From Casetext: Smarter Legal Research

Txu Portfolio Mgmt. Co. v. FPL Energy, LLC

Court of Appeals of Texas, Dallas.
Aug 18, 2016
529 S.W.3d 472 (Tex. App. 2016)

Opinion

No. 05-08-01584-CV.

08-18-2016

TXU PORTFOLIO MANAGEMENT COMPANY, L.P. n/k/a Luminant Energy Company, L.L.C., Appellant v. FPL ENERGY, LLC; FPL Energy Pecos Wind I, LP ; FPL Energy Pecos Wind II, and Indian Mesa Wind Farm, L.P., Appellees

William Thompson, Michael L. Raiff, James W. Walker, James C. Ho, Ashley Elizabeth Johnson, for TXU Portfolio Management Company, L.P. N/K/A Luninant Energy Company, L.L.C. Jeffrey M. Tillotson, Ryan Paulsen, Ben L. Mesches, Anne McGowan Johnson, Nina Cortell, John D. Volney, for FPL Energy, LLC; FPL Energy Pecos Wind I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P.


William Thompson, Michael L. Raiff, James W. Walker, James C. Ho, Ashley Elizabeth Johnson, for TXU Portfolio Management Company, L.P. N/K/A Luninant Energy Company, L.L.C.

Jeffrey M. Tillotson, Ryan Paulsen, Ben L. Mesches, Anne McGowan Johnson, Nina Cortell, John D. Volney, for FPL Energy, LLC; FPL Energy Pecos Wind I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P.

Before Justices Francis, Evans, and Whitehill

The Honorable Justice David Evans succeeded the Honorable Justice Joseph B. Morris, a member of the original panel and author of the original opinion in this case, upon Justice Morris's retirement.

The Honorable Justice Bill Whitehill succeeded the Honorable Justice Kerry P. FitzGerald, a member of the original panel, upon Justice FitzGerald's retirement.

OPINION ON REMAND

Opinion by Justice Whitehill

This contract dispute between TXU Portfolio Management Company, L.P. n/k/a Luminant Energy Company, L.L.C. (TXUPM) and FPL Energy, LLC, FPL Energy Pecos Wind I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P. (Wind Farms) is before us on remand from the Supreme Court of Texas. The case concerns three contracts requiring the Wind Farms to supply TXUPM with annual quantities of wind generated electricity and related renewable energy credits (the Agreements). The Wind Farms, however, did not meet their delivery obligations.

The supreme court affirmed our previous holding that TXUPM was not responsible for ensuring transmission capacity under those Agreements, but concluded that the Agreements' liquidated damages provisions were unenforceable as a penalty and thus reversed our ruling that TXUPM was entitled to damages based on those provisions. FPL Energy, L.L.C. v. TXU Portfolio Mgmt. Co. L.P. , 426 S.W.3d 59, 72–73 (Tex.2014). The supreme court then remanded the case to us "to determine damages consistent with [its] opinion." Id . at 73. The parties provided supplemental briefs on the remaining damages issues.

Our damages analysis turns on two questions the trial court submitted to the jury:

• Question 4 asked the jury to determine TXUPM's market damages for failing to deliver "Renewable Energy," which consists of both wind power generated electricity and its corresponding renewable energy credits; and

• Question 5 asked whether TXUPM covered for the electricity the Wind Farms failed to provide under the Agreements.

Based on the "yes" answer to Question 5, the trial court ruled that TXUPM was precluded from recovering market price based damages. Therefore, the trial court disregarded the $8,900,000 answer to Question 4 and entered a take nothing judgment against TXUPM, which adduced no evidence of damages calculated on a cover basis. TXUPM argues that the trial court erred in doing so because the undisputed facts show that the Wind Farms' defensive cover theory does not apply.

For the reasons discussed below, we sustain TXUPM's fourth point of error and hold that business and commerce code § 2.712(a) requires post-breach conduct taken for the purpose of effecting statutory cover, and, as a matter of law, TXUPM's non-contractual, daily supply and demand balancing activities were not evidence of § 2.712(a) covering transactions. Accordingly, the trial court erred both by submitting Question 5 over TXUPM's objection and by not disregarding the answer to that question as TXUPM requested.

We use the "point of error" nomenclature because that is what TXUPM used in its opening brief.

Because the trial court erroneously relied on the Question 5 answer to ignore the jury's Question 4 market damages finding, and because no party challenged the jury's Question 4 answer in the trial court on legal or factual sufficiency grounds, TXUPM is entitled to recover the $8,900,000 the jury awarded. However, we reject TXUPM's new argument on remand that the market damages award should be increased.

We further conclude that, because TXUPM is entitled to market damages, the trial court erred by concluding that TXUPM was not entitled to retain the $3,075,000 it accessed under the letters of credit the Wind Farms provided to secure their performance under the Agreements. And TXUPM is entitled to recover its attorney's fees because it is the prevailing party on its breach of contract claim.

I. ISSUES

We address only those issues preserved in the trial court, raised in the original briefs, and that remained after the supreme court opinion. Those issues are whether: (i) the trial court erred by submitting the cover question to the jury and refusing to disregard the corresponding answer; (ii) TXUPM should recover market value damages; (iii) TXUPM is entitled to retain the amounts collected under the letters of credit; and (iv) TXUPM is entitled to recover civil practice and remedies code Chapter 38 attorney's fees.

TXUPM acknowledges, and the Wind Farms agree, that, given the supreme court's rulings, we need not consider the following issues previously raised: (1) the trial court's denial of TXUPM's trial amendment; (2) the admission of Dr. Baughman's testimony; (3) the denial of the Wind Farms' motion for JNOV and motion for new trial on their counterclaim; (4) the admission of Dr. Siddiqi's testimony; and (5) the exclusion of evidence in support of the Wind Farms' counterclaim. Although we granted the parties' request to provide supplemental briefing on the remand issues, the parties did not request, nor did we grant, leave to raise new issues.

II. BACKGROUND

A detailed recital of this case's factual and procedural background is provided in our prior opinion. See TXU Portfolio Mgmt. Co., L.P. v. FPL Energy, LLC , 328 S.W.3d 580, 581–85 (Tex.App.–Dallas 2010), aff'd in part, rev'd in part , 426 S.W.3d 59 (Tex.2014). Here, we limit our discussion to the matters needed to resolve the issues before us.

TXUPM sued the Wind Farms alleging that they failed to deliver the contractually required minimum annual quantities of wind generated electric energy (electricity) and related renewable energy credits (RECs) due under the Agreements, and the trial court instructed the jury that the Wind Farms breached the Agreements as TXUPM alleged. The Wind Farms, however, contested TXUPM's legal ability to recover market damages for those breaches by arguing that (i) market price damages under business and commerce code § 2.713(a) are not allowed if the buyer covered for the seller's breaches and (ii) TXUPM covered for the Wind Farms' annual deficiencies within the meaning of business and commerce code § 2.712(a) when it daily replaced from other sources any electricity the Wind Farms did not deliver as projected.

Section 2.712(a) provides: "After a breach within the preceding section the buyer may ‘cover’ by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller." Tex. Bus. & Com. Code § 2.712(a).

The Wind Farms' argument was based on undisputed evidence of TXUPM's real-time "balancing activities." The parties agree that electricity cannot be stored and therefore, once generated, must be immediately transmitted to its destination. According to TXUPM, real-time balancing refers to the constant adjustments it makes to its electricity supply to ensure that it meets its demand for energy at every given moment, without regard to the Wind Farms' annual deficiencies.

At a pretrial hearing, the parties and the trial court discussed the competing damage theories and the Wind Farms' argument that TXUPM had not produced in discovery, and therefore could not present at trial, evidence of its cover costs. The Wind Farms contended that the parties had a factual dispute regarding whether TXUPM's conduct constituted cover that should be submitted to the jury. TXUPM, however, argued that cover did not apply because its daily balancing activities did not occur post-breach. The trial court then said that whether TXUPM covered was likely a fact question for the jury and that TXUPM would receive a take-nothing judgment if the jury answered that TXUPM had covered and TXUPM had no evidence of the costs to cover.

Consistent with its prior position regarding cover, TXUPM at trial adduced evidence of only market damages measured at the time TXUPM learned of the breaches. At the close of evidence, the trial court submitted the two damages related questions at issue. Question 4 instructed the jury to answer a market price damages question for combined electricity and RECs (together, Renewable Energy) independent of its answer to the cover question:

What sum of money, if any, if paid now in cash, would fairly and reasonably compensate [TXUPM] for its damages, if any, that resulted from the Wind Farm's [sic] failure to pay [TXUPM] for the Renewable Energy not provided?

...[T]he amount of damages that you determine must be based on the market value of the Renewable Energy the Wind Farms failed to provide to [TXUPM], and this market value should be the market value as of the time that [TXUPM] learned of the Wind Farms' failure to comply with the Agreements.

Consider the following element of damages, if any, and none other.

The difference between the market value of the Renewable Energy not delivered and the contract price for the Renewable Energy provided in the Agreements.

In response, the jury found $8,900,000 in damages.

At the Wind Farms' request, the trial court also submitted Question 5 to the jury, which asked: "Did [TXUPM] ‘cover’ for the electricity that the Wind Farms failed to provide under the Agreements?" In connection with that question, the trial court instructed the jurors that, " ‘Cover’ means purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements." Because the charge defined "Agreements" to be the three contracts at issue, the jury was required to answer this question in light of the Agreements' terms.

TXUPM objected to submitting Question 5 concerning the Wind Farms' defensive cover theory, arguing that there was no evidence of cover and the question was a comment on the weight of the evidence. For support, TXUPM directed the trial court to our sister court's holding in Jon – T Farms, Inc. v. Goodpasture, Inc. , 554 S.W.2d 743, 750 (Tex.Civ.App.–Amarillo 1977, writ ref'd n.r.e.), disapproved on other grounds by McKinley v. Drozd , 685 S.W.2d 7, 10–11 (Tex.1985), which we discuss below. TXUPM, however, did not object to that instruction for not including § 2.712(a)'s "After a breach" language. The trial court overruled TXUPM's objections and submitted the question to the jury, which found that TXUPM had covered the Wind Farms' failure to provide the electricity due under the Agreements.

TXUPM objected to the instruction on the basis that the instruction (and the question) should refer to renewable energy instead of just electricity. It did not otherwise object to the instruction's content.

Following the verdict, TXUPM moved the trial court to disregard the Question 5 answer and to enter judgment based on the $8,900,000 Question 4 damages answer. To that end, TXUPM argued that Question 5 should not have been submitted since there was no evidence of post-breach replacement electricity purchases. TXUPM, however, did not challenge the Question 4 answer under legal or factual sufficiency grounds as being too low. The trial court denied TXUPM's motion.

Conversely, the Wind Farms moved the trial court to enter judgment that TXUPM take nothing based on the Question 5 answer. The Wind Farms, however, did not alternatively ask the trial court to disregard Question 4 based on legally insufficient evidence to support the $8,900,000 answer to that question. Nor did they ask the trial court to grant a new trial because the evidence was factually insufficient to support that answer.

Based on the jury's cover finding, the trial court entered judgment that TXUPM take nothing on its breach of contract claims. The trial court reasoned that the jury's cover finding precluded TXUPM from recovering the damages the jury found because that award was based on an incorrect market price damages measure and there was no evidence of the correct damages measure (cover costs). Consequently, the trial court also declared that TXUPM had to return the $3,075,000 TXUPM accessed as the beneficiary of letters of credit that the Wind Farms posted as security for payments owed to TXUPM under the Agreements. The trial court thus entered judgment that TXUPM take nothing, and denied both parties' request for attorney's fees under the declaratory judgment statute.

The trial court had previously held as a matter of law that TXUPM could not recover liquidated damages, which constituted a penalty.

TXUPM timely appealed. As noted above, we reversed and rendered judgment for TXUPM based on the Agreements' liquidated damages provisions. The supreme court affirmed in part but reversed our liquidated damages decision, remanding to us the damages issues we discuss below.

III. ANALYSIS

A. Controlling Facts

The controlling facts are few and straightforward:

• Electricity is a fungible, non-segregable product.

• The Agreements required the Wind Farms to deliver specific minimum annual quantities of electricity.

• The Wind Farms failed to meet their annual electricity quotas for the years in question.

• Generated electricity cannot be stored for future use. Thus, TXUPM must simultaneously match the amount of electricity its customers demand with the amount of electricity its suppliers provide.

• TXUPM daily balanced its customer demands with electricity it acquired from its sources, including electricity it acquired from the Wind Farms.

• The Agreements required the Wind Farms to provide TXUPM on a daily basis a document projecting the amount of electricity that the Wind Farm would deliver to TXUPM the next day.

• But no Agreement contractually required a Wind Farm to deliver electricity according to its prior day's estimate. That is, no Wind Farm ever had a contractual duty to deliver its daily projection amount, and thus no Wind Farm ever breached its Agreement by failing to meet its prior day's estimate.

• TXUPM never made a post- year-end electricity purchase to replace electricity that a Wind Farm did not deliver during the prior year.

B. TXUPM's Fourth Point of Error: Did the trial court err by (i) submitting Question 5, (ii) not disregarding the jury's answer to Question 5, and (iii) not entering judgment based on the Question 4 answer?

1. Introduction

In light of the dissenting opinion's analysis, we begin by discussing the relationship between error preservation and standard of review principles as concerns TXUPM's fourth point of error, which presented the following issue:

ISSUE PRESENTED: Did the trial court err in: 1) submitting to the jury the question of whether TXUPM's undisputed continuous "balancing" of energy supplies to energy demands constituted cover as a matter of law; 2) refusing to disregard the jury's incorrect answer to that legal question; and 3) voiding the jury's award of actual damages to TXUPM on the ground that TXUPM failed to submit evidence of "cover" damages when, in fact, TXUPM did not cover as a matter of law?

Under that point of error, TXUPM argues that the undisputed facts established that its daily balancing activities as a matter of law were not covering activities within the meaning of business and commerce code § 2.712(a) because (i) that statute's words "After a breach" mean that, "Cover is a remedy available to a buyer that necessarily first requires the seller's breach of contract[,]" and (ii) "Courts hold that a buyer's purchases to meet its own commitments that occur before the seller's breach are not cover."

As we understand it, TXUPM's position is that as a matter of law cover does not apply here because the undisputed facts establish that it did not make any post-breach electricity purchases to replace the electricity that the Wind Farms failed to provide as their Agreements required. Therefore, the argument goes, whether the Wind Farms' defensive cover theory applied was a pure question of law for the trial court to decide and should not have been submitted to the jury. And, according to TXUPM, had the trial court decided that legal question correctly, it should have entered judgment for TXUPM based on the $8,900,000 answer to Question 4. Because the facts regarding the Wind Farms' performance and TXUPM's balancing activities are undisputed, the key to TXUPM's argument, and the disposition of this point of error, is whether, as a matter of statutory construction, the words "After a breach" in § 2.712(a) constitute an element of the cover remedy.

Thus, regardless of the preservation method TXUPM asserted in the trial court, be it an objection that Question 5 should not be submitted or that the jury's answer should be disregarded, its legal argument comes to us in the context of a no evidence scenario. Therefore, before we can address the merits of TXUPM's fourth point of error we must first determine whether and, if so, how it preserved those arguments in the trial court because the answer to those questions determines the legal framework against which a "no evidence" standard of review applies.

Here, the standard of review framework is intertwined with the statutory construction issue regarding § 2.712(a)'s "After a breach" words. If those words constitute an element of the Wind Farms' defensive cover theory that were omitted from the charge and TXUPM preserved its statutory construction argument in the trial court, the no evidence standard of review is performed under Rule 279's omitted element framework. But, if TXUPM did not preserve its statutory construction argument, then the no evidence review would, as the dissent posits, be performed against the question and instruction as submitted. Accordingly, our first step requires us to first decide the nature and extent of TXUPM's trial court error preservation.

2. Error Preservation Under Appellate Procedure Rule 33.1

Our ability to resolve substantive legal questions, like the statutory interpretation argument that TXUPM presents in this case, ordinarily turns on whether that argument was first preserved in the trial court. See TEX. R. APP. P. 33.1(a)(2) (error preservation is "a prerequisite to presenting a complaint for appellate review"). Error preservation can occur in several different ways. See id . 33.1(a)(1) (preservation can be accomplished by "request, objection, or motion"); see also TEX. R. CIV. P. 273 – 74, 276 (rules specific to jury charge error preservation); T.O. Stanley Boot Co., Inc. v. Bank of El Paso , 847 S.W.2d 218, 220 (Tex.1992) (listing ways to preserve no evidence point). The common characteristic, however, is that the party seeking to preserve a legal argument for our review usually must invoke a procedure that apprises the trial court of the argument in a way that calls for the trial court to decide that issue. See TEX. R. APP. P. 33.1(a) (preservation requires either a ruling or a refusal to rule); Burbage v. Burbage , 447 S.W.3d 249, 257 (Tex.2014) ("[T]he objection must apprise the trial court of the error alleged such that the court has the opportunity to correct the problem."); In re S.H.V. , 434 S.W.3d 792, 801 (Tex.App.–Dallas 2014, no pet.) (party must both "take proper action to make the trial judge aware of the complaint and obtain a ruling, either express or implied").

Here, TXUPM presented its no evidence of cover argument to the trial court both by objecting to the submission of Question 5 and by later asking the trial court to disregard the answer to that question. For the following reasons, we conclude that TXUPM preserved its fourth point of error arguments for our review. See TEX. R. APP. P. 33.1(a)–(b).

Had TXUPM moved for a directed verdict against the Wind Farms' cover theory because there was no evidence of any post-breach replacement purchases, the language of Question 5's instruction would not matter and it would be beyond debate that TXUPM preserved its case dispositive statutory construction argument. See First Nat'l Collection Bureau, Inc. v. Walker , 348 S.W.3d 329, 337 (Tex.App.–Dallas 2011, pet. denied) (discussing legal sufficiency preservation in a jury trial). There is no logical difference between preserving the legal argument that way and doing so by objecting to an instruction for the same reason. In both instances, the challenging party apprises the trial court of the purported legal error in time for the trial court to correct it. In both instances, the challenge is that as a matter of controlling law there is no question for the jury to decide, not whether the jury is being given a technically correct question to decide. The same analysis and result also apply where, as here, the challenging party presents its legal argument in a motion to disregard the answer to that question.

Whether a particular statutory remedy is available is a legal question for the court to decide. See Wal – Mart Stores, Inc. v. McKenzie, 997 S.W.2d 278, 280 (Tex.1999).

Accordingly, by objecting to the submission of Question 5 about whether it effected cover or by asking the trial court to disregard the answer to that question, TXUPM preserved its legal argument that § 2.712(a) requires post-breach conduct taken for the purpose of effecting cover before that remedy applies.

3. Osterberg v. Peca

This is not a situation like Osterberg v. Peca where there was no prior objection to the question or any other basis for preserving the appellants' legal argument to the trial court in the first instance. See 12 S.W.3d 31, 54–56 (Tex.2000) (issue of correct statutory requirements not preserved because the issue was not presented to trial court by motion or charge objection). Specifically the relevant substantive issue in Osterberg was whether the election code's campaign finance reporting requirements were met by substantial compliance with the applicable filing deadline. The jury found that the defendants did not file by the date specified in the charge. The defendants, however, argued on appeal that the sufficiency of the evidence supporting that answer should be measured by a "substantial compliance" standard instead of a literal compliance standard.

The supreme court affirmed the court of appeals' decision to perform its evidentiary sufficiency analyses measured by the literal standard stated in the charge because, as the supreme court repeatedly observed, the defendants never raised their substantial compliance argument in the trial court:

On appeal, the Osterbergs argued for the first time that they need only "substantially comply" with the Election Code's expenditure reporting provisions, and they did so. They contended that because there was insufficient evidence to support the unrequested "substantial compliance" issue , the evidence was legally and factually insufficient to support the jury's finding that they failed to report their expenditures.

The court of appeals held that the Osterbergs waived their substantial compliance argument. The court explained:

The Osterbergs never argued prior to, or during, trial that substantial compliance satisfies the filing requirements of Section 254.124....

* * *

The Osterbergs could instead be arguing that when a court submits a defective issue to the jury, an appellate court should review the sufficiency of the evidence against the question and instruction that the trial court should have submitted—not the one actually submitted—even if the defect was never brought to the court's attention and the question or instruction never requested. That assertion is misguided. Even if Peca [the plaintiff] had a burden of proof with regard to some substantial compliance standard—an issue we do not decide today—it is the court's charge, not some other unidentified law , that measures the sufficiency of the evidence when the opposing party fails to object to the charge. [Citations omitted]. As we recently stated in Holland v. Wal–Mart Stores, Inc. , 1 S.W.3d 91 (1999), if the trial court has "to resolve a legal issue before the jury could properly perform its fact-finding role[,] ... a party must lodge an objection in time for the trial court to make an appropriate ruling without having to order a new trial."

12 S.W.3d at 54–55 (emphasis added); see State Dept. of Highways & Pub. Transp. v. Payne , 838 S.W.2d 235, 241 (Tex.1992) ("There should be but one test for determining if a party has preserved error in the jury charge, and that is whether the party made the trial court aware of the complaint, timely and plainly, and obtained a ruling.").

Here, TXUPM repeatedly apprised the trial court of TXUPM's position. At a minimum, it did so when it objected to the charge. And it did so again when it moved to disregard the Question 5 answer. Because TXUPM told the trial court what TXUPM believed was the correct standard for applying the law to the undisputed facts, we conclude that it preserved its argument in the trial court.

4. Rule of Civil Procedure 279 and Omitted Elements

Because TXUPM preserved its statutory construction argument, and assuming it is correct about what § 2.712(a) requires, Rule 279 would require us to perform a no evidence analysis compared to a deemed finding on that element which would support the trial court's order. See TEX. R. CIV. P. 279 ; Serv. Corp. Int'l v. Guerra , 348 S.W.3d 221, 228–29 (Tex.2011). Specifically, the supreme court's Service Corp. opinion implicitly clarified the line of cases holding that evidentiary sufficiency is measured against the given charge if there is no objection to the question or instruction at issue:

When an element of a claim is omitted from the jury charge without objection and no written findings are made by the trial court on that element then the omitted element is deemed to have been found by the court in such manner as to support the judgment. TEX. R. CIV. P. 279 ; In re J.F.C ., 96 S.W.3d 256, 263 (Tex.2002). Here there was no objection to the charge on the basis that it omitted the element nor did the trial court make findings on it, so there is a deemed finding in support of the judgment. But just as with any other finding, there must be evidence to support a deemed finding. Thus, we next address whether legally sufficient evidence supports the finding here. See In re J.F.C. , 96 S.W.3d at 276 ; Ramos v. Frito–Lay, Inc. , 784 S.W.2d 667, 668 (Tex.1990).

348 S.W.3d at 228–29.

The supreme court so held despite the court of appeals' express holding in that case that, "In the context of a jury trial, the sufficiency of the evidence is reviewed in light of the charge submitted if no objection is made to the charge." Serv. Corp. Int'l v. Guerra , 348 S.W.3d 239, 245 (Tex.App.–Corpus Christi 2009), rev'd , 348 S.W.3d at 228–29. It thus follows that the supreme court rejected the court of appeals' "charge as given" rule for the express language in Rule 279 because the alleged legal error was otherwise preserved. See PopCap Games, Inc. v. MumboJumbo, LLC , 350 S.W.3d 699, 712–13 (Tex.App.–Dallas 2011, pet. denied) ; Alfia v. Overseas Serv. Haus, Inc. , No. 05–11–01390–CV, 2013 WL 3477345, at *3–4 (Tex.App.–Dallas July 9, 2013, no pet.) (mem. op.).

We note that the appellate briefs reflect that Service Corp. moved for a directed verdict and a JNOV on legal and factual sufficiency grounds.

But here it is undisputed that TXUPM never made post-year-end replacement electricity purchases. Thus, the dispositive issue is whether § 2.712(a) imposes a post-breach purchase requirement as an element of proving § 2.712(a) cover. Accordingly, we address the threshold statutory construction question TXUPM preserved in the trial court and presented to us to decide.

5. The Applicable Statutes

Given the undisputed facts, this becomes a statutory construction case. When construing a statute, we attempt to ascertain and effectuate the legislature's intent. City of San Antonio v. City of Boerne , 111 S.W.3d 22, 25 (Tex.2003). We start with the plain and ordinary meaning of the statute's words. Id. If a statute is unambiguous, we generally enforce it according to its plain meaning. Id. We read the statute as a whole and interpret it so as to give effect to every part. Id. ; see also Phillips v. Bramlett , 288 S.W.3d 876, 880 (Tex.2009) ("We further try to give effect to all the words of a statute, treating none of its language as surplusage when reasonably possible.").

Here, it is undisputed that the Agreements required the Wind Farms to deliver annual quantities of electricity as determined by a post-year-end analysis. Moreover, electricity's fungible and ephemeral nature made it impossible for TXUPM to replace previously non-delivered electricity with substitute electricity days, weeks, or months later.Accordingly, as we explain below, unambiguous statutory language compels the result that TXUPM's pre-breach balancing acquisitions as a matter of law could not be evidence of covering transactions that would bar TXUPM from pursuing a market damages theory. That is, any electricity TXUPM acquired from other sources to ensure its pre-breach ability to meet its daily customer demands cannot be considered evidence of a cover purchase because the balancing transactions occurred before there was a contract breach to be remedied. See TEX. BUS. & COM. CODE §§ 2.711(a), 2.712(a).

Specifically, the cover remedy is available to an aggrieved buyer who, after the seller breaches the contract by failing to deliver goods as required, in good faith reasonably purchases goods to substitute for those the seller failed to deliver:

After a breach within the preceding section the buyer may "cover" by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.

Id . § 2.712(a) (emphasis added).

The "preceding section" is § 2.711, captioned "Buyer's Remedies in General; ...." As its caption suggests, § 2.711 states the remedies generally available to a buyer when the seller breaches its contract by failing to deliver a contractually required quantity of goods. Id. § 2.711(a). A buyer so situated may choose between effecting cover under § 2.712 or recovering market damages under § 2.713 :

Where the seller fails to make delivery ... the buyer may ... in addition to recovering so much of the price as has been paid (1) "cover" and have damages under the next section [ § 2.712 ] as to all the goods affected whether or not they have been identified to the contract; or (2) recover damages for non-delivery as provided for in this chapter ( Section 2.713 ).

Id . § 2.711(a) (emphasis added).

Accordingly, cover "is not a mandatory remedy for the buyer." Id . § 2.712 cmt. 3. That is, an aggrieved buyer need not minimize its damages by "covering" and not doing so does not bar it from pursuing a market price damages theory:

Under § 2.712(c), upon seller's breach the buyer is not required to cover as a means of minimizing damages, and his failure to effect cover does not bar him from any other remedy. Thus, on seller's breach a buyer is free to choose between damages based upon the difference between the contract price and the cost of cover under § 2.712, and damages for non-delivery, consisting of the difference between the market price at the time when the buyer learns of the breach and the contract price under § 2.713(a).

Jon – T Farms, Inc. , 554 S.W.2d at 750.

Thus, as a matter of unambiguous statutory language, a buyer aggrieved by a seller's failure to deliver the contractually required quantity of goods may either effect cover or recover market damages. See TEX. BUS. & COM. CODE §§ 2.711(a), 2.712(a). Likewise, also as a matter of plain statutory language, a buyer may effect a cover remedy only "[a]fter a breach." See id . § 2.712(a).

Because the statutory language is unambiguous and there is no applicable precedent from us or the supreme court, we could end our analysis of this legal question here.

6. Case law

The parties have not presented, and we have not found, a case squarely on point. But Jon – T Farms, Inc. is close. In that case, the buyer (Goodpasture) and the seller (Jon-T) in January contracted for the seller to deliver grain to the buyer in October and November of that same year. Unfortunately, a railcar shortage developed and by November 30th the seller had delivered only slightly more than 20% of its contractual requirement. The buyer, however, encouraged the seller to keep delivering, exercised its right to extend the delivery period, and even used its own trucks to help the seller make deliveries.

But grain prices had increased after the parties created their contract, and the seller on December 10th sent the buyer a letter repudiating the contract by refusing to deliver more grain unless the buyer agreed to a price increase. The buyer, however, declined to do so and a week later sued the seller for § 2.713 market damages. In response, the seller (like the Wind Farms here) argued that the buyer could not recover market damages because (i) the buyer covered for the seller's breaches by meeting the buyer's customers' demand with grain that the buyer had otherwise previously arranged for and (ii) having "covered" for the seller's breaches, market price damages were no longer an available remedy.

The case was tried to a jury, which found that the seller breached the contract and caused the buyer substantial market price damages. The trial court rejected the seller's argument that the buyer had used its pre-breach arrangements to effect cover, thereby precluding a market price damages recovery, and entered judgment for the buyer accordingly.

On appeal, the seller argued that (i) there was no evidence supporting the damages finding because the buyer had used its other grain sources to cover for the seller's delivery breaches; (ii) the buyer did not proffer any evidence of its cover damages; and (iii) the alleged covering conduct precluded a market price damages recovery.

Our sister court in Amarillo reviewed business and commerce code §§ 2.711 – 2.713 in detail, analyzed the buyer's inventory management practices, and rejected the seller's argument because the buyer was not required to cover and there was no evidence that it made any post-breach purchases for the purpose of covering for the seller's non-delivery breaches:

The testimony of the plaintiff's witnesses, Long and Truitt, was that Goodpasture normally bought sufficient grain in order to meet its contracts for sale. There is no evidence that in Goodpasture's mode of operation it makes a specific purchase contract in order to meet the requirements of a specific sales contract. The company maintains "position" records as to its overall operation which disclose the total amount of grain it has contracted to sell and the total amount it has contracted to buy, and its "position" is maintained in order to fill its sales contracts. The contract entered into between Jon-T and Goodpasture cannot be said to have been entered into to fill any particular outstanding commitment. The grain purchased is commingled with other grain. Although in the overall operation Goodpasture may have bought some grain to compensate for the undelivered Jon-T grain to insure an adequate supply to meet its commitments, there is no testimony that Goodpasture went out and bought specific grain to make up for the specific amount of grain undelivered by Jon-T.

In fact, this record reveals that Goodpasture filed its suit within a week after learning of Jon-T's breach and, as was its right, elected to seek the difference between the contract and market price, together with incidental and consequential damages. Goodpasture was not required to cover and there is no evidence

of Goodpasture's purchase of grain for the purpose of cover during that week.

554 S.W.2d at 750 (emphasis added).

In sum, the Amarillo court rejected the seller's argument because the buyer's pre-breach purchases made to ensure its ability to meet its own customers' demands were no evidence of post-breach replacement purchases for the purpose of remedying the seller's actual breach.

The Jon – T facts are remarkably similar to ours except that, unlike generated electricity, (i) grain can be held in inventory and (ii) a specific lot can be segregated and delivered to a particular customer. And the Wind Farms argue that there was no testimony that the buyer (Goodpasture) bought specific grain to replace the grain that the seller (Jon-T) breached the contract by failing to deliver, whereas, here there was testimony that TXUPM's daily balancing practice was to take the Wind Farms' electricity first and then, if there was a shortfall from the Wind Farms' daily estimate, acquire replacement electricity from other sources to settle the difference. For several reasons, however, those distinctions and that argument do not suggest a different result here.

One, that grain can be held in inventory, segregated, and delivered to a specific customer would present a more compelling argument that a purchase from a different source replaced a specific seller's non-delivered grain. That difference is significant because the cover damages measure requires the buyer to match the replacement goods' cost with the undelivered goods' contract price and to make additional adjustments related to specific matching transactions:

The buyer may recover from the seller as damages the difference between the cost of cover and the contract price together with any incidental or consequential damages ... but less expenses saved in consequence of the seller's breach.

TEX. BUS. & COM. CODE § 2.712(b). That calculus, however, would be extraordinarily difficult, if not impossible, where, as here, the breach occurs and is determined only after a full year of daily transactions, some of which were below and some of which were above the day-before projections, and the buyer has other supply sources simultaneously providing fungible and non-segregable goods.

Two, Jon-T 's reference to "undelivered" goods is statutorily significant. Section 2.712(a) affords the cover remedy to compensate for a breach within § 2.711(a)'s scope. Section 2.711(a) in turn enumerates a buyer's remedies, including cover, when "the seller fails to make a delivery." Id. § 2.711(a). But not just any "non-delivery" will support the cover remedy. Instead, the non-delivery must first breach a contract. This principle is necessarily so because the code remedies apply only if there has first been a contractual failure to perform within the meaning of code subchapter E concerning "Performance" that produces a breach within the meaning of subchapter F concerning "Breach, Repudiation and Excuse." That is, there is no statutory remedy unless there is a prior contract breach as statutorily defined.

Three, because the cover remedy is an alternative to market damages, its application requires an intentional decision to make a substitutionary purchase for the purpose of remedying a breach. That optional nature combined with § 2.713(a)'s requirement that the market contract price difference be measured "at the time when the buyer learned of the breach" means that the buyer must know of the breach and related quantity before it can decide on an informed basis between its cover and market price damages. See id . § 2.713(a). Accordingly, the Amarillo court correctly focused on whether there was evidence of post-breach purchases made for the purpose of effecting cover as opposed to routine pre-breach purchases to meet operational needs. See Jon – T Farms, Inc. , 554 S.W.2d at 750. Thus, pre-breach balancing transactions for the purpose of meeting customer needs do not satisfy the statutory language or scheme.

The seller also argued that certain grain purchases in the following spring were cover transactions, but the court rejected that argument because the court did "not find any evidence of such specific purchases for such alleged cover set out in the record." Jon – T Farms, Inc., 554 S.W.2d at 750. Thus, that holding as to those post-breach transactions reinforces the principle that specific post-breach purchases must be matched to specific breaching non-deliveries to be cover transactions.

The cases cited by the Wind Farms are not persuasive. Those cases involve anticipatory repudiation, which is not at issue here. See, e.g., Dura – Wood Treating Co. v. Century Forest Indus., Inc., 675 F.2d 745, 748 (5th Cir.1982) (seller advised buyer that it would not be able to honor its contractual obligation to sell); Commonwealth Edison Co. v. Allied Chem. Nuclear Prods., Inc., 684 F.Supp. 1434, 1437 (N.D.Ill.1988) (fact issue concerning use of pre-existing contracts to cover after seller refused to provide uranium before the time of delivery claiming contract was void due to government action).

Finally, we note that in another part of the charge in the present case, the trial court instructed the jury that the Wind Farms had breached the Agreements and the breach upon which TXUPM's damages must be measured was the Wind Farms' failure to pay TXUPM for their annual deficiencies. This implicitly recognizes that breach was not measured on an interim basis during a compliance year, but rather that performance was assessed on an annual basis.

Therefore, we conclude that Question 5 should not have been submitted and once answered should have been disregarded. Thus, the trial court erred as a matter of law in both instances because that question was legally immaterial. See Spencer v. Eagle Star Ins. Co. , 876 S.W.2d 154, 157 (Tex.1994). We sustain the first part of TXUPM's fourth point of error.

Furthermore, the trial court used the immaterial answer to Question 5 to disregard the jury's answer to Question 4 in which the jury found that the Wind Farms breaches regarding electricity and RECs caused TXUPM to suffer $8,900,000 in market damages for failing to deliver Renewable Energy, which the Agreements define to include both electricity and Renewable Energy Credits (RECs). Doing so was harmful, and thus reversible, error if it probably caused the rendition of an improper judgment (or probably prevented the appellant from properly presenting its case on appeal). TEX. R. APP. P. 44.1(a).

Because we conclude that the trial court should not have submitted Question 5 and should have disregarded the answer to it, we next consider whether TXUPM is entitled to recover the market damages the jury found in response to Question 4.

C. Should TXUPM recover market value damages, and if so, in what amount?

1. The Answer to Question 4

Under § 2.713, the damages measure for a seller's non-delivery is the difference between the market price at the time when the buyer learned of the breach and the contract price together with any incidental and consequential damages, but less expenses saved in consequence of the seller's breach:

Subject to the provisions of this chapter with respect to proof of market price (Section 2.723), the measure of damages for non-delivery or repudiation by the

seller is the difference between the market price at the time when the buyer learned of the breach and the contract price together with any incidental and consequential damages provided in this chapter (Section 2.715), but less expenses saved in consequence of the seller's breach.

TEX. BUS. AND COM. CODE. § 2.713(a). The jury awarded TXUPM $8,900,000 in damages.

The Wind Farms argue that there is no evidence to support market value damages because TXUPM's expert, Manu Asthana, offered irrelevant and unreliable expert testimony. According to the Wind Farms, Ashthana's models (i) do not measure the value of the Wind Farms' electricity at the correct time, and (ii) rely on inapplicable and unreliable pricing reports.

This no evidence point, however, was not preserved for our review. A no evidence point is preserved through: (1) a motion for instructed verdict; (2) a motion for judgment notwithstanding the verdict; (3) an objection to the submission of the issue to the jury; (4) a motion to disregard the jury's answer to a vital fact issue; or (5) a motion for new trial. T.O. Stanley Boot Co. , 847 S.W.2d at 220. Although the Wind Farms availed themselves of many of these procedural vehicles, every challenge to TXUPM's market damages request rested solely on the ground that market damages were not available because TXUPM had covered.

For example, the Wind Farms' motion for directed verdict argued that Asthana's damage models were not competent evidence solely because he failed to account for cover and market damages are unavailable to a party who covers. Likewise, when the Wind Farms objected to the jury charge, they complained that the charge did not state the appropriate damages measure because the appropriate measure was cover. Furthermore, there was no legal or factual sufficiency challenge to the $8,900,000 finding when the Wind Farms moved for judgment. And there was no motion for new trial, JNOV, or to disregard on these grounds. Consequently, the jury's finding that TXUPM suffered $8,900,000 in market damages is an unchallenged finding that sets a damages floor. See Carbona v. CH Med. Inc ., 266 S.W.3d 675, 687 (Tex.App.–Dallas 2008, no pet.).

On remand, the Wind Farms rely on § 1.305(a) for the premise that TXUPM should not recover the damages the jury awarded because TXUPM suffered no actual economic injury. See TEX. BUS. & COM. CODE § 1.305(a). This section provides:

The remedies provided by this title must be liberally administered to the end that the aggrieved party may be put in as good a position as if the other party had fully performed, but neither consequential or special damages nor penal damages may be had ....

Id . Comment 1 to this section states that "Compensatory damages are limited to compensation." Id . cmt. 1. Thus, the Wind Farms contend that we should render a take-nothing judgment because TXUPM suffered no actual economic injury.

This was not raised as an objection to Question 4, nor did the Wind Farms argue that the trial court should disregard the Question 4 answer for that reason. And the Wind Farms did not make that argument in their opening brief. Accordingly, that argument is not properly before us. See TEX. R. APP. P. 33.1, 38(f).Therefore, on this record, TXUPM is entitled to recover at least the $8,900,000 in market damages the jury found in Question 4. We thus sustain the first part of TXUPM's fourth point of error concerning the recovery of $8,900,000 in market damages.

The Wind Farms' opening brief cited § 1.305 as supporting its argument that TXUPM could not recover market damages because it, according to the Wind Farms, elected to cover for the Wind Farms' electricity shortages.

2. TXUPM's Request for Increased Damages

TXUPM's remand brief argues that TXUPM's market damages recovery should be increased. Specifically, TXUPM contends that the jury "plainly" discounted the $20,900,000 damages it requested based on the Wind Farms' expert's testimony that damages should be reduced by $10,600,000 for lack of transmission capacity. Because this Court and the supreme court rejected the trial court's conclusion that TXUPM was contractually obligated to provide transmission capacity, TXUPM maintains that it is "entitled to the full amount of market price damages, untainted by the district court's erroneous transmission capacity holding." To this end, TXUPM requests that we add $10,600,000 to the jury's $8,900,000 finding, and render judgment for that amount. We decline to do so.

In the court below, TXUPM's motion for judgment asked the court to enter judgment based on the $8,900,000 award. Likewise, its brief in support of its motion for judgment prayed for an $8,900,000 judgment. TXUPM's arguments in its initial appellate briefing were consistent with those requests. TXUPM, however, never asked the trial court to enter a $19,500,000 judgment, nor did it initially claim that the trial court erred in not doing so. Thus, there is no basis preserved for our doing so now. See TEX. R. APP. P. 33.1.

TXUPM's remand brief also argues that the law of the case doctrine applies to foreclose all challenges to its request for a judgment "in excess of $20 million." We disagree. Neither this Court nor the supreme court decided any part of TXUPM's claim for market damages, and the law of the case does not apply to legal issues that were not decided in prior appeals. See Grant Thornton LLP v. Suntrust Bank, 133 S.W.3d 342, 363 (Tex.App.–Dallas 2004, pet. denied).

In addition, there is no basis for us to conclude as a matter of law that absent the trial court's transmission capacity holding the jury would have awarded TXUPM $19,500,000 in damages. TXUPM's expert presented nine damage models and the amount of damages was disputed. We cannot speculate about what the jury intended when reaching a particular verdict, which entering the verdict TXUPM now requests would require us to do. See Houston Med. Testing Servs. Inc., v. Mintzer , 417 S.W.3d 691, 696 (Tex.App.–Houston [14th Dist.] 2013, no pet.).

TXUPM argues that an appellate court may increase a jury award when the higher amount is established as a matter of law. See, e.g. , Hill v. Spencer & Son, Inc ., 973 S.W.2d 772, 775–76 (Tex.App.–Texarkana 1998, no pet.) (appellate court may render judgment if no evidence supports the award and undisputed evidence conclusively established the amount as a matter of law). Here, however, there is no undisputed amount, and it is not established as a matter of law. We thus resolve the second part of TXUPM's second issue against it.

3. Conclusion

For the reasons previously stated, we conclude that:

(i) effective cover under business and commerce code § 2.712(a) requires as an element that the buyer make an after the breach purchase or contract to purchase goods in substitution for those due from the seller;(ii) resolution of TXUPM's fourth point of error requires us to conduct a no evidence review to determine whether the trial court erred by submitting Question 5 to the jury or by denying TXUPM's motion to disregard the answer to that Question;

(iii) because the "after a breach" element was omitted from the Question 5 instruction without objection but TXUPM preserved its statutory construction argument, our no evidence review is conducted under Rule 279 measured against that missing element;

(iv) the trial court instructed the jury that, "It has been established that the Wind Farms were deficient in providing the required minimum Annual Quantity of Renewable Energy for the years 2002, 2003, 2004 and 2005 and failed to comply with the Agreements by failing to pay [TXUPM] for this deficiency[;]"

(v) no party challenged on appeal the legal or factual sufficiency of the evidence supporting that instruction;

(vi) it is undisputed that there is no evidence that TXUPM made any post-breach purchases of electricity to substitute for electricity that the Wind Farms failed to deliver as contractually required;

(vii) the trial court erred by submitting Question 5 and by denying TXUPM's motion to disregard the answer to that Question;

(viii) no party challenged on appeal the legal or factual sufficiency of the evidence supporting the Question 4 answer;

(ix) the trial court erred by denying TXUPM's motion to enter judgment based on the Question 4 answer; and

(x) the trial court's errors caused the rendition of an improper judgment.

Accordingly, we reverse the trial court's judgment that TXUPM take nothing on its breach of contract claim and render judgment that TXUPM recover from the Wind Farms damages of $8,900,000.

D. TXUPM's Fifth Point of Error: Is TXUPM entitled to retain the amounts collected under the letters of credit in partial satisfaction of the judgment?

TXUPM's fifth issue argues that it is entitled to retain the amounts collected under the Wind Farms' letters of credit. We agree.

The trial court declared that TXUPM was required to return the $3,075,000 proceeds from the Wind Farms' letters of credit that were posted as security for the Wind Farms' performance under the Agreements. That ruling rested on the trial court's holding that TXUPM was not entitled to recover damages. But we have concluded that TXUPM is entitled to recover market damages. Therefore, the trial court erred in its conclusion, and TXUPM is entitled to retain the letter of credit proceeds in partial satisfaction of the judgment. We sustain TXUPM's fifth issue.

E. Is TXUPM entitled to recover attorney's fees?

The district court exercised its discretion under Chapter 37 to deny both parties' attorney's fees and award costs to the Wind Farms. See TEX. CIV. PRAC. & REM. CODE § 37.009. Because neither party challenges that ruling, a request for Chapter 37 fees is not before us.

But TXUPM's motion for judgment on the verdict also argued that TXUPM was entitled to Chapter 38 attorney's fees and TXUPM prayed for fees in its original briefing when it asked this Court to render judgment on the breach of contract claim. Thus, TXUPM argues that it is entitled to recover Chapter 38 attorney's fees because it established that the Wind Farms breached the Agreements and it is the prevailing party entitled to damages. See TEX. CIV. PRAC. & REM. CODE § 38.001. We agree.

Civil practice and remedies code Chapter 38 allows a reasonable attorney's fees recovery in breach of contract cases. Id . To recover attorney's fees under § 38.001, a party must prevail on the underlying claim and recover damages. Ventling v. Johnson , 466 S.W.3d 143, 154 (Tex.2015) ; Intercontinental Grp. P'ship v. KB Home Lone Star L.P ., 295 S.W.3d 650, 653 (Tex.2009). An award of reasonable attorney's fees is mandatory under this section if there is proof of the reasonableness of the fees. Ventling , 466 S.W.3d at 154. A request in a prayer is sufficient to support an attorney's fees award. See Tull v. Tull , 159 S.W.3d 758, 762 (Tex.App.–Dallas 2005, no pet.) ("A general request for attorney's fees in the prayer of the pleading is itself sufficient to authorize the award of attorney's fees.").

We thus sustain TXUPM's request for attorney's fees. We reverse the trial court's judgment awarding costs to the Wind Farms, render judgment that TXUPM is entitled to recover its Chapter 38 attorney's fees, and remand the case to the trial court to determine the amount of such fees.

The parties agreed on the record that attorney's fees and supporting evidence would be submitted to the trial court for determination after the verdict. Although TXUPM's brief requests rendition of judgment for fees in a specific amount, it does not cite any authority or provide any record references to support rendition. Accordingly, we leave the fees issue to the trial court on remand. See Delta Steel Bldgs. Co. v. Crow, 633 S.W.2d 343, 344 (Tex.App.–Dallas 1982, no writ) (remanding for determination of reasonable attorney's fee).

IV. DISPOSITION

We affirm the trial court's judgment that neither party is entitled to recover Chapter 37 attorney's fees.

We reverse the trial court's judgment that: (i) TXUPM take nothing on its breach of contract claim; (ii) the Wind Farms recover costs; and (iii) TXUPM return the funds accessed under the letters of credit.

We render judgment that TXUPM recover from the Wind Farms damages of $8,900,000 plus pre and post judgment interest and reasonable attorney's fees, and we further render judgment that TXUPM is entitled to retain the $3,075,000 it accessed under the letters of credit in partial satisfaction of that judgment.

We remand to the trial court solely for the purpose of calculating pre and post judgment interest and to determine the amount of reasonable Chapter 38 attorney's fees and costs TXUPM is entitled to recover.

Evans, J., dissenting

Dissenting Opinion by Justice Evans

I regret that I must respectfully dissent. I disagree with the majority's standard of appellate review used to evaluate the fourth issue regarding cover raised by TXU Portfolio Management Company, L.P. n/k/a Luminant Energy Company, L.L.C. (TXUPM), so I arrive at a different result using what I understand is the correct standard. Using the charge as submitted to measure whether there was any evidence to submit the question and support the jury's answer to it, I conclude the evidence was legally sufficient to support submission of the question and the jury's answer that TXUPM covered by "purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements." For the reasons stated below, I would affirm the take- nothing judgment of the district court on TXUPM's breach of contract claims against FPL Energy, LLC, FPL Energy Pecos Wind I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P. (Wind Farms). I then reach the subsequent issue regarding TXUPM's draw down of $3.075 million from the Wind Farms' letters of credit and conclude the trial court did not err in granting declaratory relief that TXUPM must return the money.

I.

STANDARD OF REVIEW

I "begin by determining the appropriate standard of review, then move in turn to each challenge." Fin. Comm'n of Tex. v. Norwood , 418 S.W.3d 566, 584 (Tex.2013).

TXUPM stated its fourth issue as the following:

ISSUE PRESENTED: Did the trial court err in: 1) submitting to the jury the question of whether TXUPM's undisputed continuous "balancing" of energy supplies to energy demands constituted cover as a matter of law; 2) refusing to disregard the jury's incorrect answer to that legal question; and 3) voiding the jury's award of actual damages to TXUPM on the ground that TXUPM failed to submit evidence of "cover" damages when, in fact, TXUPM did not cover as a matter of law?

The Wind Farms proposed, the trial court submitted, and the jury answered the following cover question:

QUESTION FIVE

Did TXU "cover" for the electricity that the Wind Farms failed to provide under the Agreements?

"Cover" means purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements.

Answer Yes or No:

Yes X No ______

TXUPM objected that no evidence supported the submission of Question 5 or the definition and objected that the question incorrectly separated electricity from the RECs and should have referenced annual quantities of renewable energy promised but not delivered under the agreements. But TXUPM did not bring forward any complaint in its initial brief on appeal to the form of the question or instruction.

A no-evidence or legal insufficiency issue is preserved in the trial court by any one of the following methods: "(1) a motion for instructed verdict, (2) a motion for judgment notwithstanding the verdict, (3) an objection to the submission of the issue to the jury, (4) a motion to disregard the jury's answer to a vital fact issue or (5) a motion for new trial." Cecil v. Smith , 804 S.W.2d 509, 510–11 (Tex.1991) (citing Aero Energy, Inc. v. Circle C Drilling Co. , 699 S.W.2d 821, 822 (Tex.1985) ); see First Nat'l Collection Bureau, Inc. v. Walker , 348 S.W.3d 329, 338 (Tex.App.–Dallas 2011, pet. denied) ; accord TEX. R. CIV. P. 301. So when TXUPM objected at the charge conference that no evidence supported the submission of Question 5 regarding cover, it preserved its legal insufficiency issue to the submission of and the jury's answer to the cover question.1 See Cecil , 804 S.W.2d at 510–11.The starting point generally of a legal or factual sufficiency review is the charge and instructions to the jury. Golden Eagle Archery, Inc. v. Jackson , 116 S.W.3d 757, 762 (Tex.2003). This is necessary in order to "first have a clear understanding of the evidence that is pertinent to [the appellate court's] inquiry." Id . When there is no objection to the form of a charge brought forward as an issue on appeal, we should assume the charge is correct without deciding that issue and evaluate the sufficiency of the evidence against the charge. See Akin, Gump, Strauss, Hauer & Feld, L.L.P. v. Nat'l Dev. & Research Corp. , 299 S.W.3d 106, 112 (Tex.2009) ("Because there was no objection to the charge as submitted, we assume, without deciding, that the instruction was correct and measure the evidence by the charge as given.") (citing Osterberg v. Peca , 12 S.W.3d 31, 55 (Tex.2000) ); Boehringer v. Konkel , 404 S.W.3d 18, 27 (Tex.App.–Houston [1st Dist.] 2013, no pet.) (where party made objections to question during charge conference but did not bring those challenges forward in appeal yet complained on appeal regarding factual and legal sufficiency of the jury's answer to the question, court would not imply a challenge to the wording of the question, so it measured the sufficiency of the evidence by the question in the charge), disapproved on other grounds by Ritchie v. Rupe , 443 S.W.3d 856 (Tex.2014). Even where a party argues the submission of a question is not supported by evidence or is precluded as a matter of law by certain evidence but that party does not object to the form of the question submitted, we measure the legal sufficiency of the evidence by the form of the question asked. See Shows v. Man Engines & Components, Inc. , 364 S.W.3d 348, 357 (Tex.App.–Houston [14th Dist.] 2012), aff'd , 434 S.W.3d 132 (Tex.2014) ; Houston Poly Bag I, Ltd. v. Kujanek , 370 S.W.3d 82, 88 (Tex.App.–Houston [14th Dist.] 2012, no pet.) (applied Osterberg evaluating legal sufficiency of evidence against charge as given because appellant had not objected to form of question while acknowledging appellant had objected at charge conference it had no legal duty); Lone Starr Multi – Theatres, Ltd. v. Max Interests, Ltd. , 365 S.W.3d 688, 694–95 (Tex.App.–Houston [1st Dist.] 2011, no pet.) (appellant objected to one question on sufficiency grounds but not to form of question so court used charge to analyze sufficiency of evidence citing Osterberg ). "Even if another legal theory was argued to the jury and explained by the lawyers in argument, we are bound by the instructions given to the jury and presume that the jury followed those instructions." Seger v. Yorkshire Ins. Co., Ltd. , No. 13–0673, 503 S.W.3d 338, 407, 2016 WL 3382223, at *12 (Tex. June 17, 2016) (no objection to direct employee instruction; lawyers argued alter ego theory not in charge). We measure the legal sufficiency by the form of question and instructions submitted to the jury even where an appellant objected that the question as a whole was not in broad form and was a comment on the weight of the evidence and objection to a different instruction in the question, but did not object to the instruction at issue in the appeal. See Eagle Oil & Gas Co. v. TRO – X, L.P. , 416 S.W.3d 137, 148–49 (Tex.App.–Eastland 2013, pet. denied).

TXUPM does not present any argument why we should not use the charge and instead use what it views as the correct law to evaluate the sufficiency of the evidence. In fact, TXUPM does not argue for any standard for our review of its complaint that the trial court submitted the cover question to the jury and the jury answered it "yes" thereby causing reversible error. It appears from its briefing that TXUPM assumes a de novo standard of review. For that reason alone, we should default to use the charge submitted to the jury for the legal standard until a party adequately briefs with authorities why we should use a different standard. See EMC Mortg. Corp. v. Jones , 252 S.W.3d 857, 869 (Tex.App.–Dallas 2008, no pet.) (evaluating sufficiency of the evidence based on law stated in charge reasoning, "Although EMC's sufficiency argument is based on this [legally correct] standard, EMC offers no explanation as to why we should measure sufficiency based upon the correct legal standard rather than by the charge that the jury was actually given.").

In its original brief on appeal, TXUPM did not challenge the form of Question 5 or the definition of cover, but argued its view of the correct law directly from sections 2.712 and 2.713 of the Uniform Commercial Code and opinions interpreting those provisions. In its brief on remand TXUPM argued the definition of cover in the charge "failed to instruct the jury of the crucial requirement that cover occur ‘after’ breach." Generally, a new issue may not be raised for the first time after the opening brief. See, e.g. , TEX. R. APP. P. 33.1(i) (appellant's brief must include "a clear and concise argument for the contentions made, with appropriate citations to authorities and to the record"); 38.3 (reply brief to address "any matter in the appellee's brief"); Stull v. LaPlant , 411 S.W.3d 129, 136 n.3 (Tex.App.–Dallas 2013, no pet.). For the reasons stated above, the Wind Farms urged us not to consider TXUPM's complaint about the definition of cover being incorrect made for the first time in its brief on remand. I conclude the Wind Farms are correct because TXUPM does not complain on appeal about error in the form of the definition of "cover" in Question 5 or argue for a standard of review different from the charge as submitted.2 See Boehringer , 404 S.W.3d at 27 (legal sufficiency evaluated by charge as submitted where objection to form of question not brought forward on appeal); EMC Mortg. Corp. , 252 S.W.3d at 869 (where appellant did not argue for standard of review different than charge as submitted, charge was standard for legal sufficiency review); see also Eagle Oil & Gas Co. , 416 S.W.3d at 148–49.

I, therefore, would follow the supreme court's and our precedent by beginning our analysis of legal or factual sufficiency with the charge as submitted unless a party has presented argument why we should use a different standard. See Golden Eagle Archery , 116 S.W.3d at 762 ; EMC Mortg. , 252 S.W.3d at 869. For these reasons, I conclude the correct analysis in this case is to evaluate the legal sufficiency of the evidence for the submission of, and to support the jury's answer to, Question 5 using the question and instruction that were submitted in the charge. I begin my analysis there using the traditional standards for evaluating the legal sufficiency of the evidence. II.

We conduct a legal sufficiency review by considering all the evidence before the jury, crediting evidence in support of the verdict if reasonable jurors could, and disregarding evidence contrary to the verdict unless reasonable jurors could not. See City of Keller v. Wilson, 168 S.W.3d 802, 823, 827 (Tex.2005). We consider all the evidence in the light most favorable to the judgment indulging every reasonable inference in favor of the judgment. See St. Joseph Hosp. v. Wolff, 94 S.W.3d 513, 520 (Tex.2003). "On an issue where the opposing party bears the burden of proof, we sustain a legal-sufficiency challenge to an adverse finding if our review of the evidence demonstrates a complete absence of a vital fact, or if the evidence offered is no more than a scintilla." Burbage v. Burbage, 447 S.W.3d 249, 259 (Tex.2014) (citing Waste Mgmt. of Tex., Inc. v. Tex. Disposal Sys. Landfill, Inc., 434 S.W.3d 142, 156 (Tex.2014) ). Anything more than a scintilla of evidence is legally sufficient to support the jury's finding. See Formosa Plastics Corp. USA v. Presidio Eng'rs & Contractors, Inc., 960 S.W.2d 41, 48 (Tex.1998). When the evidence offered to prove a vital fact is so weak as to do no more than create a mere surmise or suspicion of its existence, the evidence is no more than a scintilla and, in legal effect, is no evidence. Kindred v. Con/Chem., Inc., 650 S.W.2d 61, 63 (Tex.1983). When there is no objection to the form of a charge submission, we measure the legal and factual sufficiency of the evidence against the jury charge as given. See Wolff, 94 S.W.3d at 530 (citing Osterberg, 12 S.W.3d at 55 ("it is the court's charge, not some other unidentified law, that measures the sufficiency of the evidence when the opposing party fails to object to the charge")).
In conducting our review of the legal sufficiency of the evidence, we are mindful that the jury, as fact finder, was the sole judge of the credibility of the witnesses and the weight to be given their testimony. City of Keller, 168 S.W.3d at 819 ; Hinkle v. Hinkle, 223 S.W.3d 773, 782 (Tex.App.–Dallas 2007, no pet.). "[Jurors] may choose to believe one witness and disbelieve another. Reviewing courts cannot impose their own opinions to the contrary." City of Keller, 168 S.W.3d at 819 (footnotes omitted).

ANALYSIS OF COVER

" ‘Cover’ means purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements."

TXUPM first argues section 4.04 of each contract with the Wind Farms requires an annual reconciliation of annual minimum quantities of electricity and RECs and, therefore, the Wind Farms could not and did not breach the agreements until each annual reconciliation occurred. The Wind Farms argue one of the problems with TXUPM's argument is it assumes the annual reconciliation included an annual minimum electricity requirement in conflict with the supreme court's opinion. The supreme court carefully analyzed TXUPM's view that the annual reconciliation involved both electricity and RECs and rejected that position. FPL Energy, LLC , 426 S.W.3d at 67–69. Section 4.04 refers only to RECs, does not include electricity, Net Energy (a defined term including both electricity and RECs), or any other reference to electricity. For example, section 4.04(a) announces, "At the end of each calendar year, ... the amount of RECs produced in that year is compared to the Annual Quantity." Sections 4.04(b) and (c) deal with the amount of RECs exceeding or being less than the Annual Quantity. Sections 4.04(d), (e), and (f) make provision for how the parties would deal with the Wind Farms' deficient delivery of RECs. In making its determination, the supreme court rejected TXUPM's position that in the contracts "the parties simply use RECs as a counting mechanism for both" RECs and electricity. Id . The supreme court determined that section 4.04 "deals only with RECs, and not electricity." Id . at 67. Because the annual reconciliation provisions of the contracts do not involve electricity deficiencies, I agree with the Wind Farms that the annual reconciliation contractual provisions do not provide support for TXUPM's argument that there is legally insufficient evidence to support the jury's verdict that TXUPM covered the electricity deficiencies of the Wind Farms. This case was tried and submitted to the jury by a charge that separated electricity from RECs and limited the issue of cover to electricity deficiencies in the definition of cover: " ‘Cover’ means purchasing or producing electricity as a substitute for the electricity promised but not delivered under the agreements." (Emphasis added). The supreme court's analysis of the contracts indicates that the trial court was correct to approach electricity separately from RECs.

TXUPM's other argument is it could not cover the Wind Farms' breach of annual minimum electricity requirements in the contracts because it would have had to cover during each year before breach of the Agreements occurred. In support, TXUPM argues the Wind Farms could not breach during any given year an annual minimum electricity requirement until the close of that year, so TXUPM's real-time balancing of electricity could not occur after the Wind Farms' breach—as required by section 2.712(a) —and still occur within the year. First, TXUPM does not cite any cases from any jurisdiction making this conclusion based on an annual quantity requirement in a contract. Second, TXUPM did not bring forward on appeal any issue that the trial court erred by omitting "after breach" or should have referenced annual quantities of renewable energy promised but not delivered under the agreements in the definition of cover. Thus, we are bound by the definition of cover in the charge: " ‘Cover’ means purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements."

For this reason, I do not decide this issue under sections 2.712(a) and 2.713(a) of the Uniform Commercial Code.

The Agreements to which the cover definition directed the jury were three contracts that were the same in most respects relevant to the issues on appeal. They required in section 4.01, each wind farm "shall sell and deliver, and [TXUPM] shall purchase and accept, all of the RECs and Net Energy produced by" two of the wind farms and 38% of the RECs and Net Energy produced by the third wind farm. (Net Energy was, essentially, the amount of electricity the Wind Farms delivered to the electric grid). The contracts stated in section 2.01 the "anticipated net average annual generation" was 250,000 megawatt-hours ("MWh") for two of the Wind Farms and 300,000 MWh for the third wind farm. TXUPM was not only obligated to accept delivery of 100% or 38%, respectively, of the Net Energy, but according to section 4.02 of each contract TXUPM was to pay the Full Price for the first 105% of the "Annual Quantity" and 50% of the Full Price for amounts in excess of that. The "Annual Quantity" was defined as 250,000 MWh for two of the Wind Farms and 105,000 to 115,000 MWh for the third wind farm. There was no dispute at trial that the Wind Farms never delivered the Annual Quantity to TXUPM, so the price never dropped by 50%.

Section 3.01(b) of the contracts required the Wind Farms to deliver a daily plan for the next day by 9:00 a.m., including day ahead generation projections, and inform TXUPM of other circumstances that might affect the Wind Farms' ability to generate electricity, such as notifications if five percent or more of the generating units were unavailable. Section 3.02 of the contracts required the Wind Farms to attend quarterly meetings with TXUPM to discuss, among other things, the production of the Wind Farms and "the outlook for the current compliance period production of RECs." Manu Asthana, TXUPM's vice president, testified that when TXUPM received the generation forecasts from the Wind Farms, it would put that into their day ahead resource plan to ERCOT. Any deviation from the levels forecasted and amended down by ERCOT, "which happens, you know, frequently, because the wind changes all the time, we will actually spend money to have resources on line to absorb that instantaneous realtime variation." Asthana further stated, "as the wind fluctuated, we would actually step in with our own resources sometimes to make up the slack, if you will, at no charge to FPL."

In addition, because electricity cannot be stored, any electricity delivered by the Wind Farms had to be immediately transmitted to TXUPM's ultimate destinations—its customers. Likewise, any failure of the Wind Farms to deliver the electricity promised during the year necessarily had to be replaced during that year so TXUPM could meet its own electricity obligations. When the atmospheric conditions or other circumstances, such as ERCOT curtailments, prevented the Wind Farms from meeting their daily forecasts, TXUPM's real-time balancing resulted in TXUPM's replacing the electricity that the Wind Farms failed to deliver. When the Wind Farms were unable to deliver their projected generation, the evidence is undisputed that TXUPM always generated or acquired sufficient electricity to meet its needs and would make up for any shortfall by obtaining substitute power from its own sources. Based on the evidence, I conclude there was legally sufficient evidence to support the submission of the cover question and the jury's answer effectively that TXUPM's real-time balancing was TXUPM's way of "purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements," as cover was defined in the jury charge.

Cover is often a factual issue a jury must decide. Based on this record, there is legally sufficient evidence to support the trial court's submission of Question 5 regarding cover and the jury's finding that TXUPM covered by "purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements."

See Manon v. Tejas Toyota, Inc., 162 S.W.3d 743, 748 (Tex.App.–Houston [14th Dist.] 2005, no pet.) (cover including good faith in purchasing substitute is a question of fact for the jury); Mueller v. McGill, 870 S.W.2d 673, 676 (Tex.App.–Houston [1st Dist.] 1994, writ denied) (same); Kiser v. Lemco Indus., Inc., 536 S.W.2d 585, 590 (Tex.Civ.App.–Amarillo 1976, no writ) (cover is factual question for fact finder); see also Amer. Carpet Mills, Etc. v. Gunny Corp., 649 F.2d 1056, 1060 (5th Cir.1981) (same under Georgia law); Thorstenson v. Mobridge Iron Works Co., 87 S.D. 358, 208 N.W.2d 715, 717 (1973) (same under South Dakota law).

The proper measure of damages with respect to the undelivered electricity was the difference between TXUPM's cost to generate or purchase the substitute electricity and the contract price. See TEX. BUS. & COM. CODE ANN. § 2.712(b). The only damage models TXUPM offered at trial, however, were based on a market value of the combined undelivered energy and RECs after it calculated the cost of the Wind Farms' breach after the end of the contract year. As to RECs, TXUPM did not put on any evidence that it had been penalized by the PUC for the RECs the Wind Farms failed to deliver or the market price of the undelivered RECs (TXUPM instead relied on the liquidated damages clause). Because TXUPM pleaded and proved an incorrect measure of damages and submitted no evidence as to the proper measure of damages for the undelivered RECs, the trial court was correct in rendering a take-nothing judgment on TXUPM's breach of contract claim. I, therefore, would resolve TXUPM's fourth issue against TXUPM. Resolution of the cover issue makes it unnecessary to address the issue regarding the adequacy of TXUPM's evidence of combined electricity and RECs market price damages.

Notably, TXUPM does not argue that the trial court's take-nothing judgment was improper if the cover issue was properly submitted to the jury.

These arguments were in response to the third issue in the Wind Farms' cross-appeal original briefing arguing that the jury award was based on improper evidence of market-value damages.

III.

DECLARATORY JUDGMENT

TXUPM contends that the trial court erred in declaring TXUPM was required to return the $3.075 million it had accessed from the letters of credit securing the Wind Farms' contractual obligations. TXUPM's principal appellate argument to support this issue is derivative of TXUPM's argument for reversal of the take-nothing judgment based on market price versus cost of cover. Because I resolved TXUPM's damages argument against it, that no longer supports reversal of the declaratory judgment. Although there are a few additional statements in its briefs, TXUPM did not address why the trial court erred in ordering return of the $3.075 million if the trial court's judgment was affirmed regarding TXUPM's fourth issue. See TEX. R. APP. P. 38.1(i). In my view, therefore, no further argument is presented to address on the merits regarding the declaratory judgment. Accordingly, I would deny TXUPM's declaratory judgment argument.

This is TXUPM's third issue in its supplemental brief and its fifth issue in its original briefing. Under issue three in its supplemental brief, TXUPM also argues its entitlement to attorney's fees as the prevailing party pursuant to section 38.001(8) of the civil practice and remedies code. See Tex. Civ. Prac. & Rem. Code Ann. § 38.001(8) (West 2015). Because resolution of the cover issue results in the affirmance of the take-nothing judgment on TXUPM's breach of contract claims, in my opinion it is unnecessary to address attorney's fees.

TXUPM argues the Wind Farms had no live cause of action to support such a declaration. In its one paragraph argument in its original appellate brief on this issue and two paragraph supplemental briefing for this issue, TXUPM did not cite the record or any legal authority.
--------

IV.

CONCLUSION

Based on what I view as the correct standard of review, I conclude the issue of whether TXUPM covered by "purchasing or producing electricity as a substitute for the electricity promised but not delivered under the Agreements" was properly submitted to the jury and the jury's affirmative answer was supported by legally sufficient evidence in light of the charge as submitted. I further conclude that in light of the jury's finding and in the absence of any evidence as to TXUPM's cost to cover the electricity deficiencies or evidence of cost to cover or market price of the RECs or penalty imposed by the PUC, the trial court did not err in rendering judgment that TXUPM take nothing on its breach of contract claims against the Wind Farms.

I would affirm that portion of the trial court's judgment addressing TXUPM's damages. Specifically, I would affirm the judgment that TXUPM take nothing on its breach of contract claims against the Winds Farms and the declaration in the judgment that TXUPM is obligated to return the full amount of the security it accessed from the Wind Farms' letters of credit. Because the majority uses a different standard of review resulting in different conclusions, I dissent.


Summaries of

Txu Portfolio Mgmt. Co. v. FPL Energy, LLC

Court of Appeals of Texas, Dallas.
Aug 18, 2016
529 S.W.3d 472 (Tex. App. 2016)
Case details for

Txu Portfolio Mgmt. Co. v. FPL Energy, LLC

Case Details

Full title:TXU PORTFOLIO MANAGEMENT COMPANY, L.P. n/k/a Luminant Energy Company…

Court:Court of Appeals of Texas, Dallas.

Date published: Aug 18, 2016

Citations

529 S.W.3d 472 (Tex. App. 2016)

Citing Cases

Redwine v. Peckinpaugh

See TEX. R. APP. P. 33.1(a)(1) (preservation can be accomplished by "request, objection, or motion"); T.O.…

JNM Express, LLC v. Lozano

"The starting point generally of a legal or factual sufficiency review is the charge and instructions to the…