Teton Exploration v. Bokum Resources

United States Court of Appeals, Tenth Circuit
Jun 18, 1987
818 F.2d 1521 (10th Cir. 1987)

Summary

reviewing district court's original jurisdiction action under § 1291

Summary of this case from In re Kaiser Steel Corp.

Opinion

Nos. 85-1046, 85-1324.

May 18, 1987. Rehearing Denied June 18, 1987.

Robert H. Clark (Charles A. Pharris and Paula Z. Hanson with him on the briefs) of Keleher McLeod, Albuquerque, N.M., for plaintiff-appellant Teton Exploration Drilling, Inc.

Stephen P. Curtis of Melton Puccini, Albuquerque, N.M., for defendant-appellee Bokum Resources Corp.

Sarah M. Singleton (Michael W. Brennan with her on the brief) of Montgomery Andrews, Santa Fe, N.M., for defendant-appellee Long Island Lighting Co.

Appeal from the United States District Court for the District of New Mexico.

Before LOGAN, McWILLIAMS and BALDOCK, Circuit Judges.



Teton Exploration Drilling, Inc. sued Bokum Resources Corporation in a New Mexico state court to recover for services rendered under a contract to drill certain ventilation and egress shafts on Bokum's uranium mining property in New Mexico. Bokum removed the case to the Bankruptcy Court for the District of New Mexico after Bokum's creditors filed an involuntary bankruptcy petition against it. There Bokum counterclaimed against Teton, asserting breach of contract and negligence. The bankruptcy court permitted Long Island Lighting Company ("LILCO") to participate in the litigation as an interested party defendant because it had a uranium contract with Bokum, which was using funds advanced by LILCO to bring its mine into production.

The bankruptcy court found in favor of Bokum on both Teton's claim and Bokum's counterclaim, and entered a preliminary memorandum opinion on December 10, 1984, assessing Bokum's damages at $1,862,511.55. On December 13, the bankruptcy judge certified the opinion to the district court for review pursuant to the District of New Mexico's local Rule 31(g), which provides for review of "non-core" bankruptcy proceedings. On December 24, the parties filed a stipulation in the bankruptcy court that they believed the matter to be a core proceeding as defined in 28 U.S.C. § 157(b)(2), with respect to which the bankruptcy court could make a final judgment. R. II, 433. The stipulation stated that "in any event, the parties agree, pursuant to 28 U.S.C. Section 157(c)(2), that the Bankruptcy Court may enter Findings of Fact and Conclusions of Law and appropriate Orders and Judgments." Id. The stipulation contemplated a direct appeal from the bankruptcy court to this court under 28 U.S.C. § 1293. On December 28, the district court entered an order confirming the bankruptcy court's December 10 opinion in its entirety.

The bankruptcy judge had filed a more detailed supplemental memorandum opinion on December 26, 1984, to the same effect as his December 10, 1984, opinion and entered a proposed judgment on December 31, both of which he also certified to the district court for review pursuant to Rule 31(g). On January 7, 1985, Teton filed notices of appeal to both the district court and this court, seeking review of the December 28 confirmation order as well as the bankruptcy court's supplemental opinion and judgment. On February 8, the district court entered orders confirming the bankruptcy court's supplemental opinion and judgment in their entirety. Teton filed a notice of appeal from these orders on February 26, 1985. Teton's first appeal to this court was docketed as No. 85-1046; the second appeal was docketed as No. 85-1324.

I

We directed the parties to brief the issue whether this court has jurisdiction over these two appeals. Both appeals raise identical issues. Because we conclude that this court has jurisdiction to decide Teton's second appeal, No. 85-1324, we need not consider whether Teton's first appeal, No. 85-1046, is properly before us.

From the certification and confirmation procedure utilized below, it appears that both the bankruptcy court and the district court intended to treat this case as a "non-core" proceeding under 28 U.S.C. § 157(c)(1). If we were to find such treatment appropriate, then the district court's February 8 order confirming the bankruptcy court's December 31 judgment constituted a final decision of the district court, appealable to this court under 28 U.S.C. § 1291. See In re Salem Mortgage Co., 783 F.2d 626, 632 n. 15 (6th Cir. 1986); In re Amatex Corp., 755 F.2d 1034, 1038-39 n. 4 (3d Cir. 1985). Teton now argues, however, that the bankruptcy court and the district court should have treated this case as a "core" proceeding, either because it falls within one of the categories set forth in § 157(b)(2), or because the parties stipulated to treatment of the case as a core proceeding. The proper procedure, Teton contends, would have been for the bankruptcy court to enter a final order subject only to appellate review in the district court under § 158(a), not the entirely de novo review prescribed under § 157(c)(1) for "non-core" proceedings. Had the district court acted in its appellate capacity, we would then have jurisdiction to review its decision under § 158(d).

Subsection (c)(1) provides;

"A bankruptcy judge may hear a proceeding that is not a core proceeding but that is otherwise related to a case under title 11. In such proceeding, the bankruptcy judge shall submit proposed findings of fact and conclusions of law to the district court, and any final order or judgment shall be entered by the district judge after considering the bankruptcy judge's proposed findings and conclusions and after reviewing de novo those matters to which any party has timely and specifically objected."

One panel of the Ninth Circuit has held that 28 U.S.C. § 158(d) is "the exclusive basis of jurisdiction in the appellate courts in bankruptcy matters." In re Teleport Oil Co., 759 F.2d 1376, 1378 (9th Cir. 1985); accord In re Barrier, 776 F.2d 1298, 1299 (5th Cir. 1985) (following Teleport). Later Ninth Circuit cases cast doubt on the Teleport decision. See In re Benny, 791 F.2d 712, 717 n. 4 (9th Cir. 1986). Section 158(d) contains no provision for appellate review of final district court orders entered in non-core proceedings under § 157(c)(1). If Teleport were correct, then such orders would be unreviewable. Because we perceive no indication that Congress intended § 158(d) to act as a limitation on the general jurisdiction of appellate courts under § 1291, we decline to follow Teleport. Accord In re Salem Mortgage Co., 783, F.2d 626, 632 n. 15. (6th Cir. 1986).

Under § 157(b)(3), the determination whether a proceeding is core or non-core is to be made by the bankruptcy court, either sua sponte or on the motion of a party. If the bankruptcy court determines that a case is a core proceeding, it is then authorized, under § 157(b)(1), to enter a dispositive order or judgment. But even if the bankruptcy court erred in treating this as a non-core proceeding, the district court did not lack jurisdiction to enter the final order appealed from. Section 157(b)(1) provides:

"Bankruptcy judges may hear and determine all cases under title 11 and all core proceedings arising under title 11, or arising in a case under title 11, referred under subsection (a) of this section, and may enter appropriate orders and judgments, subject to review under section 158 of this title."

(Emphasis added). We do not believe § 157 required the bankruptcy court to enter a final order rather than submit proposed findings and conclusions to the district court. Whether the proceedings were core or non-core, we have jurisdiction to review No. 85-1324 under 28 U.S.C. § 1291.

Our conclusion is not affected by the parties' December 24 stipulation that the matter be treated as a core proceeding. Although the parties to a non-core proceeding may consent to final disposition by a bankruptcy judge under § 157(c)(2), we find no reason to conclude that such consent is binding on either the bankruptcy judge or the district court. None of the parties filed any objections to the certification and confirmation procedure within the time limits specified by local rule 31(g)(2), governing review of non-core proceedings. We have before us a determination by the bankruptcy court, with which the district court agreed fully. We perceive no reason of logic or public policy that would require a remand to the district court with instructions to subject the bankruptcy court's findings to an appellate type of review rather than the de novo review the district court apparently utilized. We believe the efficient utilization of judicial resources requires that the appeal be treated as ripe for determination on its merits.

II

Bokum, as owner of a uranium mine in New Mexico, contracted with Teton to drill five large-diameter shafts approximately 2000 feet deep to service that mine and provide ventilation and an emergency escape route. The shafts were to be lined with steel casings adequate to withstand the hydrostatic pressure exerted by underground water in the formations being drilled. Bokum provided Teton with lithological reports indicating the various levels at which water would be encountered.

Drilling the first hole took substantially longer than the parties had anticipated, but was eventually completed in November 1979. Teton then began lowering the steel casing into the waterfilled hole, one forty-foot section at a time. On November 24, a submerged section of the casing collapsed and the casing string dropped ninety to one hundred feet to the bottom of the hole. Teton repaired the collapsed section and completed installation of the casing, but was never able to prevent water from flooding the shaft, apparently through a rupture in the bottom of the casing.

The bankruptcy court found that the November 24 collapse was "due to a combination of inadequate design and improper fabrication [of the casing], including inadequate welding," R. II, 412, for which Teton was ultimately responsible. The court found that even if the hole could be cleared of water, the casing was not strong enough to insure against collapse or rupture due to hydrostatic pressure below 1000 feet. The court concluded that "abandonment of the hole appears to be the only safe and reasonable conclusion with respect to the utility and value of this casing." R. II, 413.

The court found that Bokum had effectively abandoned the mine when it encountered financial troubles and uranium mining became unprofitable. It therefore refused to give Bokum the benefit of the bargain. Rather the court in effect allowed rescission, and ordered that Bokum should get back all of the monies that it had paid Teton, less the amounts paid for use of Teton's drilling rig and installation of three "cellers" for use with other shafts. R. II, 427. The court rejected Teton's assertions of substantial performance and quantum merit. It found that the shaft was "of no practical benefit" to Bokum, R. II, 422, and that Teton's performance was not excused by Bokum's failure to pay invoices after the November 24 collapse.

Teton contends on appeal that (1) the contract placed the risk on Bokum for all losses of the shaft or casing caused by something other than the gross negligence of Teton; (2) the damages awarded must be reduced even if Bokum is entitled to some recovery; and (3) Bokum's failure to pay invoices breached the contract, excusing further performance by Teton.

The chief focal point of the dispute between the parties is the meaning of Article VIII(D) of the contract. Several provisions of the contract, including Article VIII(A), required Teton to perform services and work "in a good and workmanlike manner." R. I, 16. Article VIII(A) also required Teton to exercise "due diligence and care." Id. But subparagraph D of Article VIII provided that "[a]ll liability for loss of holes, casing, downhole tools, drill pipe, fishing costs, etc., except if caused by the gross negligence of Teton, shall be the responsibility of" Bokum. Id.

Article VIII, entitled "Obligations of Teton," provides in full:

"Teton will provide qualified personnel as may be necessary to drill the shafts, set the casing, complete expeditiously all the work and operations contemplated hereunder in accordance with this agreement. In furtherance of the foregoing but not by way of limitation or exclusion, Teton shall:

A. Perform the services and work required hereunder in a good and workmanlike manner with due diligence and care;

B. Be solely responsible for the supervision, control and performance of all work and services required of Teton hereunder:

C. Keep and furnish to the Owner sufficiently accurate records of all work performed by Teton on a daily report form;

D. Teton will make no warranties as to the stability of the formation to be drilled and, therefore, is not responsible for any damage, loss or delay resulting from sluffing or caving of formations. In addition, there is no guarantee as to the actual cost or time required for the completion of the contract. All liability for loss of holes, casing, downhole tools, drill pipe, fishing costs, etc., except if caused by the gross negligence of Teton, shall be the responsibility of Owner and shall not be included in the target for the purpose of bonus calculations."

R. I, 16.

Article II provides, in part: "On commencement of the work, Teton shall diligently continue operations hereunder in a good and workmanlike manner consistent with drilling industry standards until Teton has completed such operations and shafts are accepted by Owner." R. I, 13.
Article IX, entitled "Inspection and Acceptance," provides:

"Within twelve (12) hours after completion of each shaft, Owner shall visually inspect the same, and if Owner finds the work to be completed in accordance with this agreement and in a good and workmanlike manner, shall issue to Teton a written statement accepting the work with respect to each shaft.

Any remedial work required prior to acceptance of the hole will be done at the rates provided herein and charged against the target estimate."

R. I, 17.

Teton asserts that this subparagraph "clearly and unambiguously places the risk on Bokum for all losses of the shaft or of the casing which are caused by something other than the gross negligence of Teton." Appellant's Brief at 24 (emphasis in original). Bokum and LILCO, on the other hand, assert that the subparagraph deals only with unforeseen conditions encountered below the ground surface; they argue that, if given Teton's interpretation, Article VIII(D) would in effect abrogate all the other provisions in the contract that require Teton to proceed in a good and workmanlike manner.

The bankruptcy court's findings, confirmed by the district court, were to the effect that subparagraph D was ambiguous. The court allowed parol evidence on the provision's meaning, and, after considering such evidence, concluded that Article VIII(D) only referred to "losses incurred as a result of unforeseen conditions existing beneath the surface," R. II, 408, and did not excuse Teton from ordinary negligence in failing to design and install casing into the hole that would keep out the water. The determination whether a contract provisions is ambiguous is a matter of law. Devine v. Ladd Petroleum Corp., 805 F.2d 348, 349 (10th Cir. 1986); Kelliher v. Herman, 701 P.2d 1157, 1159 (Wyo. 1985). After examining the contested clause and reading the contract as a whole, we agree with the district court that the clause at issue is ambiguous. Once a provision is found to be ambiguous, the resolution of its proper meaning is a question of fact, subject to review on a clearly erroneous standard. City of Farmington v. Amoco Gas Co., 777 F.2d 554, 560 (10th Cir. 1985). We hold that the district court's interpretation of Article VIII(D) is not clearly erroneous.

Teton argues that the damages awarded must be reduced even if Bokum is entitled to recovery. It asserts entitlement to a $160,000 setoff because Bokum abandoned the drilling of the other four shafts and Article X of the contract penalized Bokum $40,000 for each shaft not drilled. The bankruptcy court found, however, that the parties, by mutual agreement, had cancelled the remaining portion of the contract, excusing the operation of the penalty clause. Teton also argues that it should not be required to return some $91,000 that it was paid for providing mud pits, water and cement, services Bokum had initially agreed to provide under Article IV of the contract. Bokum's response, apparently accepted by the court, was that the contract had been modified at the outset to require Teton to provide these services. Finally, Teton argues that the damages must be reduced because the shaft is still valuable to Bokum, and could be made usable by expenditures of $6000 to $7000. The district court rejected this argument, relying on evidence that the shaft could not feasibly be made safe.

Teton's arguments about the amount of damages due Bokum allege errors in the court's findings of fact, which we will set aside only if they are clearly erroneous. City of Farmington, 777 F.2d at 560. Teton's argument that Bokum's failure to pay invoices breached the contract and excused Teton from completing performance also alleges errors of fact. The bankruptcy court found that

"[t]he material breach by Teton which became evident on November 24, 1979 excused [Bokum] from further payments until that performance by Teton was rectified . . . . [Bokum's] refusal to pay from and after November 24, 1979 was justified as a result of the abundantly apparent defective workmanship it had been provided through and by Teton. As a result of Teton's material breach of the Drilling Contract, it cannot claim a subsequent breach by [Bokum] in refusing to pay."

R. II, 423.

We have examined the record carefully and conclude that the bankruptcy court's findings of fact, confirmed by the district court, are supported by the record. We cannot find clearly erroneous the determinations that Article VIII(D) of the contract did not excuse Teton's failure to perform in a "good and workmanlike manner;" that the parties mutually agreed to abandon the contract with respect to completing the final four holes and excused the $40,000 per hole penalty provision; that the $91,000 was a proper expenditure to be returned to Bokum as a part of making it whole; that the shaft was not usable in the condition Teton left it after many efforts to repair; and that Teton had materially breached the contract before Bokum suspended payment on the invoices.

AFFIRMED.


I cannot agree that this case is reviewable under 28 U.S.C. § 1291 as a final order of the district court. Under the circumstances, 28 U.S.C. § 158(d) relating to bankruptcy appeals is the correct statute, not § 1291. In re Morse Electric Co., 805 F.2d 262, 263 (7th Cir. 1986). Under § 158, we would lack jurisdiction.

The certification and confirmation process used by the bankruptcy and district court was not appropriate in this case. The bankruptcy court should have treated the case as a "core proceeding" under 28 U.S.C. § 157(c) because it clearly qualifies as a core proceeding under § 157(b)(2). The apparent determination that this was a non-core proceeding is appealable. 1 L. King, Collier on Bankruptcy ¶ 3.01[2][c] (15th ed. 1987). Teton filed its complaint for debt and foreclosure of liens against Bokum in state court. The case was removed to bankruptcy court after Bokum's creditors filed an involuntary petition against Bokum. Bokum counterclaimed for breach of contract and negligence. Thus, Teton claimed against the Bokum estate in bankruptcy while the Bokum estate counterclaimed against Teton. Core proceedings include "allowance or disallowance of claims against the estate," § 157(b)(2)(B), "counterclaims by the estate against persons filing claims against the estate," § 157(b)(2)(C), "determinations of the validity, extent, or priority of liens," § 157(b)(2)(K) and finally "other proceedings affecting . . . the adjustment of the debtor-creditor . . . relationship," § 157(b)(2)(O). Merely because the claim and counterclaim require reference to state law would not turn this straightforward, though factually involved, bankruptcy matter into a non-core proceeding. See 28 U.S.C. § 157(b)(3) ("A determination that a proceeding is not a core proceeding shall not be made solely on the basis that its resolution may be affected by State law.").

A final judgment of the bankruptcy court may be appealed as of right to the district court; an interlocutory order may be appealed to the district court with leave of court. 28 U.S.C. § 158(a). The 1984 amendments to Bankruptcy reform Act of 1978 replead 28 U.S.C. § 1293(b) which granted the court of appeals jurisdiction to review final orders of bankruptcy courts with the consent of the parties. In re Carter, 759 F.2d 763, 766 (9th Cir. 1985); In re General Coffee Corp., 758 F.2d 1406, 1409 (11th Cir. 1985); In re Exclusive Industries Corp., 751 F.2d 806, 808 (5th Cir. 1985); see also In re Jones, 804 F.2d 1133, 1135 n. 5 (10th Cir. 1986) (assuming without deciding the § 1293(b) was repealed by implication).

Bankruptcy Amendments and Federal Judgeship Act of 1984, Pub.L. No. 98-353, §§ 113, 122(c), 98 Stat. 343, 346.

Bankruptcy Reform Act of 1978, Pub.L. 95-598, §§ 236, 402(b), 405(c), 92 Stat. 2667, 2682, 2685.

Section 157(b)(3) requires that a bankruptcy judge determine whether a proceeding is a core proceeding or is "otherwise related" (a non-core proceeding) either on motion of a party or sua sponte. The distinction between a core and a non-core proceeding is important because it may affect the bankruptcy judge's power to enter final orders. A bankruptcy judge may enter appropriate orders and judgments in core proceedings, 28 U.S.C. § 157(b)(1), however, in non-core proceedings it is the district court which enters final orders after considering proposed findings and conclusions submitted by the bankruptcy judge, 28 U.S.C. § 157(c)(1). If all parties consent and the district court order of reference so provides, a bankruptcy judge may enter a final order even in non-core matters.

No express determination was made concerning whether this case is a core or non-core proceeding. The district of New Mexico local rules presumed that a proceeding was core unless there was a specific determination to the contrary. At this stage, no party contends that the subject matter makes this a non-core proceeding. The memorandum opinion, supplemental memorandum opinion and judgment entered by the bankruptcy judge are not designated as recommended or proposed. Rather it is in subsequent pleadings that the bankruptcy judge indicated that review by a district judge was requested. In any event, appeal of this matter lies first with the district court because a core proceeding is involved.

In another proceeding involving this bankruptcy, the district court remanded the cases to the bankruptcy court for a determination of whether a core or non-core proceeding was involved. See In re Bokum Resources Corp., 64 B.R. 924 (D.N.M. 1986).

D.N.M.R. 31(f) (Nov. 19, 1984) provided:

Determination of Non-Core Proceedings. A particular proceeding shall be "non-core" under 28 U.S.C. § 157(b) only if a Bankruptcy Judge so determines sua sponte or rules on a motion of a party filed under 28 U.S.C. § 157(b)(3) within the time periods fixed above.

D.N.M.R. 31(g)(1) (Nov. 19, 1984) provided:

Unless the parties have consented to entry of the judgment by a Bankruptcy Judge, recommended findings of fact, conclusions of law and a proposed judgment and order prepared by a Bankruptcy Judge in a "non-core" proceeding pursuant to 28 U.S.C. § 157(c)(1) shall be mailed to all parties in interest by the Bankruptcy Clerk and concurrently transmitted to the District Court Clerk for assignment to a District Judge.

The rule envisions findings, conclusions, orders and judgments of a proposed nature.

The majority opinion contends that whether a bankruptcy judge decides to enter a final order in a core proceeding is discretionary with the bankruptcy judge under 28 U.S.C. § 157(b)(1). That section provides:

Bankruptcy judges may hear and determine all cases under title 11 and all core proceeding under title 11 or arising in a case under title 11 referred in subsection (a) of this section and may enter appropriate orders and judgments, subject to review under section 158 of this title.

(emphasis of majority). If the majority approach were correct, the bankruptcy judge could also decide whether even to hear a core proceedings. Surely this is not correct. That decision rests with the district court which is empowered to refer cases to the bankruptcy judges for the district. 28 U.S.C. § 157(a). The district of New Mexico made that referral by local rule. D.N.M.R. 31(b) (Nov. 19, 1984). Once bankruptcy cases are referred to bankruptcy judges, those cases must be handled in accordance with the Bankruptcy Code, Bankruptcy Rules and local rules. Merely because the statute uses the word "may" does not mean that the bankruptcy judge is vested with discretion to use non-core procedure when resolving a core proceeding.

Thus, I would hold that the bankruptcy judge was required to enter a final order because this was a core proceeding rather than submit a memorandum opinion supplemental memorandum opinion and judgment to the district court for review. The distinction between core and non-core proceedings is relevant because the standard for district court review can differ. For example, when the bankruptcy judge submits recommended findings and conclusions or a proposed final order in a non-core proceeding, the district court may review de novo those matters objected to pursuant to 28 U.S.C. § 157(c)(1). On the other hand, in a core proceeding, the district court will review findings under the deferential clearly erroneous standard. In re Reid, 757 F.2d 230, 233-34 n. 5. (10th Cir. 1985).

The appealable final order in this case is the judgment entered by the bankruptcy court December 31, 1984, which references the bankruptcy court's findings and conclusions. On January 7, 1985, Teton filed a timely notice of appeal of that judgment, record vol. II at 445, to the district court. At that point, pursuant to 28 U.S.C. § 158(a), the district court was invested with jurisdiction to consider Teton's appeal. Bokum cross-appealed to the district court, but later withdrew its cross appeal. In my view, Teton's second notice of appeal to the court of appeals on which the majority bases jurisdiction is of no effect.

Even if this case could somehow be considered a non-core proceeding, it should still be dismissed by the court of appeals for lack of jurisdiction. Prior to the bankruptcy court's December 31, 1984, judgment, the parties, in accordance with the Bankruptcy Code and the local rule, stipulated not only that this was a core proceedings, but also that in any event the bankruptcy court could enter findings and conclusions, as well as orders and judgments. The majority suggests that this is not binding on either the bankruptcy judge or the district court. I cannot agree.

28 U.S.C. § 157(c)(2) specifically provides that "the district court, with consent of all parties to the proceeding, may refer a proceeding related to a case under and title 11 to a bankruptcy judge to hear and determine and to enter appropriate orders and judgments, subjects to review under section 158 of this title." Thus, the district court may refer non-core proceedings to bankruptcy judges for entry of orders and judgments when the parties have consented. The district court had referred all bankruptcy cases to bankruptcy judges and contemplated that the parties could avail themselves of the above consent jurisdiction. See D.N.M.R. 31(b) 31(g)(1) (Nov. 19, 1984). Indeed, D.N.M. R. 31(g) (Nov. 19, 1984) provided for de novo district court review of non-core proceedings heard by a bankruptcy judge "unless the parties have consented to entry of judgment by a Bankruptcy Judge." Where the parties had consented, the local rules provided, in harmony with 28 U.S.C. § 157(c)(2), that the appeal should be taken to the district court. D.N.M.R. 3(i) (Nov. 19, 1984) (" Appeals. (1) An appeal from a final or interlocutory order of a Bankruptcy Judge in a core or non-core proceeding under 28 U.S.C. § 157(c)(2) shall be taken to the District Court.") It is axiomatic that the district court and the bankruptcy court are obligated to follow the district court's own rules; and in this case those rules are binding. The district court has yet to exercise its proper appellate function; local rules contemplate designation of a record for the district court's review and filing of briefs by the parties. D.N.M.R. 31(e) (f) (Nov. 19, 1984).

The procedure used in this case does not operate when the parties have consented to entry of judgment by the bankruptcy court because the district court has referred the non-core proceeding to the bankruptcy judge for entry of orders and judgments. D.N.M. R. 31(g) (Nov. 19, 1984). Although the district court could modify the reference and withdraw the proceeding, 28 U.S.C. § 157(d) D.N.M.R. 31(e) (Nov. 19, 1984), such was not done here.

The majority indicates that one of the reasons the district court's referral pursuant to 28 U.S.C. § 157(c)(2) may be disregarded is that the parties failed to file any objections to the certification and confirmation procedure within the ten days provided by D.N.M. R. 31(g)(2) (Nov. 19, 1984). If the problem before us were not jurisdictional, that argument might have some force. However, this court's bankruptcy jurisdiction is dependent upon the proper exercise of jurisdiction by the court below. In re Abdallah, 778 F.2d 75, 77 (1st Cir. 1985), cert. denied, ___ U.S. ___, 106 S.Ct. 1973, 90 L.Ed.2d 657 (1986). Moreover, as previously noted the certification procedure used by the bankruptcy judge to obtain district court review of his findings, conclusions and judgment does not appear to be consistent with D.N.M.R. 31(g) which governed review of non-core proceedings by a district judge. Although efficiency concerns may suggests that this appeal be treated as ready for decision, the jurisdictional problem outweighs such considerations. Congress has determined that the first appeal of core proceedings, or of non-core proceedings where the bankruptcy, judge has exercised consent jurisdiction, lies in the district court. 28 U.S.C. § 158(a). We are powerless to change that.


Summaries of

Teton Exploration v. Bokum Resources

United States Court of Appeals, Tenth Circuit
Jun 18, 1987
818 F.2d 1521 (10th Cir. 1987)

reviewing district court's original jurisdiction action under § 1291

Summary of this case from In re Kaiser Steel Corp.

In Teton Exploration Drilling v. Bokum Resources Corp., 818 F.2d 1521, 1526 (10th Cir.), we held that "[t]he determination whether a contract provision is ambiguous is a matter of law.... Once a provision is found to be ambiguous, the resolution of its proper meaning is a question of fact, subject to review on a clearly erroneous standard."

Summary of this case from Nunn v. Chemical Waste Management, Inc.
Case details for

Teton Exploration v. Bokum Resources

Case Details

Full title:TETON EXPLORATION DRILLING, INC., PLAINTIFF-APPELLANT, v. BOKUM RESOURCES…

Court:United States Court of Appeals, Tenth Circuit

Date published: Jun 18, 1987

Citations

818 F.2d 1521 (10th Cir. 1987)

Citing Cases

In re Kaiser Steel Corp.

The district court characterized its order as deciding an appeal from the bankruptcy court's ruling striking…

Mid-West Conveyor Co. v. Jervis B. Webb Co.

See MGA, Inc. v. LaSalle Machine Tool, Inc., 384 N.W.2d 159, 161 (Mich.Ct.App. 1986). Because the…