From Casetext: Smarter Legal Research

Santa Clara Valley Water Dist. v. CH2M Hill, Inc.

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA SAN JOSE DIVISION
Jul 24, 2020
Case No. 19-CV-08295-LHK (N.D. Cal. Jul. 24, 2020)

Opinion

Case No. 19-CV-08295-LHK

07-24-2020

SANTA CLARA VALLEY WATER DISTRICT, Plaintiff, v. CH2M HILL, INC. and CDM SMITH INC., Defendants.


ORDER GRANTING MOTION FOR LEAVE TO AMEND AND REMAND

Re: Dkt. No. 26

Plaintiff Santa Clara Valley Water District ("SCVWD") brings the instant lawsuit against CH2M Hill, Inc. ("CH2M"), CDM Smith Inc. ("CDM"), and Does 1-60 for negligence, breach of contract, and breach of implied covenant of good faith and fair dealing with respect to the design and construction of SCVWD's Rinconada Water Treatment Plant. Before the Court is SCVWD's motion for leave to amend and remand. SCVWD moves to amend the Complaint to join a non-diverse party, which would destroy diversity jurisdiction and require that the Court remand the case to state court. Having considered the submissions of the parties, the relevant law, and the record in this case, the Court GRANTS SCVWD's motion for leave to amend and remand.

I. BACKGROUND

A. Factual Background

SCVWD is a public agency that operates as a State of California Special District with jurisdiction in Santa Clara County. ECF No. 1-1 ("Compl.") ¶ 1. CH2M is a Florida-based professional engineering corporation with a principal place of business in Colorado. Id. ¶ 2. CDM is a Massachusetts-based professional engineering corporation with a principal place of business in Massachusetts. Id. ¶¶ 3-4.

SCVWD's Rinconada Water Treatment Plant ("RWTP") takes in raw water and processes it to produce potable water. Id. ¶ 10. A key component of a water treatment facility is the Residuals Management System ("RMS"), which removes solids in the water treated by the facility. Id. ¶ 12. In 2008, SCVWD's Board of Directors approved a Residuals Management Project to upgrade and modernize SCVWD's RMS as part of a broader Reliability Improvement Project. Id. ¶ 13.

SCVWD contracted with CH2M in June 2009 to provide planning phase services for the Residuals Management Project, including a Conceptual Engineering Report to determine the quantity of solids that the re-designed RMS should handle and a Final Basis of Design Report, providing thirty percent of the design plans for the re-modeled RMS. Id. ¶ 14. CH2M issued the Conceptual Engineering Report in May 2010 and the Final Basis of Design Report in May 2011. Id. ¶¶ 15, 21-22. SCVWD separately contracted with CDM in December 2010 to serve as a consultant and to provide additional planning, conceptual engineering, and preliminary design of the Reliability Improvement Project for the RWTP. Id. ¶ 23. SCVWD then amended the contract with CDM to include preparation of the final design and construction administration services. Id. CDM relied on CH2M's Conceptual Engineering Report in its own design work. Id. ¶ 35.

SCVWD alleges that the work performed by both CH2M and CDM contained significant errors that resulted in an ineffective RMS, which was too small to manage current, much less future, demands. Id. ¶ 36. Proposed Defendant TJC and Associates, Inc. ("TJC") is a subconsultant of CDM. ECF No. 26 ("Mot. to Remand") at 7. SCVWD alleges that TJC played an integral role in designing the defective RMS. Id. Specifically, SCVWD alleges that TJC's negligent design of the flow-regulation system cut the operational capacity of a core RMS component, the gravity thickeners, in half. Id. Further, SCVWD alleges that TJC's erroneous design of the polymer-dosing system directly damaged another core RMS component, the conveyors, and potentially harmed the centrifuges. Id. SCVWD likewise alleges that TJC "specified improper equipment" for the RMS' sludge-mixing tank, "failed to design for sufficient operator-access to the conveyors," ignored safety protocols in its design of fire alarms, and misaligned a maintenance monorail. Id. at 7-8.

B. Procedural History

On November 1, 2019, SCVWD filed a Complaint against CH2M, CDM, and Does 1-60 in the Superior Court of California for the County of Santa Clara. Compl. In the Complaint, SCVWD alleges that the negligence of CH2M and CDM resulted in serious design defects that produced an ineffective RMS that was unable to filter water at the capacity required by the RWTP. Id. ¶ 36. Based on these allegations, SCVWD asserted five causes of action: (1) negligence against CH2M, CDM, and Does 1-60; (2) breach of contract against CH2M and Does 21-40; (3) breach of implied covenant of good faith and fair dealing against CH2M and Does 21-40; (4) breach of contract against CDM and Does 41-60; and (5) breach of implied covenant and good faith and fair dealing against CDM and Does 21-40. Id. ¶¶ 38-59.

On December 18, 2019, the day before responsive pleadings were due in state court, CDM requested a two-week extension to file a responsive pleading, which SCVWD granted. ECF No. 41-1 ("Supp. Johnson Decl.") ¶ 7 and Ex. 3. The next day, on December 19, 2019, CH2M filed a timely notice of removal. See ECF No. 1. CH2M asserted that federal diversity jurisdiction was proper under 28 U.S.C. § 1332 because CH2M and SCVWD are citizens of different states, none of the Defendants is a citizen of California, and SCVWD alleged $2,000,000 of damages already suffered with possible damages assessed at $25,000,000. See ECF No. 1 ("Notice of Removal") at 2; see also Compl. ¶ 37.

On December 26, 2019, CH2M then filed an Answer and Cross-Complaint against CDM. See ECF No. 7. On January 2, 2020, notwithstanding the notice of removal, CDM filed an Answer and Cross-Complaint against CH2M in the state court action. Supp. Johnson Decl. ¶ 9. On January 13, 2020, in light of CDM's filing in the state court action, SCVWD inquired as to whether or not CDM had consented to CH2M's removal. Id. ¶ 10; Ex. 2. CDM confirmed that CDM had in fact provided prior consent to removal. Id. On January 17, 2020, SCVWD then notified CDM and CH2M of the need to add TJC as a non-diverse defendant because of TJC's indispensable role in the design defects at the RWTP. Id. Shortly thereafter, SCVWD consulted with an independent professional engineer to "understand the precise technical nature and scope of TJC's design work on the RMS . . . and how that work interrelated with the design work performed by CDM and CH2M." Mot. to Remand at 9.

On March 6, 2020, CDM filed Answers, a Cross-Complaint against CH2M, and a Counter-Complaint against SCVWD in the instant case. See ECF No. 21. On March 19, 2020, SCVWD then filed the instant motion for leave to amend and remand. Mot. to Remand. SCVWD's proposed amended complaint adds the non-diverse party TJC as a Defendant. See id. SCVWD alleges three additional causes of action against TJC: (1) professional negligence; (2) negligent misrepresentation; and (3) third-party beneficiary breach of contract. Id. at 15-21. On March 30, 2020, the parties stipulated to an extension of briefing to permit CDM and CH2M to respond by June 1, 2020 and to permit SCVWD to reply by June 15, 2020. ECF No. 30.

On June 1, 2020, CDM opposed SCVWD's motion for leave to amend and remand. ECF No. 34 ("CDM Opp'n"). CH2M also opposed SCVWD's motion to amend and remand on June 1, 2020. ECF No. 36 ("CH2M Opp'n"). Both CDM and CH2M contend that TJC is not a necessary party and that SCVWD seeks to join TJC merely to defeat diversity jurisdiction. CDM Opp'n at 6; CH2M Opp'n at 2. On June 15, 2020, SCVWD filed a reply in support of its motion for leave to amend and remand. ECF No. 41 ("Reply").

II. LEGAL STANDARD

District courts in the Ninth Circuit scrutinize the "specific situation of a plaintiff attempting to use a Rule 15(a) amendment 'as a matter of course' to destroy diversity jurisdiction by adding claims against a non-diverse defendant [. . .] under § 1447(e)." McGrath v. Home Depot USA, Inc., 298 F.R.D. 601, 607 (S.D. Cal. 2014); see Clinco v. Roberts, 41 F. Supp. 2d 1080, 1088 (C.D. Cal. 1999) (explaining that "a diversity-destroying amendment must be considered under the standard set by § 1447(e)"). Pursuant to 28 U.S.C. § 1447(e), "[i]f after removal the plaintiff seeks to join additional defendants whose joinder would destroy subject matter jurisdiction, the court may deny joinder, or permit joinder and remand the action to the State court." 28 U.S.C. § 1447(e). In these circumstances, "[t]he decision regarding joinder of a diversity destroying-defendant is left to the discretion of the district court." Newcombe v. Adolf Coors Co., 157 F.3d 686, 691 (9th Cir. 1998).

A court's decision to deny joinder of a diversity-destroying defendant after removal is subject to an abuse of discretion review. Id. A court's decision to remand under § 1447 for lack of subject matter jurisdiction, however, is "not reviewable on appeal or otherwise." 28 U.S.C. § 1447(d); see, e.g., DeMartini v. DeMartini, -- F.3d --, 2020 WL 3636345, at *4-6 (9th Cir. July 6, 2020) (explaining that decisions to permit joinder of diversity-destroying parties and remand under 28 U.S.C. § 1447(e) are unreviewable because of lack of subject matter jurisdiction).

III. DISCUSSION

SCVWD moves to amend the complaint to join TJC as a non-diverse Defendant, which would destroy federal diversity jurisdiction and require that the Court remand the instant case to state court. In deciding whether to allow joinder of a diversity-destroying defendant, district courts consider a number of factors, including: (1) whether the proposed defendant is a necessary party; (2) whether any statute of limitations would preclude an original action against the proposed defendant in state court; (3) whether the plaintiff has unjustifiably delayed in seeking joinder; (4) whether joinder is intended solely to defeat federal jurisdiction; (5) whether the claims against the proposed defendant appear valid; and (6) whether denying joinder would prejudice the plaintiff. E.g., Palestini v. Gen. Dynamics Corp., 193 F.R.D. 654, 658 (S.D. Cal. 2000); Boon v. Allstate Ins. Co., 229 F. Supp. 2d 1016 (C.D. Cal. 2002). "Any of the factors might prove decisive, and none is an absolutely necessary condition for joinder." Yang v. Swissport USA, Inc., No. C 09-03823 SI, 2010 WL 2680800, at *3 (N.D. Cal. July 6, 2010). The Court therefore considers each of these factors in turn.

A. First Factor - The Necessary Party Standard

The first factor requires courts to determine whether a proposed defendant is a "necessary party." SCVWD argues that the first factor weighs in favor of amendment because TJC is intimately involved in the alleged design defects and therefore joinder of TJC will preserve judicial resources. By contrast, CH2M and CDM argue that the first factor weighs against amendment because SCVWD can obtain complete relief without joinder of TJC. The Court agrees with SCVWD.

The Ninth Circuit has described necessary parties "as those '[p]ersons having an interest in the controversy, and who ought to be made parties, in order that the court may act on that rule which requires it to decide on, and finally determine the entire controversy, and do complete justice, by adjusting all the rights involved in it.'" CP Nat. Corp. v. Bonneville Power Admin., 928 F.2d 905, 912 (9th Cir. 1991) (quoting Shields v. Barrow, 58 U.S. (17 How.) 130, 139 (1855)). Thus, in evaluating the first factor, courts "look at least for a high degree of involvement by the defendant in the occurrences that gave rise to the plaintiff's cause of action." Boon, 229 F. Supp. 2d at 1022.

The first factor may support joinder either when complete relief cannot be afforded without the additional defendant or when the proposed defendant is more than tangentially related to the case. See IBC Aviation Servs. Inc. v. Compania Mexicana de Aviacion, S.A. de C.V., 125 F. Supp. 2d 1008, 1012 (N.D. Cal. 2000) ("Courts disallow joinder of non-diverse defendants where those defendants are only tangentially related to the cause of action or would not prevent complete relief."). Courts also look to whether permitting joinder would avoid "separate and redundant actions," inconsistent results, and the waste of judicial resources. IBC Aviation, 25 F. Supp. 2d at 1011-12 (citing CP Nat'l Corp. v. Bonneville Power Admin., 928 F.2d 905, 910 (9th Cir. 1991)). For instance, courts consider the likelihood that the existing defendants will place blame on the proposed defendant at trial. See Boling Air Media v. Panalpina Inc., 2019 WL 3798492 (E.D. Cal. Aug. 13, 2019) (finding the Rule 19 standard for joinder met when "it is possible that [the existing defendants] will blame the [proposed defendants] at trial, and will point to their empty chairs at trial if they are not joined as defendants").

In the instant case, SCVWD alleges that TJC was intimately involved in the RMS defects at the center of the instant case. Mot. to Remand at 9-14. Specifically, SCVWD alleges that TJC was responsible for electrical, structural, and implementation design elements of the RMS and produced approximately thirty percent of the designs used in the construction of the RMS. Id. at 9-10. SCVWD attributes specific design defects to TJC, including a defect that impacts regulation of the flow from the gravity thickeners to the sludge-mixing tank and another defect that impacts regulation of the frequency and dosages of polymers required to effectively separate the water. Id. at 12-13. Neither CDM nor CH2M disputes TJC's alleged intimate involvement in the defects that give rise to SCVWD's causes of action. Instead, the Defendants solely argue that SCVWD may receive complete relief without joinder of TJC. See CDM Opp'n at 5; CH2M Opp'n at 6.

For instance, CH2M relies on Newcombe v. Adolf Coors Co. to argue that when only money damages are sought and a plaintiff may receive complete relief from existing defendants, the Ninth Circuit does not find a non-diverse defendant to be a necessary party. Id. (citing Newcombe, 157 F.3d at 691). The instant case, however, is distinguishable from Newcombe. In Newcombe, the defendants (the publisher, the advertiser, and the advertised beer company) and the proposed defendant (the artist) all performed distinct roles in the production of the unconsented-to depiction of the plaintiff in Sports Illustrated. Newcombe, 157 F.3d at 689-91. In the instant case, SCVWD alleges that TJC's role, unlike that of the artist in Newcombe, is so intertwined with those of CDM and CH2M that it would be prejudicial to adjudicate relative responsibility without TJC present. Reply at 10.

Furthermore, SCVWD argues that without joinder of TJC, SCVWD will be forced to pursue an action against TJC in state court, which will result in "almost wholly duplicative" proceedings that invite inconsistent outcomes. See Mot. to Remand at 24. CDM also hints that CMD will pursue such a course of action, as CDM states that "[i]t is clear that CDM is the party that would be entitled to relief from TJC, not SCVWD . . . ." CDM Opp'n. at 6. When disallowing the amendment would require a redundant action, courts have found that the first factor weighs in favor of amendment regardless of whether or not full relief may be obtained without joinder of the non-diverse defendant. See, e.g., Carillo v. FCA US LLC, No. 20-CV-0138 W (LL), 2020 WL 2570122, at *3 (S.D. Cal. May 21, 2020) (focusing on the proposed defendant's level of involvement and the likelihood of redundant actions under the first factor). Moreover, in the instant case, even if no future claims against TJC arise, the Court finds it likely that CDM will point to TJC as a source of blame at trial. Thus, under these circumstances and for the reasons discussed above, the Court finds that the first factor weighs in favor of amendment.

B. Second Factor - Statute of Limitations

Under the second factor, courts consider whether "a statute of limitations would affect the plaintiff's ability to bring a separate suit against a new party." Clinco, 41 F. Supp. 2d at 1083. Here, SCVWD concedes that its claims against TJC are not time barred. Mot. to Remand at 25; Reply at 10. Thus, this factor does not weigh in favor of permitting amendment. Boon, 229 F. Supp. 2d at 1023.

C. Third Factor - Timeliness of Amendment

Under the third factor, courts consider whether "the amendment was attempted in a timely fashion." Clinco, 41 F. Supp. 2d at 1083. SCVWD argues that the third factor weighs in favor of amendment because SCVWD has adequately explained the reason that SCVWD did not previously seek joinder of TJC and because no significant activity has yet occurred in the case. CH2M and CDM argue that the third factor weighs against amendment because SCVWD's amendment is untimely. The Court agrees with SCVWD.

In assessing the third factor, Courts determine whether a plaintiff attempted amendment in a reasonable length of time following filing of the complaint. Id. Courts also consider whether a plaintiff has provided an explanation for any delay in amending the complaint. See, e.g., Boone, 229 F. Supp. 2d at 1023 (noting that plaintiffs "acted timely in filing the amendment especially in light of the substitution of new counsel that occurred during the early stages of the litigation"). Lastly, courts consider whether significant activity occurred in federal court before the motion for amendment was filed. See Yang, 2010 WL 2680800, at *4 (weighing factor three in favor of amendment after nine months where "no dispositive motions have been filed, and the discovery completed thus far will be relevant whether the case is litigated in this court or state court"); Graunstadt v. USS-POSCO Industries, No. C 10-03225 SI, 2010 WL 3910145, at *3 (N.D. Cal. Oct. 5, 2010) ("For a motion to amend to be granted, it is important that the litigation has not yet made considerable progress.") (citing Righetti v. Shell Oil Co., 711 F. Supp. 531, 534 (N.D. Cal. 1989)).

In the instant case, SCVWD filed the instant motion approximately five months after the Complaint and three months after removal. District courts within the Ninth Circuit have found amendment timely when a plaintiff files an amended complaint "less than three months after [plaintiffs] filed their original complaint in Superior Court, and less than a month after removal." Boon, 229 F. Supp. 2d at 1023. CH2M relies on this "standard" and argues that SCVWD's motion to amend and remand is untimely. CH2M Opp'n at 8. However, district courts within the Ninth Circuit have also found motions to amend timely when filed up to nine months after the initial complaint. See, e.g., Negrete v. Meadowbrook Meat Co., No. ED CV 11-1861, 2012 WL 254039, at *5 (C.D. Cal. Jan. 25, 2012) (five-and-a-half months after original filing); Watson v. Ford Motor Co., No. 18-CV-00928-SI, 2018 WL 3869563, at *2, 4 (N.D. Cal. Aug. 15, 2018) (six months after original filing); Yang, 2010 WL 2680800, at *4 (nine months after original filing). Indeed, CDM itself acknowledges that the timing in the instant case "seems to fall roughly in the middle of the spectrum of what various courts have deemed timely." CDM Opp'n at 7. Moreover, SCVWD explains the delay in seeking amendment by pointing to the need to consult with a professional engineer to determine whether TJC's design work was defective, a process which took "considerable time." Mot. for Remand 26.

As of March 19, 2020, the date SCVWD filed the instant motion for leave to amend and remand, the parties had not exchanged initial disclosures, and the initial case management conference had not yet occurred. Reply at 11. Furthermore, CDM did not appear in this federal action until two weeks prior on March 6, 2020. Mot. to Remand at 9. As of June 10, 2020, the date of the parties' joint case management statement, "no discovery ha[d] been undertaken to date." ECF No. 37 at 10. Under these circumstances, in light of the short length of time following the filing of the Complaint, SCVWD's need to obtain expert analysis, and the lack of activity in the instant case, the Court finds that the third factor weighs in favor of amendment.

D. Fourth Factor - Motive for Joinder

Under the fourth factor, courts consider "whether joinder is intended solely to defeat federal jurisdiction." IBC Aviation, 125 F. Supp. 2d at 1011. SCVWD argues that the fourth factor weighs in favor of amendment here because SCVWD has significantly modified the proposed amended complaint to add three new causes of action against TJC, and SCVWD has adequately explained why SCVWD waited to assert claims against TJC. CH2M and CDM argue that factor four weighs against amendment because SCVWD's motive for joinder is to defeat diversity. The Court agrees with CH2M and CDM, but only somewhat.

The Ninth Circuit has instructed that, because "motive in seeking joinder" is a relevant factor in determining whether to grant amendment, "a trial court should look with particular care at such motive in removal cases, when the presence of a new defendant will defeat the court's diversity jurisdiction . . . ." Desert Empire Bank v. Ins. Co. of N. Am., 623 F.2d 1371, 1376 (9th Cir. 1980).

First, in evaluating motive, courts have considered whether the plaintiff was "aware of the removal" when the plaintiff amended its complaint. Clinco, 41 F. Supp. 2d at 1083. Second, "courts have inferred an improper motive where the plaintiff's proposed amended complaint contains only minor or insignificant changes to the original complaint." Forward-Rossi v. Jaguar Land Rover N. Am., LLC, No. 2:16-CV-00949-CAS, 2016 WL 3396925, at *4 (C.D. Cal. June 13, 2016); see San Jose Neurospine v. Cigna Health and Life Ins. Co., No. 16-CV-05061-LHK, 2016 WL 7242139, at *10 (N.D. Cal. Dec. 15, 2016) (weighing the fourth factor against amendment when "[p]laintiff's FAC alleges all of the same facts as [p]laintiff's state court Complaint [... and] asserts the same eight causes of action . . . ."). Third, courts evaluating a plaintiff's motive for amendment have considered whether a plaintiff has provided an explanation for why the plaintiff waited to assert claims against the non-diverse defendant. See Chan v. Bucephalus Alt. Energy Grp., LLC, 2009 WL 1108744, at *5 (N.D. Cal. Apr. 24, 2009) (finding a proper motive for joinder where the plaintiff "amended her Complaint only after discovering that [the non-diverse defendant] was no longer associated with [the diverse defendant]"). Importantly, even when the circumstances suggest that one of the plaintiff's motives is to defeat jurisdiction, factor four does not necessarily weigh against amendment when "it is not readily apparent that it is the sole motivation, particularly [when] there is a seemingly valid claim against [the proposed defendant]." Sandhu v. Volvo Cars of N. Am., LLC, No. 16-CV-04987-BLF, 2017 WL 403495, at *3 (N.D. Cal. Jan. 31, 2017) (weighing factor four somewhat against amendment in light of the circumstances).

In the instant case, SCVWD was undoubtedly "aware of the removal" at the time SCVWD requested amendment because CH2M filed a notice of removal on December 19, 2019, and SCVWD filed the instant motion for leave to amend and remand on March 19, 2020. Clinco, 41 F. Supp. 2d at 1083. The circumstances of the case thus suggest that one of SCVWD's motives is to defeat jurisdiction.

SCVWD, however, seeks to bring three new causes of action against TJC and has added approximately ten pages to its proposed amended complaint in support of these allegations. See generally Mot. to Remand at 10-21. These detailed allegations comprise more than "minor or insignificant changes" to the Complaint. Forward-Rossi, 2016 WL 3396925, at *4.

As noted, SCVWD has also explained that it waited to assert claims against TJC because it was uncertain of TJC's role in the design element defects of the RMS. Mot. to Remand at 9. In fact, in the Complaint that SCVWD filed in California Superior Court on November 1, 2019, SCVWD indicated that SCVWD was evaluating the performance of various subconsultants, including TJC. Id. Specifically, SCVWD noted that "[t]he role of these subconsultants, if any, in bringing about the events complained of herein has not yet been determined [. . . and SCVWD] will substitute one or both of these subconsultants for Doe Defendants should discovery reveal that either or both played a role in causing [SCVWD's] damages." Compl. ¶ 26. SCVWD explains that it then hired an independent professional engineer to assess the work of TJC on the RMS to "understand the precise technical nature and scope of TJC's design work on the RMS and how that work interrelated with the design work performed by CDM and CH2M." ECF No. 26-1 ("Johnson Decl.") ¶ 11.

In light of the detailed claims SCVWD seeks to allege against TJC and the fact that SCVWD indicated in its Complaint filed in California Superior Court on November 1, 2019 that it was considering its potential claims against TJC, SCVWD's motive only weighs slightly against amendment.

E. Fifth Factor - Strength of Claims Against TJC

Under the fifth factor, courts consider "whether a new claim sought to be added seems to have merit." Clinco, 41 F. Supp. 2d at 1083. SCVWD argues that the fifth factor weighs in favor of amendment because SCVWD alleges three valid causes of action against TJC in the proposed amended complaint. CH2M and CDM argue that the fifth factor weighs against amendment because SCVWD's claims against TJC are invalid. The Court agrees with SCVWD.

"The existence of a facially legitimate claim against the putative defendant weighs in favor of permitting joinder under § 1447(e)." Taylor v. Honeywell Corp., No. 09-CV-4947-SBA, 2010 WL 1881459, at *3 (N.D. Cal. May 10, 2010) (citing Righetti, 711 F. Supp. at 534-35). Thus, the Court only need determine whether the claims SCVWD seeks to assert seem valid. See, e.g., Sandhu, 2017 WL 403495, at *3 (noting that a court need only determine whether claim asserted against proposed diversity-destroying defendant "seems valid"). In making that assessment, the court uses a less rigorous standard than that used in a motion to dismiss. See, e.g., Freeman v. Cardinal Health Pharmacy Servs., LLC, No. 2:14-CV-01994-JAM, 2015 WL 2006183, at *3 (E.D. Cal. May 1, 2015) ("[U]nder section 1447(e), the Court need only determine whether the claim 'seems' valid.").

In the proposed amended complaint, SCVWD alleges claims of professional negligence, negligent misrepresentation, and third-party beneficiary breach of contract against TJC. Mot. to Remand at 15-21. The Court addresses each of SCVWD's claims in turn.

1. Professional Negligence

In the proposed amended complaint, SCVWD seemingly alleges the necessary elements of professional negligence because SCVWD alleges: (1) that a relationship giving rise to a duty of care existed between SCVWD and TJC; (2) that TJC breached that duty; and (3) that the breach was a proximate cause of SCVWD's claimed damages. Id. at 15-17. SCVWD relies on Beacon Residential Community Assn. v. Skidmore, Owings & Merrill LLP, 59 Cal. 4th 568 (2014), to allege that TJC owed a duty of care to SCVWD notwithstanding the absence of contractual privity between SCVWD and TJC. Id. CDM and CH2M both argue that SCVWD's reliance on Beacon is misguided because the holding of Beacon was "narrowly tailored . . . to allow residential homeowners to bring a negligence claim against architects [under the Right to Repair Act]." CDM Opp'n at 8; see CH2M Opp'n at 11 (arguing that SCVWD's "reliance on Beacon is fundamentally flawed, because the duties and damages established in Beacon . . . are only available to residential homeowners, as it is based on the California Right to Repair Act"). SCVWD, however, contends that the scope of Beacon is not limited to the Right to Repair Act and cites numerous cases in which district courts in the Ninth Circuit have relied on Beacon to find the existence of a duty of care without contractual privity in non-residential contexts. Reply at 16-17. The Court agrees with SCVWD's reasoning. See United States for Use & Benefit of Bonita Pipeline, Inc. v. Balfour Beatty Constr. LLC, No. 3:16-CV-00983-H-BGS, 2016 WL 10079157, at *1, *4 (S.D. Cal. Sept. 9, 2016) (hanger replacement at Camp Pendleton); Apex Directional Drilling, LLC v. SHN Consulting Engineers & Geologists, Inc., 119 F. Supp. 3d 1117, 1125-26 (N.D. Cal. 2015) (municipal sewage construction project).

Moreover, in the instant case, SCVWD alleges that TJC served as the engineer in "responsible charge" of thirty percent of the designs used to build the RMS. Mot. to Remand at 16-17. Hence, TJC allegedly served a "primary role" in the design of the RMS. See Balfour, 2016 WL 10079157, at *3 (noting that duty of care for professional negligence claim may exist when defendant played a "primary role" in transaction intended to affect plaintiff and when that primary role is closely connected to plaintiff's injury). Thus, the Court finds that the proposed professional negligence claim seems to be valid by the standard that courts use to assess factor five under § 1447(e).

2. Negligent Misrepresentation

CDM argues that SCVWD does not adequately plead negligent misrepresentation because SCVWD "fails to provide any specific, supporting facts that show TJC acted in a deceitful or fraudulent manner." CDM Opp'n at 9. Similarly, CH2M argues that SCVWD's claim fails because SCVWD does not meet the heightened pleading standard of Rule 9(b). CH2M Opp'n at 12.

These arguments are unpersuasive. As SCVWD contends, the tort of negligent misrepresentation "does not require intent to defraud but only the assertion, as a fact, of that which is not true, by one who has no reasonable ground for believing it to be true." Reply at 18 (quoting Conroy v. Regents of Univ. of Cal., 45 Cal. 4th 1244, 1255 (2009)). SCVWD appears to make sufficiently detailed allegations against TJC regarding its role in designing the RMS, the defects in those designs, and the harm those defects caused. Johnson Decl. ¶¶ 31-37. Moreover, SCVWD correctly notes that it is unclear whether the heightened pleading standard of Rule 9(b) applies to SCVWD's proposed negligent misrepresentation claim because "Ninth Circuit law is unsettled regarding whether California negligent misrepresentation claims must satisfy Rule 9(b)'s requirements." Apex Directional Drilling, LLC v. SHN Consulting Engineers & Geologists, Inc., 119 F. Supp. 3d 1117, 1128 (N.D. Cal. 2015); see also Howard v. First Horizon Home Loan Corp., No. 12-CV-05735-JST, 2013 WL 6174920, at *5 (N.D. Cal. Nov. 25, 2013) ("[T]he Court concludes that to allege a negligent misrepresentation claim, Plaintiff must satisfy the requirements of Rule 8, but does not need to satisfy the heightened pleading requirements of Rule 9(b).") .

Thus, the Court finds that the proposed negligent misrepresentation claim seems to be valid by the standard that courts use to assess factor five under § 1447(e).

3. Third-Party Beneficiary Breach of Contract

Both CDM and CH2M argue that SCVWD's claim of third-party breach of contract is invalid because the contract between CDM and SCVWD makes CDM responsible for the work of subconsultants like TJC. CH2M Opp'n at 13; CDM Opp'n at 10. SCVWD, however, argues that the only contract that the Court should consider under a third-party beneficiary breach of contract theory is the contract between CDM and TJC, not that between CDM and SCVWD. Reply at 19.

The Supreme Court of California has outlined three elements that a party must meet in order to bring a third-party beneficiary breach of contract claim. Goonewardene v. ADP, LLC, 6 Cal. 5th 817, 821 (2019). The plaintiff must establish "(1) that it is likely to benefit from the contract, but also (2) that a motivating purpose of the contracting parties is to provide a benefit to the third party, and further (3) that permitting the third party to bring its own breach of contract action against a contracting party is consistent with the objectives of the contract and the reasonable expectations of the contracting parties." Id.

CH2M argues that because the contract between SCVWD and CDM holds CDM responsible for the work of CDM's subconsultants, it would be unreasonable for TJC to be held directly liable to SCVWD. CH2M Opp'n at 13. Although the contract between SCVWD and CDM may be a relevant consideration under the third factor outlined by the Supreme Court of California, the key contract is the one between CDM and TJC, which CDM has not provided. See Goonewardene, 6 Cal. 5th at 821 ("As explained, under California's third party beneficiary doctrine, a third party—that is, an individual or entity that is not a party to a contract—may bring a breach of contract action against a party to a contract . . . ."); Reply at 19. Without visibility into the contract between CDM and TJC, the Court cannot say that permitting SCVWD to bring a breach of contract action directly against TJC is inconsistent with the reasonable expectations of CDM and TJC. The language of the contract between CDM and TJC would shed light on the parties' reasonable expectations but, again, CDM has not provided the contract. See, e.g., The Ratcliff Architects v. Vanir Constr. Mgmt., Inc., 88 Cal. App. 4th 595, 599 (2001) (finding the contractual language in the contract between a contractor and its subcontractors "critical" to determine whether the plaintiff is a third party beneficiary to the contract); Faulkner, USA, Inc. v. Durrant Grp., Inc., No. CV-11-08086-PHX-NVW, 2013 WL 11834262, at *4 (D. Ariz. May 30, 2013) (holding that the plaintiff is not a third party beneficiary because the contractual language between the defendant and the defendant's subcontractors "expressly disclaims any intent to benefit any third parties").

Thus, the Court cannot say that SCVWD's proposed third-party beneficiary breach of contract claim against TJC seems invalid. In sum, in the instant case, SCVWD seeks to allege three seemingly valid claims against TJC. Accordingly, under these circumstances, the Court finds that the fifth factor weighs in favor of amendment.

F. Sixth Factor - Prejudice to Plaintiff

Finally, under the sixth factor, courts consider whether a plaintiff will "suffer undue prejudice if the Court chooses not to exercise its discretion to allow joinder." Boon, 229 F. Supp. 2d at 1025. In the instant case, it appears that SCVWD will suffer prejudice if the Court does not allow SCVWD to file the amended complaint. Refusal to allow the amendment would require SCVWD to either litigate in two forums or to forgo asserting claims against TJC. IBC, 125 F. Supp. 2d at 1013. On the other hand, discovery has either still not yet begun or is in the early stages. ECF No. 37 at 10 (noting that as of June 10, 2020 joint case management statement, "[n]o discovery ha[d] been undertaken to date"); see also, e.g., Watson, 2018 WL 3869563, at *5 ("Further, amendment will not prejudice a defendant when discovery has not begun."). Thus, Defendants will suffer either no prejudice or minimal prejudice. Accordingly, under these circumstances, and for the reasons discussed above, the Court finds that the sixth factor weighs in favor of amendment.

Balancing the above factors as a whole, the Court will exercise its discretion and permit amendment and joinder of TJC. The joinder of TJC destroys diversity jurisdiction and divests this Court of the remaining basis of subject matter jurisdiction. Accordingly, this case must be remanded to state court.

IV. CONCLUSION

For the foregoing reasons, the Court GRANTS the motion for leave to amend. In light of the amendment, the Court determines that it lacks subject matter jurisdiction over the instant case and REMANDS the instant case to California Superior Court for the County of Santa Clara. The Clerk shall close the file.

IT IS SO ORDERED.

Dated: July 24, 2020

/s/_________

LUCY H. KOH

United States District Judge


Summaries of

Santa Clara Valley Water Dist. v. CH2M Hill, Inc.

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA SAN JOSE DIVISION
Jul 24, 2020
Case No. 19-CV-08295-LHK (N.D. Cal. Jul. 24, 2020)
Case details for

Santa Clara Valley Water Dist. v. CH2M Hill, Inc.

Case Details

Full title:SANTA CLARA VALLEY WATER DISTRICT, Plaintiff, v. CH2M HILL, INC. and CDM…

Court:UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA SAN JOSE DIVISION

Date published: Jul 24, 2020

Citations

Case No. 19-CV-08295-LHK (N.D. Cal. Jul. 24, 2020)

Citing Cases

Villarroel v. Staples, Inc.

” Santa Clara Valley Water Dist. v. CH2M Hill, Inc., No. 19-cv-08295-LHK, 2020 WL 4252677, at *3 (N.D.…

Quesada v. Atrium Hosp.

The second factor considers whether "a statute of limitations would affect the plaintiffs ability to bring a…