From Casetext: Smarter Legal Research

Stonewall Contracting Corp. v. Long Island R.R.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Aug 12, 2020
186 A.D.3d 640 (N.Y. App. Div. 2020)

Opinion

2017–05682 Index No. 503994/12

08-12-2020

STONEWALL CONTRACTING CORP., Respondent, v. LONG ISLAND RAIL ROAD COMPANY, Appellant.

Hoguet Newman Regal & Kenney, LLP, New York, N.Y. (Ira J. Lipton, Helene R. Hechtkopf, and Miriam J. Manber of counsel), for appellant. Rich, Intelisano & Katz, LLP, New York, N.Y. (Daniel E. Katz and Steven Cramer of counsel), for respondent.


Hoguet Newman Regal & Kenney, LLP, New York, N.Y. (Ira J. Lipton, Helene R. Hechtkopf, and Miriam J. Manber of counsel), for appellant.

Rich, Intelisano & Katz, LLP, New York, N.Y. (Daniel E. Katz and Steven Cramer of counsel), for respondent.

RUTH C. BALKIN, J.P., JEFFREY A. COHEN, BETSY BARROS, ANGELA G. IANNACCI, JJ.

DECISION & ORDER In an action, inter alia, to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Kings County (Leon Ruchelsman, J.), dated May 4, 2017. The order, insofar as appealed from, granted those branches of the plaintiff's motion which were for summary judgment dismissing the defendant's fourth affirmative defense and third and fourth counterclaims, and denied the defendant's cross motion for summary judgment dismissing the complaint.

ORDERED that the order is modified, on the law, (1) by deleting the provision thereof granting that branch of the plaintiff's motion which was for summary judgment dismissing the defendant's fourth affirmative defense, and substituting therefor a provision denying that branch of the motion, and (2) by deleting the provision thereof denying the defendant's cross motion for summary judgment dismissing the complaint, and substituting therefor a provision granting the cross motion; as so modified, the order is affirmed insofar as appealed from, without costs or disbursements.

In December 2005, the defendant, Long Island Rail Road Company (hereinafter the LIRR), awarded the plaintiff a contract in the amount of $25,784,209, whereby the plaintiff would serve as the general contractor on a construction project located at the Atlantic Terminal in Brooklyn. The contract provided, among other things, that "[a]ll legal action against the [LIRR] arising out of this Contract shall be initiated within 90 days following Construction Completion," and that "[a]ll rights and remedies relating to all claims, disputes, or legal action filed by the Contractor more than 90 days thereafter, shall be waived and any such item shall be deemed settled." "Construction Completion" is referred to in the contract as a milestone that must be achieved within 616 calendar days from the "Notice of Award." However, during the course of the project, the parties entered into a total of 26 contract modifications, which extended the completion date under the contract to May 31, 2011, and increased the amount due to the plaintiff under the contract "to a revised maximum obligation of $29,646,357.61."

On or about June 7, 2011, the plaintiff submitted to the LIRR its final application for payment for the period ending May 31, 2011, which the LIRR approved on or about July 26, 2011. It is undisputed that, by then, the plaintiff had demobilized from the work site and that "the work was already 100% complete." Thereafter, on May 25, 2012, the plaintiff submitted a "Request for Equitable Adjustment" (hereinafter REA) to the LIRR, seeking an additional payment in the amount of $4,329,619.36, representing the costs that it allegedly incurred due to delays "during the 1095 calendar days" between May 31, 2008, and May 31, 2011. By letter dated July 3, 2012, the LIRR rejected the REA.

In November 2012, approximately one and one-half years after the project was complete, the plaintiff commenced this action against the LIRR, inter alia, to recover damages it allegedly incurred due to construction delays. The LIRR subsequently interposed an answer with affirmative defenses and counterclaims. As relevant here, the fourth affirmative defense alleged that the action was time-barred. The third counterclaim sought to recover liquidated damages, and the fourth counterclaim sought to recover damages for unjust enrichment. The plaintiff moved, inter alia, for summary judgment dismissing the LIRR's fourth affirmative defense and the third and fourth counterclaims, and the LIRR cross-moved for summary judgment dismissing the complaint. The Supreme Court, among other things, granted those branches of the plaintiff's motion and denied the LIRR's cross motion. The LIRR appeals.

The " ‘fundamental, neutral precept of contract interpretation ... [is] that agreements are construed in accord with the parties' intent,’ and ‘[t]he best evidence of what parties to a written agreement intend is what they say in their writing’ " ( 2138747 Ontario, Inc. v. Samsung C & T Corp., 31 N.Y.3d 372, 377, 78 N.Y.S.3d 703, 103 N.E.3d 774, quoting Greenfield v. Philles Records, 98 N.Y.2d 562, 569, 750 N.Y.S.2d 565, 780 N.E.2d 166 ; see Deutsche Bank Natl. Trust Co. v. Barclays Bank PLC, 34 N.Y.3d 327, 340, 117 N.Y.S.3d 137, 140 N.E.3d 511 ). " ‘[W]here the terms of a contract are clear and unambiguous, the intent of the parties must be found within the four corners of the contract, giving a practical interpretation to the language employed and reading the contract as a whole’ " ( Tomhannock, LLC v. Roustabout Resources, LLC, 33 N.Y.3d 1080, 1082, 104 N.Y.S.3d 596, 128 N.E.3d 674, quoting Ellington v. EMI Music, Inc., 24 N.Y.3d 239, 244, 997 N.Y.S.2d 339, 21 N.E.3d 1000 ).

Further, " ‘[a]n agreement which modifies the Statute of Limitations by specifying a shorter, but reasonable, period within which to commence an action is enforceable’ " ( Executive Plaza, LLC v. Peerless Ins. Co., 22 N.Y.3d 511, 518, 982 N.Y.S.2d 826, 5 N.E.3d 989, quoting John J. Kassner & Co. v. City of New York, 46 N.Y.2d 544, 551, 415 N.Y.S.2d 785, 389 N.E.2d 99 ; see J Constr. Co., LLC v. Westchester Fire Ins. Co., 165 A.D.3d 1076, 1078, 87 N.Y.S.3d 585 ). " ‘[T]he period of time within which an action must be brought ... should be fair and reasonable, in view of the circumstances of each particular case.... The circumstances, not the time, must be the determining factor’ " ( Executive Plaza, LLC v. Peerless Ins. Co., 22 N.Y.3d at 519, 982 N.Y.S.2d 826, 5 N.E.3d 989, quoting Continental Leather Co. v. Liverpool, Brazil & Riv. Plate Steam Nav. Co., 259 N.Y. 621, 622–623, 182 N.E. 207 ; see D & S Restoration, Inc. v. Wenger Constr. Co., Inc., 160 A.D.3d 924, 926, 75 N.Y.S.3d 505 ). "Absent proof that the contract is one of adhesion or the product of overreaching, or that [the] altered period is unreasonably short, the abbreviated period of limitation will be enforced" ( State of Narrow Fabric, Inc. v. UNIFI, Inc., 126 A.D.3d 881, 883, 5 N.Y.S.3d 512 [internal quotation marks omitted]; see John v. State Farm Mut. Auto. Ins. Co., 116 A.D.3d 1010, 1011, 983 N.Y.S.2d 883 ).

Here, the LIRR demonstrated, prima facie, that the time within which to commence this action had expired inasmuch as the plaintiff failed to commence this action within 90 days after May 31, 2011, when construction was indisputably complete (see Piliaskas v. Mountain Val. Indem. Co., 174 A.D.3d 757, 758, 105 N.Y.S.3d 99 ; J Constr. Co., LLC v. Westchester Fire Ins. Co., 165 A.D.3d at 1078, 87 N.Y.S.3d 585 ; Batales v. Friedman, 144 A.D.3d 849, 851, 41 N.Y.S.3d 275 ; City of Yonkers v. 58A JVD Indus., Ltd., 115 A.D.3d 635, 637–638, 981 N.Y.S.2d 736 ).

In opposition, the plaintiff contended that the 90–day contractual period of limitations was never triggered since the LIRR failed to issue a "Certificate of Construction Completion" pursuant to section V–3.3 of the contract. Contrary to the plaintiff's contention, neither the language of section V–3.3, nor any other provision in the contract, supports the conclusion that the contractually fixed limitations period begins to run only upon the issuance of a certificate of construction completion by the LIRR (see Sea Crest Constr. Corp. v. Amwest Sur. Ins. Co., 263 A.D.2d 433, 433–434, 693 N.Y.S.2d 134 ; cf. J.A. Elec., Inc. v. City of New York, 119 A.D.3d 652, 654, 990 N.Y.S.2d 223 ; Highland Mech. Indus. v. Herbert Constr. Co., 216 A.D.2d 161, 162, 628 N.Y.S.2d 655 ). "This interpretation is consistent with the plain meaning of the contract and basic principles of contract construction that an interpretation which renders language in the contract superfluous cannot be supported" ( Batales v. Friedman, 144 A.D.3d at 851, 41 N.Y.S.3d 275 ). The plaintiff's further contention that the shortened limitations period was unenforceable is without merit (see Malik v. Advanced Protection Servs., Inc., 123 A.D.3d 779, 779, 996 N.Y.S.2d 547 ; Hunt v. Raymour & Flanigan, 105 A.D.3d 1005, 1006, 963 N.Y.S.2d 722 ). Moreover, there is no support in the record for the Supreme Court's conclusion that the LIRR waived its right to enforce the contractual limitations period (see Gilbert Frank Corp. v. Federal Ins. Co., 70 N.Y.2d 966, 968, 525 N.Y.S.2d 793, 520 N.E.2d 512 ; Chan v. Counterforce Cent. Alarm Servs. Corp., 73 A.D.3d 1115, 1116, 900 N.Y.S.2d 884 ; Halim v. State Farm Fire & Cas. Co., 31 A.D.3d 710, 711, 818 N.Y.S.2d 476 ; Carle Place Union Free School Dist. v. Bat–Jac Constr., Inc., 28 A.D.3d 596, 598, 813 N.Y.S.2d 748 ).

Accordingly, the Supreme Court should have granted the LIRR's cross motion for summary judgment dismissing the complaint, and should have denied that branch of the plaintiff's motion which was for summary judgment dismissing the LIRR's fourth affirmative defense, alleging that the action was time-barred.

Nevertheless, we agree with the Supreme Court's determination to grant that branch of the plaintiff's motion which was for summary judgment dismissing the LIRR's third counterclaim, which sought to recover liquidated damages pursuant to section V–5.0 of the contract. It is undisputed that there were "concurrent delays" to the project, and that the LIRR agreed to extend "the contract period of performance ... to reflect a revised Contract completion date of May 31, 2011." Contrary to the LIRR's contention, the language of section V–5.0, which was entitled "Liquidated Damages for Contractor Delay," does not support the conclusion that such damages were recoverable under these circumstances (see generally Plato Gen. Constr. Corp./EMCO Tech Constr. Corp., JV, LLC v. Dormitory Auth. of State of N.Y., 89 A.D.3d 819, 826, 932 N.Y.S.2d 504 ). In addition, we agree with the court's determination to grant that branch of the plaintiff's motion which was for summary judgment dismissing the LIRR's fourth counterclaim, seeking to recover damages for unjust enrichment, given that the relationship between the parties was governed by a valid and enforceable contract (see Corsello v. Verizon N.Y., Inc., 18 N.Y.3d 777, 790, 944 N.Y.S.2d 732, 967 N.E.2d 1177 ; Clark–Fitzpatrick, Inc. v. Long Is. R.R. Co., 70 N.Y.2d 382, 388–389, 521 N.Y.S.2d 653, 516 N.E.2d 190 ; D & S Restoration, Inc. v. Wenger Constr. Co., Inc., 160 A.D.3d at 926, 75 N.Y.S.3d 505 ).

The parties' remaining contentions need not be addressed in light of our determination.

BALKIN, J.P., COHEN, BARROS and IANNACCI, JJ., concur.


Summaries of

Stonewall Contracting Corp. v. Long Island R.R.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Aug 12, 2020
186 A.D.3d 640 (N.Y. App. Div. 2020)
Case details for

Stonewall Contracting Corp. v. Long Island R.R.

Case Details

Full title:Stonewall Contracting Corp., respondent, v. Long Island Rail Road Company…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department

Date published: Aug 12, 2020

Citations

186 A.D.3d 640 (N.Y. App. Div. 2020)
129 N.Y.S.3d 433
2020 N.Y. Slip Op. 4505

Citing Cases

Der Velde v. N.Y. Prop. Underwriting Ass'n

question of fact as to whether the statute of limitations is tolled or is otherwise inapplicable, or whether…

Newburgh Commercial Dev. Corp. v. Cappelletti

Moreover, this issue does not fall within the exception to the rule permitting review of pure questions of…