and the time spent by Mr. Harred on the same date reviewing and revising the response to be reasonable. The remainder of time spent on this activity is excessive. The court believes the entry by attorney Stiff on July 13, 2006, the day after Western's response to these motions was filed with the court, must have been made in error. The court therefore is of the opinion the sum of $1,026.50 is excessive and not reasonably incurred. 8/10/2006 JKH Correspondence with all counsel confirming .50 37.50 upcoming deposition schedule. 8/11/2006 JKH Correspondence with counsel for defendants .40 30.00 confriming (sic) deposition schedule. The court finds the second charge for this activity redundant and subtracts $30.00. 8/25/2006 BAD Conference with architect for Alabama Department of .70 129.50 Education regarding inspection obligations . . . 8/25/2006 LGS . . . conference with state architect re procedures and 4.40 880.00 policies for electrical inspections and confirmation of status of inspections by State Building Commission . . . 8/28/2006 BAD Conference with Alabama Building Commission re .20 37.00 inspection of projection file for Columbia High School project These two entries seem to include some of the same activities. The court reduces the reasonable fee by .70 hours at 200.00/hour, and an additional .20 at $185.00/hour, for a sum of $177.00. 9/25/2006 JKH Drafting non-party subpoena and deposition notice .70 52.50 for representative of Building Commission 9/25/2006 LGS Preparation of notice of deposition to John Vandiver. . . . 1.80 360.00 9/25/2006 BAD . . . conference with John Vandiver confirming availability 1.10 203.50 for deposition; review of deposition notice and subpoena; correspondence to Mr. Vandiver enclosing same 9/26/2006 JKH Review and revision of deposition subpoena to .80 60.00 Building Commission official. . . .

Both Mr. Harred and attorney Stiff claim to have prepared the subpoena to John Vandiver, who was deposed as the representative from the Building Commission. The court allows the time claimed by Mr. Harred only. The court also allows the time claimed by attorney Dodd to confirm and mail the subpoena to John Vandiver on September 25, 2006, but finds Mr. Harred's claim of reviewing and revising the same subpoena the following day to be unreasonable. The court deducts the total amount of $420.00.

1/13/2006 LGS Preparation for and attendance at deposition of Robert 9.80 1960.00 Walker; meeting with all defense counsel re proposed rescheduling of mediation and meeting of defense counsel prior thereto; review and revision of mediators statement and report to Joan Clements 11/13/2006 LGS Preparation for and attendance at deposition of Robert 9.80 1960.00 Walker; meeting with all defense counsel re proposed rescheduling of mediation and meeting of defense counsel prior thereto; review and revision of mediators statement and report to Joan Clements. When questioned about the first of these charges during the hearing, attorney Stiff related that "1/13/2006" was obviously a wrong date and that it was either November or October 13, 2006. The court notes that the proper date must have been November 13, 2006, as this attorney performed these exact activities again on that date. Therefore, finding that this entry was erroneously made two times due to the date being entered improperly the first time, the court deducts the sum of $1,960.00.

The court finds the following claims for reimbursement excessive for the reasons set forth thereafter:

12/1/2005 JKH Continued creation of. 1.30 97.50 3/31/2006 TLS Further evaluation fo (sic) arguments advanced by 2.10 420.00 plaintiff in support of "bad faith" claim. . . . 10/26/2006 JKH Review and analysis of deposition notices for. .40 30.00

The court cannot determine what may have been created for 1.30 hours. This sum shall be deducted as unreasonable. Unless Western argued in support of the claim against it, the entry of March 31, 2006, is nonsensical, as Western is the plaintiff. The entry of October 26, 2006, is unintelligible. The court shall deduct the additional sum $547.50.

11/21/05 LGS Lunch meeting with expert 746.78 The court is of the opinion that lunch should never cost this much. If this disbursement was for something other than the cost of food, this information is not reflected in Western's claim of indemnity for attorney fees and expenses. The sum of $746.78 shall be deducted as unreasonable. 1/30/06 LGS General preparation for hearing . . . 5.40 1,080.00 1/31/2006 LGS Conference with Joan Clements and continued 3.80 760.00 preparation for preliminary injunction hearing . . . The court finds these two claims to be excessive, given that the preliminary injunction hearing never occurred. Rather, the surety obtained a consent order against its principal restraining Bradford from disposal of its assets (doc. 11). The court therefore finds 4.20 hours of these claims to be excessive, reducing the amount recoverable under the GAI by $840.00. 2/14/2006 TLS Review and analysis of counterclaim filed by 2.40 480.00 Consolidated against surety; evaluation of recent case law . . . and confirmation of plans of seeking early dismissal of "bad faith" claim. 2/15/2006 LGS Review and analysis of CCC Counterclaim . . . 5.50 1,100.00 2/16/2006 LGS . . . review of Answer and Counterclaim and 1.80 360.00 confirmation of client instructions re: Motion to Dismiss bad faith claim, etc. 2/17/2006 LGS Further evaluation of Counterclaim and defense 2.50 500.00 strategy 2/21/2006 LGS Further review of CCC counterclaim and proposed 3.30 660.00 response thereto. . . . 3/2/2006 TLS Further review of Counterclaim filed by Consolidated . . . .80 160.00 A total of 16.3 hours were spent by these attorneys in solely the review of the counterclaim against Western. This was not a complex or novel counterclaim, but rather basic contract claims under Alabama law, including a bad faith failure to pay claim against Western. At most, "review," "analysis," "evaluation" and crafting a proposed response should have taken no more than 4 hours. The court deducts 12.30 hours, for a monetary reduction of $2,460.00. 4/3/2006 BAD . . . review and evaluation of Order (denying motion to 1.60 296.00 strike bad faith claim). 4/3/2006 TLS Receipt of Order denying Motion to Dismiss . . . .60 120.00 4/4/2006 BAD Continued analysis of Order denying Motion to Strike . . . 2.70 499.50 The Order in question was one and a half pages and concluded that the law on the issue was unsettled. The court allows one hour for Attorney Dodd to review and evaluate this Order, a reduction of $730.50. 3/8/2006 BAD Review of Order setting briefing schedule on Motion .90 166.50 to Dismiss bad faith count of counterclaim . . . 3/8/2006 TLS Receipt of Order directing Consolidated to response .80 160.00 (sic) to Motion to Dismiss "bad faith" claim This "briefing schedule" was a one page order allowing defendant Consolidated twenty-one days to respond to Western's motion to dismiss one of Consolidated's counter-claims against it. It should not have taken two attorneys 1.70 hours total time to review a one page order which did not require them to do anything. The court finds a total of .2 hours for reviewing this Order reasonable, reducing the attorneys' time .80 for attorney Dodd and .70 for attorney Seldon. This amounts to a reduction of $288.00. 3/10/2006 LGS Conference with client . . . preparation for planning 2.30 460.00 conference. 3/13/2006 BAD Conference with all counsel of record . . . preparation 1.90 351.50 of Report of Parties Planning Meeting . . . 3/13/2006 LGS Preparation for and participation in planning meeting; 2.80 560.00 report to client . . . 3/13/2006 TLS General preparation for mandatory parties' planning 1.10 220.00 meeting . . . 3/14/2006 BAD Review of revised Report of Parties Planning Meeting; .20 37.00 conference with counsel for Consolidated Construction Company regarding same. 3/14/2006 LGS Review of final planning meeting report and 1.60 320.00 confirmation of status of document delivery. 3/16/2006 JKH Conferences with opposing counsel re: Report .30 22.50 Parties Planning Meeting and filing of same. The court is of the opinion that 9.90 hours for preparation of a Report of Parties' Planning Meeting is excessive, especially given that it was filed by counsel for Consolidated Construction Company, and not Western. The court notes that attorneys use a "fill in the blank form" for such reports. Even given that these attorneys did not file the report with the court, the court finds a reasonable amount of time to be 3 hours for preparation of the report and 2 hours for the planning meeting itself, a reduction of 4.9 hours, which the court finds to be $955.50. The court finds the claim for filing of the same completely unreasonable, and disallows its entirety, a reduction of $22.50. 3/20/2006 LGS . . . confirmation of status of document production 2.50 500.00 from parties and non-parties and further evaluation of discovery plan. 4/13/2006 LGS Review of status of document production from parties 2.80 560.00 and non-parties; evaluation of discovery plan. 4/19/2006 LGS Further review and evaluation of discovery plan in 1.20 240.00 light of mediation schedule. 5/1/2006 LGS Review of correspondence . . . further review and 1.40 280.00 evaluation of discovery plan required before mediation 1.50 300.00 5/10/2006 LGS Report to client . . . confirmation of status of documents received from all parties; outline of discovery plan. The court finds that Attorney Stiff spent 9.4 hours confirming documents produced and evaluating a discovery plan. The court cannot ascertain what exactly these activities might entail. Presumably, before the parties submitted a Report of Parties Planning Meeting to this court, the need for discovery and a plan therefore was evaluated, analyzed and reviewed. The court allows one hour for confirming the status of document production, resulting in a deduction of $1,680.00. 3/17/2006 JKH Review and downloading of documents served .30 22.50 electronically by federal court. The court "served" no documents on this date. 4/5/2006 JKH Confirming status of pending motions in assistance .40 30.00 to attorney.

On April 5, 2006, the sole motion pending in this case was Western's motion for reconsideration. Looking at CM/ECF for a ruling on this one motion should not take anyone 24 minutes. The court allows .10 for this activity, a reduction of $22.50.

Joan Clements' deposition was attended by attorney Stiff, not attorney Seldon. The court notes attorney Stiff spent no less than 20 billed hours preparing for that deposition, which resulted in a 129 page transcript.

See infra regarding Western's fees incurred on the collateralization issue.

6/1/2006 TLS . . . evaluation of filing Partial Summary Judgment Motion .80 160.00 re: claims for exoneration 6/26/2006 JKH Review and analysis of Motion for Partial Summary .90 67.50 Judgment. . . . 6/26/2006 BAD . . . preparation of Motion for Partial Summary Judgment 4.10 758.50 and Supporting Memorandum Brief 6/27/2006 JKH Assisting attorney with drafting Motion for Summary .60 45.00 Judgment 6/27/2006 BAD Continued preparation of revision of Motion for Partial 2.30 425.00 Summary Judgment . . . preparation of First Amended Complaint 6/27/2006 LGS Review and revision of Motion For Partial Summary 1.80 360.00 Judgment . . . preparation of Amended Complaint 6/28/2006 BAD Continued preparation and revision of First Amended 1.30 240.50 Complaint . . . 6/28/2006 LGS . . . further review and revision of Proposed Amendment 3.40 680.00 to Complaint and Motion for Partial Summary Judgment 6/29/2006 JKH Assisting attorney with drafting of Amended Complaint .30 22.50 6/29/2006 BAD Continuing preparation and revision of First Amended .90 166.50 Complaint. 6/29/2006 LGS . . . review and continued preparation of First Amended 4.70 940.00 Complaint . . . 6/30/2006 LGS Final review and revision of First Amended Complaint . . . 3.30 660.00 7/3/2006 LGS . . . evaluation of collateralization needs; continued 3.50 700.00 preparation of Amended Complaint 7/5/2006 JKH Assisting attorney with revisions to amended 1.20 90.00 complaint . . . 7/5/2006 BAD Review of revised First Amended Complaint. .30 55.50 7/5/2006 LGS . . . final review and revision of proposed Amended 3.20 640.00 Complaint . . . 7/7/2006 JKH Review of Amended Complaint . . . .90 67.50 7/7/2006 BAD Final review and revision of Motion for Leave to file 1.10 203.50 First Amended Complaint . . . 7/10/2006 BAD Review of Order granting Motion for leave to file . . . .40 74.00 final preparation of Amended Complaint for filing 7/10/2006 LGS Confirmation of entry of Order granting Motion for 1.70 340.00 Leave to File . . . conference with all counsel regarding service of Amended Complaint and compliance with Court Order . . . 8/14/2006 JKH Review and revision of motion and memorandum brief .60 45.00 in assistance to attorney. 8/14/2006 BAD . . . revision of Motion for Partial Summary Judgment 2.60 481.00 and supporting Memorandum brief . . . 8/15/2006 JKH Continued review and revision of Motion for Summaru .90 67.50 (sic) Judgment in assistance to attorney 8/15/2006 BAD . . . continuing preparation and revision of Motion for 4.10 758.50 Partial Summary Judgment and supporting Memorandum Brief . . . 8/15/2006 TLS Conference with Ms. Clements re deposition 1.50 280.00 testimony, etc; review of terms of General Agreement of Indemnity and finalized Memorandum Brief in Support of Motion for Partial Summary Judgment 8/18/2006 BAD Conference with client . . . execution of affidavit 3.10 573.50 supporting Motion for Partial Summary Judgment . . . review of response from Bradford Electric Company to collateralization demand. 10/16/2006 BAD . . . Revision of motion for partial summary judgment 5.10 943.50 and supporting memorandum . . . Review of property report prepared by Preferred Title. Revision of demand note, mortgage and seculity (sic) agreement. Report to file. 10/18/2006 JKH Assisting attorney with preparation of motion for .40 30.00 sumary (sic) judgment. 10/18/2006 LGS Continuing revision of Motion for Partial Summary 3.10 620.00 Judgment and supporting Memorandum Brief; conference with counsel for Bradford Electric Company regarding execution of demand note, mortgage and security agreement. . . . confirmation of license status of expert retained by Bradford Electric Company; report to file 10/18/2006 LGS Review of recent cases of holding surety's rights of 2.30 460.00 exoneration; revised Memorandum Brief and Evidentiary Submission in support of Partial Summary Judgment 10/23/2006 JKH Drafting Notice of Evidentiary Submission for filing .80 60.00 with court. 10/23/2006 JKH Preparation of Motion and Brief for filing with court and 1.40 105.00 electronic filing of same. 10/23/2006 JKH Assisting attorney with selection of documents for use .50 37.50 as exhibits to Motion. The only motion for partial summary judgment filed by Western was filed on October 23, 2006. The Amended Complaint was filed July 10, 2006. However, Western's counsel managed to lump together billing for both of these activities. The time spent collectively on these two activities is 63.1 hours, which is excessive. The court allows forty hours as reasonable for preparing a motion for summary judgment, and ten hours for preparation of the amended complaint. The court therefore shall deduct 13.1 hours for the sum of $2,323.30 7/15/2006 WDB Researching caselaw regarding joint attorney-client 1.10 176.00 privilege between principal and surety. 7/17/2006 WDB Drafting report to file regarding research for joint .60 96.00 defense privilege between principal and surety. 7/17/2006 BAD Preparation off (sic) responses to Consolidated 1.40 259.00 Construction Company's second document request; research regarding privilege between principal and surety in defense of claim. 7/18/2006 WDB Continuing to research law regarding joint attorney- 2.80 448.00 client privilege . . . 7/18/2006 BAD Continuing research regarding claim of privilege 1.30 240.50 between principal and surety . . . 7/16/2006 Westlaw search 374.58 Western has repeatedly informed this court that it had to bring this litigation and incur the attorney fees in issue because its position was always adverse to that of Bradford. As such, the court finds the above research concerning a joint defense privilege to have been unreasonably undertaken. Western's claim is reduced by $1,594.08. 4/5/2006 JKH Research of Tennessee Code re: Homestead .50 37.50 Exemption . . . 4/6/2006 JKH Research of court records re: divorce case of Richard 1.10 82.50 T. Bradford . . . 4/6/2006 JKH Purchased of money order to obtain copy of Mr. Bedford's 5.79 divorce decree 4/11/2006 JKH Review of request for information from accounting .40 30.00 consultant; report to file re: divorce decree and settlement agreement. 4/11/2006 JKH Research Secretary of State website re: real estate .50 37.50 partnerships owned by principal . . . 4/13/2006 JKH Review of Settlement Agreement from divorce of 1.80 135.00 Richard and Pamela Bradford . . . 4/18/2006 LGS Review of mediator's statement for service . . . 2.60 520.00 conference . . . regarding collateralization issues raised by divorce decree and property settlement 4/26/2006 JKH Review of memorandum from accounting consultant .30 22.50 . . . documentation of divorce settlement 5/10/2006 JKH Review of memorandum from accounting consultant . . . .80 60.00 8/21/2006 LGS Review of collateralization proposal and report to .70 140.00 Joan Clements. 9/27/2006 LGS Further review and analysis of expert licensure 2.30 460.00 requirement for engineering testimony and exceptions thereto . . . preparation and transmittal of collateral demand to plaintiff's counsel 10/6/2006 BAD Preparatoin (sic) of demand note, mortgage and 2.10 388.50 security agreement; correspondence to counsel for Bradford Electric Company enclosing same 10/9/2006 BAD . . . continuing revision of demand note, mortgage 1.70 314.50 and security agreement; conference with title company confirming agreement to perform title search on principal's property. 10/9/2006 LGS . . . review and revision of Note and Mortgage Security 3.50 700.00 Agreement; response to Tyndal/Zulanas re collateral security issues 10/10/2006 JKH Review of documents from counsel for Bradford; .60 45.00 conference with Preffered (sic) Title re: title search of Winchester Road property 10/10/2006 JKH Review and revision of Promissory Note and Mortgage .70 52.50 Agreement. 10/10/2006 JKH Correspondence with counsel for principal re: Promissory .40 30.00 Note and Mortgage Agreement. 10/10/2006 BAD Final revision of demand note mortgage and security .90 166.50 agreement; confirmation of status of title search on commercial property; report to file 10/13/2006 JKH Correspondence with title company re: Title search of .40 30.00 Property owned by principal. 10/13/2006 JKH Correspondence with title company enclosing legal .30 22.50 Description of property for completion of title search. 10/13/2006 BAD Continuing conference with Preferred Title regarding 1.70 314.50 Status of title search. . . . 10/16/2006 JKH Assisting attorney with selection of exhibits for .70 52.50 enclosure with letter to counsel for principal. 10/16/2006 JKH Review and revision of mortgage and security .30 22.50 agreement 10/17/2006 JKH Review and analysis of title search; report to file. .30 22.50 10/17/2006 BAD Continuing conference with counsel for Bradford .30 55.50 Electric Company regarding status of execution of note . . . 10/17/2006 LGS Conference with clients. . . . review and revision of motion 5.50 1100.00 for deposit for collateral. 10/20/2006 BAD Revision of note, security, agreement and mortgage; 2.30 425.50 correspondence to client enclosing same; conference with counsel for Bradford Electric Company regarding 10/20/2006 LGS Review and revision of letter to attorneys Zulanas and 4.70 940.00 Tyndall re collateral demand and unilateral settlement options; conference with Joan Clements; review of order from Judge Johnson on all pending motions and repot (sic) to client . . . execution of note . . . 10/20/2006 LGS Conference with Ken McLaughlin . . . confirmation of 4.50 900.00 status of Note and Mortgage Security Agreement . . . 10/23/2006 BAD Continuing preparation and revision of note, security 5.80 1073.00 agreement and mortgage . . . final preparation of Motion for Partial Summary Judgment and supporting Memorandum Brief . . . 10/23/2006 TLS Evaluation of bankruptcy and related issues; report re .50 100.00 same. 10/23/2006 LGS Conference with Joan Clements; review and revision of 5.80 1160.00 Note and Security Agreements. . . . review and revision of Note and Security Agreement as directed by Joan Clements and transmittal to opposing counsel 10/24/2006 BAD . . . . . conference with counsel for Bradford Electric 2.90 536.00 Company regarding status of note and security agreement . . . 10/24/2006 LGS Review of expert reports . . . report to Joan Clements re 6.50 1300.00 revised Note and Security Agreement and continued negotiation with opposing counsel re execution thereof. 10/25/2006 JKH Assisting attorney with review of documents re: .40 30.00 promissory note and agreement; report to file. 10/25/2006 LGS Continued review and revision of Note and Security 4.30 860.00 Agreement; conference with attorney Tyndall regarding same; review and revision of Motion to Compel Collateral Deposit . . . 10/26/2006 BAD Review of file in preparation for meeting of Scott Cole . . . 5.20 962.00 conference with counsel for Bradford Electric Company regarding status of none (sic) security agreement and mortgage 11/6/2006 BAD Conference with counsel for Bradford Electric Company 4.70 869.50 regarding collateralization demand . . . 11/17/2006 LGS Continued review and analysis of effect of mediation 4.50 900.00 and conference . . . re unilateral settlement options . . . and analysis of collateralization requirements. 11/20/2006 LGS Review and revision of letter to attorneys Zulanas and 4.70 940.00 Tyndall re collateral demand and unilateral settlement options . . . review of order from Judge Johnson on all pending motions and report to client; preparation of physician's summary for pretrial order and confirmation of discovery schedule.

The court finds these activities unnecessary as Western already had a Consent Restraining Order in place protecting its interest in its principal's assets. Therefore, delving into Richard Bradford's divorce could not assist Western in this litigation. Similarly, in spite of the vast amounts of time spent obtaining title searches of Bradford's property, preparing a mortgage and note and talking about "unilateral settlements," Western never paid any amount of money out under the performance bond. It paid one claim of approximately $24,000.00 under the payment bond. In exchange, its counsel billed Western the sum of $15,843.79 solely on investigating and attempting to tie up Bradford's assets. This too was in spite of the fact that Bradford had already entered into a consent order preventing either the business or the individual from disposing of their respective assets. The court finds the entire sum of $15,843.79 unnecessarily incurred.

7/30/2006 LGS Review of order on Motion to Compel and Motion 2.70 540.00 to Reconsider by CCC counsel; report to client and preparation for status conference with Judge Johnson — confirmation of discovery status. The court issued an Order granting a motion to compel filed by Consolidated (CCC) on July 12, 2006. On July 21, 2006, Bradford filed a motion to reconsider. The court did not enter any Order on this motion to reconsider until July 31, 2006. Consolidated did not file any motion to reconsider the court's granting of Consolidated's motion. As the court cannot ascertain what Attorney Stiff actually did for 2.70 hours, and Attorney Stiff spend at least another 6.80 hours preparing for the status conference with this court (entries dated 7/25/2006 and 7/31/2006), the court finds this $540.00 charge unreasonable. 11/28/2006 JKH review and analysis of court order setting briefing .40 $30.00 schedule for indemnity claim; report to file The court notes this Order was a grand total of five lines, which should have taken less than thirty seconds to read. It contained one deadline. It was also issued November 29, 2006, the day after this review and analysis took place. The court finds a reasonable amount of time to be .10 hours, reducing the sum allowable by $22.50. 8/18/2006 JKH Confirming state licensure status of electrical expert; .30 22.50 report to file. 8/23/2006 BAD Analysis of recent Alabama case law regarding 1.40 259.00 disqualification of non-licensed engineers from providing expert testimony; conference with architect license board confirming status of potential expert; report to file. 8/24/2006 LGS Conference with possible architectural experts and 2.50 500.00 confirmation of Ken McLaughlin position re engineering negligence. 9/14/2006 LGS Review of expert issue; conference wiht (sic) Ken 3.30 660.00 McLaughlin re qualifications/licensure issue . . . 9/18/2006 BAD Conference with expert regarding availability for 2.10 388.50 deposition; continuing evaluation of effect of recent Alabama Supreme Court opinion regarding license requirements for proposed engineering experts. 9/19/2006 BAD Conference with counsel regarding status of proposed 1.70 314.50 mediation . . . continuing evaluation of recent case law regarding qualifications of non-licensed experts. 9/28/2006 JKH Preparation of documents re; Qualification of Expert .40 30.00 Witnesses in Alabama . . . 9/28/2006 JKH Correspondence with engineering consultant re: .40 30.00 Supreme Court decision and advisory opinion 9/28/2006 LGS Conference with Ken McLaughlin re licensure issue; 3.80 760.00 conference with Joan Clements; further evaluation of exceptions/applicability to licensure requirement as condition precedent to expert testimony . . . 10/27/2006 JKH Review and analysis of Motion to Strike Expert Witness .50 37.50 by counsel for architect. 10/27/2006 BAD Review and analysis of Motion to Strik (sic) . . . 2.20 407.00 10/30/2006 TLS Review of Motion to Strike Expert Designation and Brief .80 160.00 filed in support thereof; review of case law and confirmation of deadline for responding to same. 11/6/2006 WDB Researching law regarding admissibility of expert 5.40 864.00 testimony in federal court and whether state law applies to such admissibility; researching the Alabama disciplinary rules for architects . . . 11/6/2006 LGS Preparation and repsonse (sic) to SKT Motion to Strike 5.60 1120.00 McLaughlin . . . comprehensive discussion with attorneys Zulanas and Tyndall re indemnity issues and collateral issues . . . As this was the expert of Western's choosing, Bradford should not be liable for Western's decision to select an expert from outside the state of Alabama, who was not licensed in the state of Alabama. The sum of $5,553.00 is excessive. 9/6/2006 BAD Conference with counsel for all parties regarding 1.60 296.00 . . . proposed extension of discovery deadline. . . . preparation of draft unopposed Motion to Extend Discovery. 9/7/2006 JKH Assisting attorney with drafting of Motion for Extension .80 60.00 of time. 9/7/2006 BAD Final revision of unopposed Motion to Extend Discovery; 2.10 388.50 correspondence to counsel enclosing same for review . . . .50 37.50 9/8/2006 JKH Preparation of document and electronic filing of same with Federal Court. The motion to extend discovery was one page plus one line long. Any attorney should have been able to prepare the motion, proofread the motion, discuss the motion and file the motion in under one and a half hours. The court deducts 3.50 hours from the 5.0 hours claimed. Hence, the court finds a reasonable sum for this activity to be $185.00 (1 hour) for attorney Dodd, and $37.50 (1/2 hour) for Mr. Harred, a reduction of $559.50. 9/26/2006 LGS Preparation for meeting with expert Bill Sealy; general 2.40 480.00 preparation for deposition of John Vandiver. . . . 9/29/2006 LGS Outline of areas for coverage for Vandiver deposition. 1.60 320.00 The deposition of John Vandiver reflects that it was attended by attorney Dodd. The court can find no reasonable basis for an attorney to charge for 4 hours work to prepare for a deposition he was not going to attend. The sum of $800.00 is subtracted. 10/30/2006 JKH Review and analysis of court order on briefing schedule .40 30.00 for Motion; report to file This court order was four lines long. It could not have required more than thirty seconds to read. The court finds charging 24 minutes to read a four line order is excessive. Billing .10 hour for this activity would have been reasonable. The court eliminates .30 hours, for a reduction of $22.50. 11/20/06 JKH Review and analysis of order denying motion for .40 30.00 partial summary judgment This Order was one and a half pages long. It may have taken two minutes to read. Billing .10 for this activity would have been reasonable. The court eliminates .30 hours, for a reduction of $22.50.

Counsel for Western also billed thousands of dollars in expenses. Considering the reasonableness of these charges, the court finds as follows:

Ikon Invoice of 3/9/2006: $791.83 for office supplies. Ikon Invoice of 5/14/2006: 658.68 for office supplies. Office supplies are out of pocket expenses that are simply law firm overhead. The items purchased include folders, labels and binders. The court will deduct the sum of $1,450.51. Dominick, Fletcher Invoice of 6/29/2006: $584.00 This amount was incurred by Western because all of the parties agreed to attempt mediation in an effort to resolve this case. Each party to the mediation was to pay an equal share of the cost of the mediation. The court is of the opinion that Western is not entitled to recoup this expense from Bradford, as Bradford has already paid its fair share for the cost of this mediation, necessitated by Western's filing of this lawsuit. The court shall deduct this amount. Cypress Consulting Invoice of 3/31/2006 $2,263.12 Bradford Electric Invoice of 3/27/2006 224.06 Allied Photocopy Invoice of 3/10/2006 217.30 Cypress Consulting Invoice of 5/31/2006 812.50 These amounts were incurred by Western in its review of Bradford's financial condition. Bradford's financial condition was never an issue in this lawsuit. No evidence, argument, letter, statement or thought that Bradford might enter bankruptcy over the issues in this lawsuit has ever been brought up by any party to this litigation, other than by Western in trying to justify why it spent tens of thousands of dollars researching Bradford's financial condition. The court finds the amount of $3,516.98 unreasonably incurred.

McLaughlin invoices from 9/25/2005 through 9/8/2006 include the following:

9/25/2005 Travel to Huntsville $1,040.00 9/25/2006 Milage 465.60 9/25/2006 Hotel 388.50 9/28/2005 Travel from Huntsville 1,040.00 9/28/2005 Travel Expense Reimbursement 465.60 10/24/2005 Travel to Huntsville 1,040.00 10/24/2005 Travel Expense Reimbursement 933.09 10/26/2005 Travel from Huntsville 1,040.00 1/20/2006 Trip to Huntsville 1,560.00 1/20/2006 Airfare 521.20 6/25/2006 Arbitration Meeting — Huntsville (Travel Meet) 1,040.00 6/25/2006 Hotel 191.21 6/26/2006 Mileage 358.90 6/27/2006 Arbitration Meeting — Huntsville (Travel Day) 780.00 Western hired an engineering consultant from Louisiana. This individual was not qualified to give expert testimony under Alabama law. While Western was entitled to hire the expert of its choosing, Bradford should not have to pay for that expert to travel to Alabama. Western could have retained experts within the State of Alabama, as there has been no showing that a qualified engineering expert already licensed in this state was unobtainable, or that all engineering consultants in Alabama were unqualified. The court subtracts the amount of $10,864.10. Similarly, the court deducts the amount of $1,546.63, which attorney Stiff claimed for travel expenses on October 17, 2006, to New Orleans, Louisiana, for the deposition of Mr. McLaughlin.

In sum, the court finds the amount of $73,236.47 not reasonably incurred. Because it was not reasonably incurred, it is not recoverable under the surety agreement. Therefore, the amount of fees and expenses reasonably recoverable by Western from Bradford under the GAI is $178,384.18. The amount paid under the payment bond, $24,262.30 is also due to Western from Bradford. The court shall so rule by separate Order.

DONE and ORDERED.

Mr. Harred 1.64 hours @ $75/hr = $123.00 Attorney Selden 0.44 hours @ 200/hr = 88.00 Attorney Dodd 5.78 hours @ 185/hr = 1068.30 Attorney Stiff 5.22 hours @ 200/hr = $2,323.30


Summaries of

Western Sur. Co. v. Bradford Elec. Co., Inc.

United States District Court, N.D. Alabama, Northeastern Division
Jan 8, 2007
483 F. Supp. 2d 1114 (N.D. Ala. 2007)

noting that hours spent on clerical work is not recoverable and time billed must not be excessive, redundant or otherwise unnecessary and allowing for reductions in time for various activities, including reductions of 1/3 of the time billed

Summary of this case from Ford v. Navika Capital Grp., LLC

noting that hours spent on clerical work is not recoverable and time billed must not be excessive, redundant or otherwise unnecessary

Summary of this case from Norman v. Alorica, Inc.
Case details for

Western Sur. Co. v. Bradford Elec. Co., Inc.

Case Details

Full title:WESTERN SURETY COMPANY, Plaintiff, v. BRADFORD ELECTRIC CO., INC., et al.…

Court:United States District Court, N.D. Alabama, Northeastern Division

Date published: Jan 8, 2007

Citations

483 F. Supp. 2d 1114 (N.D. Ala. 2007)

Citing Cases

Hartford Casualty Insurance Company v. Jenkins

See, e.g, Kilgore v. Union Indemnity Co., 132 So. 901, 902 (Ala. 1931) ("When a surety is sued for the…

Wolff v. Royal Am. Mgmt., Inc.

Id.Western Sur. Co. v. Bradford Elec. Co., Inc., 483 F.Supp.2d 1114, 1121 (N.D.Ala.,2007) Attorney Henry…