From Casetext: Smarter Legal Research

Seaward Constr. Co. v. City of Rochester

Supreme Court of New Hampshire Strafford
Mar 10, 1978
383 A.2d 707 (N.H. 1978)

Summary

In Seaward Construction Co. v. City of Rochester, 118 N.H. 128, 383 A.2d 707 (1978), the city was obliged to pay for construction work only to the extent it received federal funds for that purpose, and the contract expressed no duty on the city's part to seek the funds, id. at 129, 383 A.2d at 708.

Summary of this case from Centronics Corp. v. Genicom Corp.

Opinion

No. 7868

Decided March 10, 1978

1. Contracts — Implied Covenants — Good Faith In every agreement there exists an implied covenant that each of parties will act in good faith and deal fairly with the other.

2. Contracts — Implied Covenants — Good Faith Mere fact that defendant in action on contract to install certain sewer pipe was a city did not release it from implied obligation to act in good faith and deal fairly with plaintiff.

3. Contracts — Implied Covenants — Good Faith In action on contract to install certain sewer pipe for city, where company was to be paid $19 per linear foot of pipe installed at depth of zero to ten feet and $60 per linear foot of pipe laid at depth of ten to eighteen feet, and dispute arose over depth pipe was installed and price to be paid, and contract provided that money due under contract was subject to receipt of said money from Department of Housing and Urban Development (HUD), city had burden of showing that it complied with implied obligation of good faith by making good-faith effort to obtain additional funds from HUD to pay whatever was found to be due company installing pipe, and regardless of city's contention denying any obligation to seek additional funds because it denied there was anything due company even if funds were available.

Shaines, Madrigan McEachern, of Portsmouth (Gregory D. Robbins orally), for the plaintiff.

William B. Cullimore, of Farmington, by brief and orally for the defendant.


This is an action on a contract to install certain sewer pipe for the city of Rochester. Defendant's motion to dismiss was granted by the trial court and plaintiff's exception was transferred by Loughlin, J.

On or about January 22, 1974, the plaintiff and the defendant entered into an agreement for the installation of certain sewer pipe. Plaintiff was to be paid $19 per linear foot of pipe installed at a depth of zero to ten feet and $60 per linear foot of pipe laid at a depth of ten to eighteen feet. The written agreement between the parties contained the following provisions:

2. All monies due under the Contract are subject to the receipt of said monies by said Rochester Housing Authority from the Federal Housing and Urban Development Agency (HUD) and turned over to said City of Rochester for payment of the construction of said facilities.

* * * *

5. The City of Rochester shall be under no legal obligation to advance any of its own funds for said construction.

6. Payment to said Seaward Construction Company, Inc. is contingent upon receipt of funds by the Rochester Housing Authority and turning same over to the City of Rochester for payment to said Seaward Construction Company.

During the course of construction Seaward periodically made claims for what ultimately amounted to over 1,000 feet of pipe at a depth of ten to eighteen feet. The city eventually claimed that 920 feet of this pipe was less than ten feet deep. Seaward made formal claim for this disputed footage, but the city refused to pay. Plaintiff instituted this suit in assumpsit based on the agreement to pay $60 per foot. It alleged that the city had paid only at the rate of $19 per foot and claimed a balance due of $37,638. The defendant moved to dismiss on the basis of the above-quoted provisions of the agreement alleging that it had no funds from the Rochester Housing Authority or HUD for payment of the claim. The defendant has not sought or pursued the availability of further funds because of the underlying dispute as to the depth of the pipe. After hearing, this motion was granted, and plaintiff's exception was transferred.

[1, 2] In every agreement there exists an implied covenant that each of the parties will act in good faith and deal fairly with the other. Griswold v. Heat Corp., 108 N.H. 119, 124, 229 A.2d 183, 187 (1967). The mere fact that the defendant is a city does not release it from this implied obligation to act in good faith and deal fairly with the plaintiff. See Leary v. City of Manchester, 90 N.H. 256, 257, 6 A.2d 760, 761 (1939).

The express language in the agreement is perfectly clear that the city will not be required to expend its own funds for payment of the installation of the sewer line, but it is also reasonably clear that the city was under an implied obligation to make a good-faith effort to obtain funds from HUD to pay the plaintiff. Rochester Park, Inc. v. City of Rochester, 38 Misc.2d 714, 238 N.Y.S.2d 822, 826-27 (1963), aff'd, 19 A.D.2d 776, 241 N.Y.S.2d 763 (1963); Public Market Co. v. Portland, 171 Or. 522, 588-89, 130 P.2d 624, 649-50 (1942).

The defendant's motion to dismiss raises an affirmative defense based on the above-quoted language of the contract. See Armstrong v. Johnson Motor Lines, Inc., 12 Md. App. 492, 496, 280 A.2d 24, 29 (1971). To be entitled to the benefit of the express provisions of the contract, the defendant has the burden of showing that it has also complied with the implied obligation by making a good-faith effort to obtain additional funds from HUD to pay whatever is found to be due plaintiff. See Buzzell v. Snell, 25 N.H. 474, 481 (1852).

The city denies any obligation to seek additional funds because it denies there is anything due plaintiff even if funds were available. However, this places the plaintiff in all impossible position. If the plaintiff is not afforded an opportunity to prove that its pipe measurement is correct, then, under the defendant's contention, there is no obligation on the part of the city to make the good-faith effort to obtain the funds. Plaintiff should be given the opportunity to prove its case on the depth of the pipe in order to bring the city's implied obligation into play.

We have no way of knowing what the length or complexity of a trial of this factual issue regarding the depth of pipe would be. If the trial would be protracted, it would seem a waste of time and effort to try the issue if no funds would be available from HUD. The city may elect to make a good-faith effort to determine whether such funds would be available if the plaintiff should prevail, and if the trial court is satisfied that no funds are available it may give judgment for the defendant. Otherwise the plaintiff should be permitted to try the issue of the depth of the pipe, and if it prevails, the city will be liable unless it proves that, given a reasonable time, it has made a good-faith effort to obtain the funds from HUD and it has been unsuccessful.

Remanded.

LAMPRON, J., did not sit.


Summaries of

Seaward Constr. Co. v. City of Rochester

Supreme Court of New Hampshire Strafford
Mar 10, 1978
383 A.2d 707 (N.H. 1978)

In Seaward Construction Co. v. City of Rochester, 118 N.H. 128, 383 A.2d 707 (1978), the city was obliged to pay for construction work only to the extent it received federal funds for that purpose, and the contract expressed no duty on the city's part to seek the funds, id. at 129, 383 A.2d at 708.

Summary of this case from Centronics Corp. v. Genicom Corp.
Case details for

Seaward Constr. Co. v. City of Rochester

Case Details

Full title:SEAWARD CONSTRUCTION COMPANY, INC. v. CITY OF ROCHESTER

Court:Supreme Court of New Hampshire Strafford

Date published: Mar 10, 1978

Citations

383 A.2d 707 (N.H. 1978)
383 A.2d 707

Citing Cases

Centronics Corp. v. Genicom Corp.

The discretion to refrain from acting, articulated in the Griswold contract, had been left unexpressed in the…

Irwin Marine, Inc. v. Blizzard, Inc.

The master noted that the city had failed to notify Irwin Marine that its bid had been rejected and that new…