From Casetext: Smarter Legal Research

Schwartz v. Knight

Supreme Court of California
Dec 28, 1887
74 Cal. 432 (Cal. 1887)

Summary

In Schwartz v. Knight, 74 Cal. 432, [16 P. 235], reaffirmed in Marchant v. Hayes, 120 Cal. 137, [52 P. 154], it is said: "The code does not mean that the building, if, as in this case, it was intended to be a dwelling-house, must be completed in all respects as contermplated by the plans and specifications, or even that it shall have become habitable as a dwelling.

Summary of this case from California Portland Cement Company v. Wentworth Hotel Company, H. S. Mckee, Assignee in Insolvency Thereof, and A. T. Hagan Company, Pacific Coast Planing Mill Company

Opinion

         Appeal from a judgment of the Superior Court of San Luis Obispo County.

         COUNSEL:

         F. Adams, and V. A. Gregg, for Appellants.

          J. M. Wilcoxon, for Respondents.


         JUDGES: In Bank. McKinstry, J. McFarland, J., Temple, J., Searls, C. J., Paterson, J., Sharpstein, J., and Thornton, J., concurred.

         OPINION

          McKINSTRY, Judge

         The appeal is from the judgment by the defendants, who insist it should be reversed because it appears from the findings that plaintiffs did not file their notice of lien until one hundred days after they had furnished materials for the house. But the plaintiffs were not "original" contractors, within the meaning of section 1187 of the Code of Civil Procedure. (Sparks v. Butte County etc ., 55 Cal. 392.) As they were not original contractors, the law required them to file their lien within thirty days after the completion of the buildings (Code Civ. Proc., sec. 1187), and the filing of a lien prior to its completion was premature. (Perry v. Brainard, 8 West Coast Rep. 429; Roylance v. San Luis Hotel Co., ante, p. 273.)

         The code does not mean that the building, if, as in this case, it was intended to be a dwelling-house, must be completed in all respects as contemplated by the plans and specifications, or even that it shall have become habitable as a dwelling. Ordinarily the lien cannot be filed until a building is so completed. But when it is made to appear that it was the original purpose of the owner to erect and build it in part only, or that the owner, having proceeded to erect the house in part, abandoned his design of finishing it, the building should be held to be completed, within the meaning of section 1187, from the time it was so built in part. The purpose of the owner may be inferred from his acts or omissions, but the ultimate fact to be determined is his original or substituted purpose to leave the building unfinished. The owner of property on which a building has been commenced cannot deprive the material-man or laborer of his lien by refusing or omitting to finish the building.

         In Harmon v. Ashmead , 68 Cal. 322, the complaint alleged that at the date of the commencement of the action the building had not been completed; that the defendant did not intend to complete it; and that he had notified the plaintiffs to that effect. The lien was decreed. The question is but incidentally referred to, but was included in the judgment recognizing and enforcing the lien of a material-man, in Germania v. Wagner , 61 Cal. 349. In that case, the building was not completed, "but work thereon ceased July 16, 1881, and has never been resumed."

         But to uphold a lien filed before the actual completion of a building, it should distinctly appear that the original purpose was to build it in part, or that the original purpose to finish it was abandoned.

         The present action was commenced June 20, 1884. The appeal is on the findings alone, and the court below found that the work of the carpenters employed in the construction of the building was completed in the month of January, 1884, but that the said building "was not then and is not now completed." There is no direct finding that between the last of January and the 20th of June no work was done on the house by masons, plasterers, plumbers, painters, or others than carpenters; [16 P. 236] nor any finding that work of some kind was not actually progressing when this suit was brought. The finding should be at least of facts from which it might be clearly inferred that it never was the intention of the defendant to complete the house, or that she had abandoned such intention.

         After finding that the carpenters completed their work in January, and the dwelling-house was not completed at the commencement of the action, the court found "that neither of the plaintiffs at the time of furnishing the materials knew that it was not the intention of the defendant Sarah to complete said building and leave it in an unfinished state."

         This is not a finding that such was her intention, or that the completion was abandoned by her.

         Judgment reversed, and cause remanded for a new trial.


Summaries of

Schwartz v. Knight

Supreme Court of California
Dec 28, 1887
74 Cal. 432 (Cal. 1887)

In Schwartz v. Knight, 74 Cal. 432, [16 P. 235], reaffirmed in Marchant v. Hayes, 120 Cal. 137, [52 P. 154], it is said: "The code does not mean that the building, if, as in this case, it was intended to be a dwelling-house, must be completed in all respects as contermplated by the plans and specifications, or even that it shall have become habitable as a dwelling.

Summary of this case from California Portland Cement Company v. Wentworth Hotel Company, H. S. Mckee, Assignee in Insolvency Thereof, and A. T. Hagan Company, Pacific Coast Planing Mill Company
Case details for

Schwartz v. Knight

Case Details

Full title:LOUIS SCHWARTZ et al., Respondents, v. WILLIAM KNIGHT et al., Appellants

Court:Supreme Court of California

Date published: Dec 28, 1887

Citations

74 Cal. 432 (Cal. 1887)
16 P. 235

Citing Cases

Pacific Mut. Life Ins. Co. v. Fisher

All these claimants of liens under the mechanics' lien law rank as either materialmen or laborers. (Sparks v.…

La Grill v. Mallard

         The plaintiffs were not "original contractors" within the meaning of section 1187 of the Code of…