From Casetext: Smarter Legal Research

State v. Lundin

Appellate Division of the Supreme Court of New York, Third Department
Feb 3, 1983
91 A.D.2d 343 (N.Y. App. Div. 1983)

Opinion

February 3, 1983

Appeal from the Supreme Court, Albany County, D. VINCENT CERRITO, J.

Robert Abrams, Attorney-General ( Richard J. Dorsey and William J. Kogan of counsel), for appellant.

Ross Cohen ( Frederick Cohen, Charles Fastenberg and Andrea Popik Taber of counsel), for Penn York Construction Corp., defendant and third-party plaintiff-respondent.

Wilson, Elser, Edelman Dicker ( James L. Fischer of counsel), for Robert L. Thorson and others, respondents.

Berman, Paley, Goldstein Berman ( Alvin Goldstein of counsel), for Northrop Corporation, third-party defendant-respondent. Hesson, Ford, Sherwood Whalen ( Donald T. Ford, Jr., and Daniel A. Whalen of counsel), for S.R. Beltrone, Inc., third-party defendant-respondent.

Altieri, Kushner Miuccio ( Denis B. Frind of counsel), for Peter Bratti Associates, Inc., third-party defendant-respondent.

Paul, Weiss, Rifkind, Wharton Garrison ( Nancy Kilson and Edward N. Costikyan of counsel), for William B. Heller, respondent.

Tunstead Schechter ( Michael S. Torre of counsel), for the Georgia Marble Company, third-party defendant-respondent.


This action arose out of the alleged defective design and construction of the marble curtain wall on the Swan Street Building in the Governor Nelson E. Rockefeller Empire State Plaza in Albany. The State commenced the action, seeking damages for alleged breach of contract and negligence, by service of a summons with notice on the various defendants in July, August and September, 1979. Defendants are the architectural partnership and two individual partners, the general contractor and various insurers who had issued performance bonds in connection with the construction. Several subcontractors were impleaded by defendants. After the State served its complaint, defendants and third-party defendants moved to dismiss upon the ground that the actions were barred by the three-year Statute of Limitations governing negligence actions and the six-year Statute of Limitations governing breach of contract actions. Special Term granted the motions and this appeal ensued.

In support of their motions, defendants and third-party defendants submitted affidavits and documents establishing that most, if not all of the actual work on the Swan Street Building was completed prior to July 31, 1973, which was six years before the first of the defendants was served in this action. For example, the building was dedicated in January, 1972 and by April, 1972 the burden of security had been assumed by the Capitol Police. By June, 1972, the building was 100% occupied by the State and it was described as complete except for minor items. In June of 1972, the general contractor was authorized to cancel its fire insurance policy on the building, and as of July, 1973, the general contractor had not been on the project for some 10 months.

The State, on the other hand, contends that although most of the physical work had been completed by July 31, 1973, a substantial contractual relationship between the State and the general contractor and the State and the architect continued after that date. Indeed, the State contends that this relationship continued until the issuance of the final certificate of payment in July, 1977, which, the State argues, should be the accrual date for its causes of action.

The general rule in contract cases is that "the cause of action accrues and the Statute of Limitations begins to run from the time of the breach" ( Kassner Co. v City of New York, 46 N.Y.2d 544, 550). The rule is somewhat different, however, in construction contract cases involving an owner's claims against an architect arising out of alleged defective construction of buildings. In such cases, the owner's causes of actions "however verbally classified, accrue for purposes of all Statutes of Limitations on completion of construction" ( Sears, Roebuck Co. v Enco Assoc., 43 N.Y.2d 389, 394). The rationale for using as the accrual date the completion of construction, rather than the actual date of the defective construction, appears to lie in the theory that the architect's duty to design a proper building is a continuous one that does not end until the building is completed (see Sosnow v Paul, 43 A.D.2d 978, affd 36 N.Y.2d 780, citing Siegel v Kranis, 29 A.D.2d 477). Given the architect's expertise and the owner's need to rely on that expertise to see that the building is properly constructed, it would be unreasonable to require the owner to resort to litigation while construction is in progress and curative steps could be taken to remedy the defect ( County of Broome v Vincent J. Smith, Inc., 78 Misc.2d 889, 892).

This court has applied the completion of construction accrual date to construction contract cases involving engineers who design the construction project ( State of New York v Ehasz, 80 A.D.2d 671). Although general contractors are not professionals like architects and engineers, the contractual duty assumed by them continues until completion of construction, and the owners rely on their expertise to see that the project is completed according to the plans. We conclude, therefore, that completion of construction is also the accrual date for an owner's claims of defective construction against a general contractor ( Excelsior 57th Corp. v 303 Assoc., NYLJ, Sept. 7, 1978, p 6, col 2, affd 73 A.D.2d 849, mot for lv to app den 49 N.Y.2d 705).

The point in time when construction was completed, of course, depends upon the facts and circumstances of each case. The courts have generally looked to the completion of the actual physical work (see, e.g., Sears, Roebuck Co. v Enco Assoc., 43 N.Y.2d 389, supra; State of New York v Ehasz, 80 A.D.2d 671, supra; Sosnow v Paul, 43 A.D.2d 978, affd 36 N.Y.2d 780, supra), but in Board of Educ. v Celotex Corp. ( 88 A.D.2d 713, affd 58 N.Y.2d 684), an action by the owner against the architect, this court used the issuance of the final certificate of payment as the completion date, despite the fact that the physical work was finished some three years earlier. Since the contract therein "required the architect to conduct inspections to determine the dates of substantial and final completion and to issue a final certificate of payment", we concluded that "the final certificate [of payment] was not merely a ministerial act but represented a substantial contractual right of plaintiff owner and a concommitant contractual responsibility of defendant architect in completing the project" ( supra, at p 714; emphasis added). Here, none of defendants had the contractual responsibility for issuing the final certificate. Rather, that responsibility lay with the State itself. The State's project manager, a third-party defendant, was obligated by its contract with the State to "conduct, in conjunction with the designing architects and engineers, final inspection of all units of construction, preliminary to acceptance, to ensure the conformance of all aspects of the work to contract requirements". The State's issuance of the final certificate of payment was, in our view, nothing more than the State's formal acceptance of an already completed project. Such acceptance served to trigger the running of the contractual guarantees and signified the end of the period for making equitable adjustments in the contract prices. It cannot, however, serve to extend the completion date of the project for those parties whose contractual obligations concerning the construction itself had ended some five years earlier when the physical work was substantially completed and the building was fully occupied by the State.

The State points out that for a substantial period of time after the physical construction work was complete there were ongoing negotiations between the State and its general contractor concerning equitable adjustments to the contract prices based upon such factors as delays and changes in specifications. These negotiations, however, did not relate to the construction itself. Rather, they were concerned solely with the prices to be paid by the State for work that was already completed, and they occurred long after the general contractor had left the work site.

Although the parties' proof does not firmly establish a fixed date for the completion of the actual construction of the building, it does establish that the work was completed and the building occupied by the State before July 31, 1973. Since the State's actions were not commenced until July 31, 1979, more than six years have passed following completion of construction and, therefore, the State's causes of action, whether grounded in negligence or breach of contract, are barred.

The order should be affirmed, without costs.


KANE and WEISS, JJ., concur with CASEY, J.; MAHONEY, P.J., and MIKOLL, J., dissent and vote to reverse in an opinion by MIKOLL, J.

Order affirmed, without costs.


We respectfully dissent.

The holding of this court in Board of Educ. v Celotex Corp. ( 88 A.D.2d 713, affd 58 N.Y.2d 684) is controlling here. Defendants' motions for summary judgment were improperly granted.

Special Term erroneously concluded that the Statute of Limitations in the instant case began to run from the date of physical completion of the work, which it concludes was prior to July 31, 1973. The court disregarded the explicit language of the agreement between the parties. The contract between the State and Foster-Lipkins, the general contractor, provided in section 101 of article 24 that: "Final certificate will not be issued until all the labor and material required under the contract have been furnished and completed, all claims of the contract submitted and disposed of and all accounts for extra work and materials and allowances for omissions have been rendered, considered and, if agreed to, made a part of such certificate."

Section 102 of the same article states: "The final certificate will constitute the acceptance of the work by the State, except as to work thereafter found to be defective. The date of such certificate shall be regarded as the date of acceptance of the work."

The plain meaning of the contract language indicates that the Statute of Limitations did not commence to run until July 12, 1977, the date of the issuance of the final certificate of payment.

The conduct of the parties also supports the conclusion that Foster-Lipkins was involved in an ongoing contractual relationship with the State until May of 1977. If the relationship had been finished as of July 31, 1973, as found by Special Term, Foster-Lipkins would have applied for final payment at that time. Applications for payment were submitted by it on July 31, 1973, May 21, 1974, November 30, 1974, June 30, 1975 and May 9, 1977, totaling $1,000,000. It is clear then that the contractual relationship between the contractor and the State continued until all claims were settled and the final certificate of payment was issued. There was an improper grant of summary judgment to defendant Penn York (formerly Foster-Lipkins), defendant surety companies and third-party defendants.

The cause of action against the architects also did not accrue until the final certificate of payment was issued. It is conceded that they had performed no work with respect to the marble facade after September 1, 1972, but they continued with work on other facets of the Swan Street Building after that date. Their services were not limited to the marble facade but encompassed the entire building. The architects submitted vouchers for supervision services for this building in the period from August 5, 1974 to November 10, 1974, and entered into an agreement for their fifth supervisory architectural services contract for this building on December 9, 1974. Significantly, too, it was their obligation to the State to participate in the final inspection of the building with construction manager Fuller who was responsible for issuing the final certificate of payment. Consequently, the cause of action against the architects did not accrue until the final certificate of payment was issued.

The order should be reversed and defendants' motions denied.


Summaries of

State v. Lundin

Appellate Division of the Supreme Court of New York, Third Department
Feb 3, 1983
91 A.D.2d 343 (N.Y. App. Div. 1983)
Case details for

State v. Lundin

Case Details

Full title:STATE OF NEW YORK, Appellant, v. EARL H. LUNDIN et al., Defendants…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Feb 3, 1983

Citations

91 A.D.2d 343 (N.Y. App. Div. 1983)
459 N.Y.S.2d 904

Citing Cases

Samuel Roberts Noble Foundation, Inc. v. Vick

The completion of the construction is the accrual date for a plaintiff's claim for breach of contract against…

United States Fidelity & Guaranty Co. v. Delmar Development Partners, LLC

Finally, we find that Supreme Court properly denied plaintiff's motion for summary judgment. Notwithstanding…