From Casetext: Smarter Legal Research

SJF Material Handling v. Motor City Scrap

United States District Court, E.D. Michigan, Southern Division
Apr 15, 2009
Case No. 08-14187 (E.D. Mich. Apr. 15, 2009)

Summary

denying motion for leave to amend complaint with respect to claims that were clearly futile, but granting leave to amend with respect to other claims whose merits may be more appropriately challenged in a motion for summary judgment

Summary of this case from Iseman v. Werner

Opinion

Case No. 08-14187.

April 15, 2009


OPINION ORDER


On February 10, 2009, Plaintiff filed a Motion to Amend, wherein it seeks to add two additional defendants and several additional claims. Defendant opposes the Motion to Amend, asserting that the claims Plaintiff seeks to add are futile. The parties have briefed the issues and the Court heard oral argument on April 6, 2009. For the reasons that follow, the Court shall grant the Motion to Amend in part and deny the motion in part. The Court denies Plaintiff's Motion to Amend to the extent that the Court denies leave to file the proposed breach of fiduciary duty claims (proposed Counts VI, XIII and XV) and the proposed civil conspiracy claim (proposed Count XVIII) contained in Plaintiff's proposed Amended Complaint because such claims are futile. Plaintiff's Motion to Amend is GRANTED in all other respects.

BACKGROUND

Plaintiff SJF Material Handling, Inc. ("Plaintiff" or "SJF") filed this action against Defendant Motor City Scrap, Inc. ("Defendant" or "Motor City") on September 29, 2008. Plaintiff's original complaint asserts the following 6 counts: "Breach of Contract" (Count I); "Quantum Meruit" (Count II); "Fraud" (Count III); "Misrepresentation" (Count IV); "Promissory Estoppel" (Count V); and "Damages" (Count VI).

On November 10, 2008, Motor City filed its Answer and Affirmative Defenses. It also asserted the following counterclaims: "Count I — Breach of Contract (Value City)," "Count II — Quantum Meruit (Value City)," "Count III — Slander/Defamation (Cinelli)," "Count IV — Tortious Interference (Cinelli)," "Count V — Breach of Contract (Beacon)," and "Count VI — Tortious Interference (Fairless)."

The Scheduling Order in this matter provides that discovery is to close on July 6, 2009, and motions are to be filed by August 7, 2009.

On February 20, 2009, SJF filed the instant "Motion to Amend." Plaintiff seeks leave to file an amended complaint that would add two individuals as defendants, Jeffrey Scott Seskin ("Seskin") and Gregg Oleshansky ("Oleshansky") and assert additional claims against Motor City.

ANALYSIS

Rule 15(a) of the Federal Rules of Civil Procedure states that leave to amend "shall be freely given when justice so requires." A motion to amend, however, should be denied "if the amendment is brought in bad faith, for dilatory purposes, results in undue delay or prejudice to the opposing party, or would be futile." Crawford v. Roane, 53 F.3d 750, 753 (6th Cir. 1995).

"A proposed amendment is futile if the amendment could not withstand a Rule 12(b)(6) motion to dismiss." Rose v. Hartford Underwriters Insur. Co., 203 F.3d 417, 420 (6th Cir. 2000); see also Thiokol Corp. v. Department of Treasury, State of Michigan, 987 F.2d 376, 382-83 (6th Cir. 1993) ("This Circuit has addressed the issue of `futility' in the context of motions to amend, holding that where a proposed amendment would not survive a motion to dismiss, the court need not permit the amendment."); Matz v. Northwest Airlines, 2008 WL 2064800 (E.D. Mich. 2008).

Here, Motor City opposes SJF's Motion to Amend on the ground that proposed amendments are futile. Thus, the Court needs to determine if the challenged claims could survive a motion to dismiss under FED. R. CIV. P. 12(b)(6). This Court has previously explained that, for purposes of this motion, that means:

"[A] complaint may be dismissed for failure to state a claim upon which relief can be granted. The court must construe the complaint in a light most favorable to the plaintiff, and accept all of [his] factual allegations as true. When an allegation is capable of more than one inference, it must be construed in the plaintiff's favor." Bloch v. Ribar, 156 F.3d 673, 677 (6th Cir. 1998) (citation omitted); see also Fed.R.Civ.P. 12(b)(6). The plaintiff is not required to provide detailed factual allegations, but must provide the grounds of his entitlement to relief by offering more than "labels and conclusions." Bell Atlantic Corporation v. Twombly, ___ U.S. ___, ___ 127 S.Ct. 1955, 1964-1965, 167 L.Ed.2d 929 (2007). A formulaic recitation of the elements of a cause of action is insufficient to state a claim. Id. at 1965. The plaintiff is required to plead enough facts to state a claim to relief that is plausible on its face. Id. at 1974.
Matz, supra, at *2.

A. SJF's Proposed Breach Of Fiduciary Duty Claims:

Motor City contends that the proposed breach of fiduciary duty claims against it and its agents arise entirely out of Motor City's obligations under the written contract with SJF and thus are conclusively barred under the Hart and Economic Loss Doctrines. (Motor City's Br. at 9). In short, Motor City contends the breach of fiduciary duty claims fail because SJF has not alleged any fiduciary duty separate from the contract.

"Under Michigan law, an action for breach of fiduciary duty requires an existing fiduciary relationship." Polydyne, Inc. v. Kirk, 238 F.3d 423, 2000 WL 1888654 (6th Cir. 2000) (citing Portage Aluminum Co. v. Kentwood Nat'l Bank, 106 Mich.App. 290, 294 (1981)). A person in a fiduciary relation to another is under a duty to act for the benefit of the other as to matters within the scope of the relation. Bero Motors v. General Motors Corp., 2001 WL 1167533 (Mich.App. 2001).

A fiduciary duty arises where there is a fiduciary relationship between the parties. Familiar examples are: trustees to beneficiaries, guardians to wards, attorney to clients, and doctors to patients. Portgage Aluminum Co., supra, at 294. Michigan court have been "reluctant to extend the cause of action for breach of fiduciary relationship beyond the traditional context." Bero Motors, supra.

In Bero Motors, where the parties were "experienced for-profit entities in a commercial setting," the court found the plaintiff's "simple allegations of reliance on another" to be insufficient. To the extent that SJF seeks to add a breach of fiduciary claim against Seskin and Oleshanky, the Court finds that SJF's proposed Amended Complaint does not sufficiently allege the existence of a fiduciary relationship between SJF and Seskin/Oleshansky.

In Horizon Painting, Inc. v. Adams, 2007 WL 600686 (Mich.App. 2007), the Michigan Court of Appeals explained that "there is no authority for the proposition that a fiduciary relationship exists between parties to contractual agreements as in this case." To the extent that SJF seeks to assert a breach of fiduciary duty claim against Motor City, the Court finds that the proposed Amended Complaint does not sufficiently allege a fiduciary relationship.

Accordingly, the Court concludes that SJF's proposed fiduciary duty claims (proposed Counts VI, XIII, and XV) are futile.

B. SJF's Proposed Fraud And Misrepresentation Claims:

The original complaint included a fraud claim (Count III of Compl.) and a misrepresentation claim (Count IV of Compl.) against Motor City. Because those claims were included in the original complaint, they have already been asserted in this action and they are not at issue in the pending Motion to Amend. SJF seeks to add, however, additional fraud and misrepresentation claims against Seskin (Counts X and XI of proposed Am. Compl.) and Oleshansky (Count XVII of proposed Am. Compl.).

Motor City contends that any such fraud and misrepresentation claims would be barred by the broad integration clause in the parties' written contract. ( See Resp. Br. at 12-13). In sum, Motor City contends that under Michigan law you cannot have any reasonable reliance on pre-contractual representations when you have a broad integration clause like the one seen in the written contract at issue here.

In response, Plaintiff states that its proposed fraud and misrepresentation claims are not based upon pre-contractual representations. Rather, it contends that the proposed counts are based upon "fraudulent acts that took place after the contract was formed, and are therefore not affected by the integration clause." (Pl.'s Reply at 5) (emphasis added).

Accordingly, the Court concludes that Defendant has not established that the proposed fraud and misrepresentation claims, which are based on post-contractual representations, are barred by the integration clause.

C. SJF's Proposed Civil Conspiracy Claim:

In SJF's proposed Amended Complaint, it seeks to assert a civil conspiracy claim against Seskin and Oleshanksy, alleging that "Defendant Seskin and Defendant Oleshansky engaged in a concerted action to wrongfully and unlawfully deprive SJF of funds that were received as payment for material removed from the Warehouse." ( See Proposed Amended Complaint at 21).

In opposing SJF's Motion to Amend, Motor City challenges this proposed civil conspiracy claim on several grounds, including that it is precluded by the intra-corporate trust doctrine.

At the April 6, 2009 hearing, SJF's counsel conceded that the proposed civil conspiracy claim (proposed Count XVIIII) is futile.

D. Remaining Challenges:

Defendant has asserted additional futility arguments regarding the remaining counts contained in Plaintiff's proposed Amended Complaint. After consideration of those arguments, the Court is not convinced that Defendant has established that the remaining claims would be futile. In arriving at this conclusion, the Court emphasizes that it makes no determination as to the merits of any of these additional claims. The Court further notes that some of the arguments raised by Defendant may be more appropriate in the context of a motion for summary judgment.

CONCLUSION ORDER

Accordingly, the Court DENIES Plaintiff's Motion to Amend to the extent that the Court denies leave to file the proposed breach of fiduciary duty claims (proposed Counts VI, XIII and XV) and the proposed civil conspiracy claim (proposed Count XVIII) contained in Plaintiff's proposed Amended Complaint because such claims are futile. Plaintiff's Motion to Amend is GRANTED in all other respects.

Plaintiff is ORDERED to file its Amended Complaint within seven (7) days of the entry of this order.

IT IS SO ORDERED.


Summaries of

SJF Material Handling v. Motor City Scrap

United States District Court, E.D. Michigan, Southern Division
Apr 15, 2009
Case No. 08-14187 (E.D. Mich. Apr. 15, 2009)

denying motion for leave to amend complaint with respect to claims that were clearly futile, but granting leave to amend with respect to other claims whose merits may be more appropriately challenged in a motion for summary judgment

Summary of this case from Iseman v. Werner
Case details for

SJF Material Handling v. Motor City Scrap

Case Details

Full title:SJF Material Handling, Incorporated, Plaintiff, v. Motor City Scrap…

Court:United States District Court, E.D. Michigan, Southern Division

Date published: Apr 15, 2009

Citations

Case No. 08-14187 (E.D. Mich. Apr. 15, 2009)

Citing Cases

Iseman v. Werner

As reviewing whether the alleged deceptive acts by Defendant involve the marketing or sale of a security…