From Casetext: Smarter Legal Research

Treece v. Southern Gem Coal Corp.

Appellate Court of Illinois, Fourth District
Oct 29, 1923
245 Ill. App. 113 (Ill. App. Ct. 1923)

Summary

In Treece v. Southern Gem Coal Corp., 245 Ill. App. 113 (1923), the court concluded that the cause of action accrued to the subsequent surface owner when the subsistence occurred.

Summary of this case from Aetna Life Casualty v. Lobianco Son

Opinion

Opinion filed October 29, 1923.

1. LIMITATIONS OF ACTIONS — when begin to run for damage from subsidence of mined land. A cause of action for damage to property from the subsidence of the ground due to not leaving sufficient support in the process of mining thereunder, arises at the time of the subsidence and not at the removal of the subjacent support, and the statute of limitations begins to run from the former date.

2. APPEAL AND ERROR — when erroneous instructions for appellant not ground for reversal. A judgment will be affirmed although instructions for the appellant lay down an erroneous rule of law, where the appellee does not assign cross-errors and does not seek reversal of the judgment.

Appeal by defendants from the Circuit Court of Franklin county; the Hon. JULIUS C. KERN, Judge, presiding. Heard in this court at the March term, 1923. Affirmed. Opinion filed October 29, 1923.

WILLIAMS, LEWIS COFFEY and HART HART, for appellant.

W.F. SPILLER, E.M. SPILLER and J.E. CARR, for appellee.


On July 1, 1908, George A. Brown, being the owner of 40 acres of land in Franklin county, let and demised to Thomas Horn and Jesse Diamond the coal underlying said premises, the lease providing for the recovery of "all coal that could be economically mined" on a royalty basis. This lease was assigned to the West Frankfort Coal Company, appellant herein. Under this lease appellant mined and removed all the coal from under the land here involved.

After the coal underlying the premises had been removed Brown sold and conveyed the surface of the land to Rolla M. Treece and Everett R. Brown. These parties subdivided the premises into lots and blocks and appellee, Rolla M. Treece, became the owner of certain lots. After acquiring these lots appellee erected thereon certain dwelling houses and on one a single story frame store building. After the buildings were erected two subsidences of the surface of the land occurred, resulting in damage to the buildings and also to the surface of the land. This suit was brought by appellee against appellant to recover the damages resulting from the subsidences, charging that they resulted from the failure of appellant to leave sufficient support for the surface of the soil.

Appellant filed its plea of not guilty and the cause was tried before a jury on that plea and the stipulation of the parties that any evidence should be admitted which would be admissible under a proper special plea. The jury found for appellee and assessed his damages at $2,500. After motions for a new trial and in arrest of judgment had been overruled, judgment was rendered on the verdict. There is no dispute as to the facts in this case.

The court instructed the jury in behalf of appellant to the effect that if the coal underlying the premises had been mined and removed prior to the time appellee became the owner of the surface and the subsidences occurred by reason of such prior mining and removal of coal, appellee could not recover. Notwithstanding this instruction and notwithstanding the fact it was admitted the coal had been mined and removed before appellee became the owner of the surface, the trial court overruled appellant's motion for a new trial. There appears in the record, however, over the signature of the trial judge, a statement to the effect that even though the verdict was contrary to the instructions of the court, yet the motion for a new trial was overruled in order that the legal propositions here involved, which appear not to have been settled by the decisions of this State, might be passed upon by a court of review.

Appellant rests its case in this court upon three propositions, the last two of which are practically but one, namely, (1) the cause of action arose at the time of the removal of the subjacent support; (2) the action for injury to real estate by interfering with support is a personal action and (3) the action being personal does not pass with a grant of the land but belongs to the owner of the land at the time the cause of action arises. It appears to us that a disposition of the question as to when the cause of action in this case arose will dispose of all of appellant's propositions so far as this particular case is concerned. Appellee was the owner of the surface at the time the subsidence occurred and if the cause of action then arose there would be no question but that the right of action was in him. The only authorities cited by appellant substantiating its contention that the cause of action arose at the time the surface support, that is the coal, was removed, regardless of when the subsidences occurred, are decisions of the Supreme Court of Pennsylvania. In Noonan v. Pardee, 200 Pa. 474, it was held that "When the coal was removed without leaving sufficient pillars, or without supplying sufficient artificial props, was the time when the subjacent owner failed in an absolute duty he owed to his neighbor above. And from that dates the cause of action. * * * If the failure to furnish sufficient support to the surface was from mining, either by defendant or his predecessors, more than six years before suit, the action is barred by the statute of limitations." In Tischler v. Pennsylvania Coal Co., 218 Pa. 82, the court approved the following instruction. "The court instructed the jury that the cause of action arose, not when the cave or subsidence took place, but when the support of the surface was so weakened that it might fall, and told them that the cause must have occurred within six years of bringing the suit." In Woods v. Pittsburg Coal Co., 230 Pa. 197, the court again approved the doctrine laid down in Noonan v. Pardee, supra, that such cause of action accrues at the time that insufficient supports are left regardless of when the subsidence occurs. If the doctrine laid down by the courts of Pennsylvania were followed in this case then the questions would arise as to whether the cause of action arose within the statutory period for bringing suit and whether or not, if within such period, such right passed to appellee in this case with his grant of the surface of the soil. Appellant, however, has not cited nor have we been able to discover any authorities other than those above mentioned supporting its contention that the cause of action arose when the coal was mined and removed.

On the other hand we find the rule of the English courts and the courts of Alabama and Kansas, and we believe New Jersey, to hold the contrary. Probably the leading case on this question in the English courts is that of Backhouse v. Bonomi, 9 H.L. Cas. 503. In that case, where a lot and the house on it were caused to settle by the excavation of the underlying strata it was expressly held that the cause of action arose when the subsidence occurred and not at the time the support was removed, and in passing upon that question Lord Chancellor Westbury used the following language: "I think it is abundantly clear upon both principle and upon authority that when the enjoyment of a house is interfered with by the actual occurrence of the mischief the cause of action then arises, and that the action may then be maintained." To the same effect is the English case of Darley Main Colliery Co. v. Mitchell, L.R. 11 App. cases 127.

In a case involving the question as to whether the statute of limitations begins to run in a case of this nature at the time the subsidence of the surface occurs or at the time the subjacent supports are removed the Supreme Court of Alabama in West Pratt Coal Co. v. Dorman, 161 Ala. 389, 49 So. 849, 23 L.R.A. (N.S.) 805, quoted with approval from the English case of Backhouse v. Bonomi, supra, and held that such cause of action accrued and the statute of limitations began to run when the subsidence of the upper soil occurred and not when the subjacent support was removed. A case note to the above in the report named contains the following statement which we consider well founded: "So far as the cases are concerned which deal with applicability of the statute of limitations to actions for injury to the surface caused by mining operations or other excavations, the great weight of authority is to the effect that a cause of action does not arise until some actual mischief has been done, from which time the statute of limitations begins to run, regardless of when the mining or other excavating was done." In Audo v. Western Coal Mining Co., 99 Kan. 454, it was held that a cause of action for damages caused by the subsidence of the land into excavations made by a mining company did not accrue until the land subsided. The facts involved in that case were very similar to those in the instant case. A coal company mined the coal from part of the land owned by it and then conveyed the surface, reserving the underlying coal. The purchaser knew that the coal had been mined from that part of the land, but had no personal knowledge in what manner the mining had been done. A portion of the surface over that part of the land from which the coal had been mined previous to the making of the deed subsided after the land had been conveyed. On these facts it was held that such cause of action did not accrue until the subsidence of the land took place, and therefore the statute of limitations did not begin to run until that time. This rule was adopted in effect in the case of Walsh v. Kansas Fuel Co., 91 Kan. 310. We are also of the opinion that the case of Church of the Holy Communion v. Paterson Extension R. Co., 66 N.J.L. 218, 49 A. 1030, 55 L.R.A. 81, supports this doctrine. In that case the court of appeals of New Jersey held that the right of action for removal of lateral support arose when the damage occurred, and not when the lateral support was removed. If appellant's contention that the cause of action arose when the subjacent support was removed and before any actual damage had been sustained by the surface, a jury would therefore be called upon to decide the speculative question as to whether any damage was likely to occur and as said Mr. Justice Willes in Backhouse v. Bonomi, supra, "it might well be that in many cases that the jury would, upon the evidence of mineral surveyors and engineers, find that no damage was likely to occur, when the most serious injury afterwards might in fact occur, and in others find and give large sums of money for apprehended damage which in point of fact never might arise. This is certainly not a state of law to be desired."

We conclude that appellee's contention that the cause of action did not arise until the subsidence occurred is supported by the greater weight of authorities and is based upon more logical reasons and sounder principles of justice than the doctrine that it arose when the coal was mined and removed. As the subsidence of the surface of the ground occurred after appellee became the owner of the same the right of action accrued directly to him and it is therefore unnecessary for us to pass upon the question whether the action is personal and will or will not pass with the grant of the land. The court erred in the rule of law laid down in the instructions to the jury on behalf of appellant, above referred to, but appellee has assigned no cross-errors and does not seek a reversal of the case. The judgment of the trial court was in accordance with the law and the facts and will therefore be affirmed.

Affirmed.


Summaries of

Treece v. Southern Gem Coal Corp.

Appellate Court of Illinois, Fourth District
Oct 29, 1923
245 Ill. App. 113 (Ill. App. Ct. 1923)

In Treece v. Southern Gem Coal Corp., 245 Ill. App. 113 (1923), the court concluded that the cause of action accrued to the subsequent surface owner when the subsistence occurred.

Summary of this case from Aetna Life Casualty v. Lobianco Son
Case details for

Treece v. Southern Gem Coal Corp.

Case Details

Full title:Rolla M. Treece, Appellee, v. Southern Gem Coal Corporation et al.…

Court:Appellate Court of Illinois, Fourth District

Date published: Oct 29, 1923

Citations

245 Ill. App. 113 (Ill. App. Ct. 1923)

Citing Cases

Gillespie Cmty. Unit Sch. Dist. No. 7, Macoupin Cnty. v. Union Pac. R.R. Co.

See Wilms v. Jess, 94 Ill. 464, 467 (1880) ; Restatement (Second) of Torts § 820(1), at 78 (1979) ; 9 Richard…

Gillespie Cmty. Unit Sch. Dist. No. 7, Macoupin Cnty. v. Union Pac. R.R.

See Wilms v. Jess, 94 Ill. 464, 467 (1880); Restatement (Second) of Torts § 820(1), at 78 (1979); 9 Richard…