From Casetext: Smarter Legal Research

Rayner v. R. J. Jones Sons

Court of Appeal of Louisiana, Third Circuit
Feb 15, 1966
182 So. 2d 353 (La. Ct. App. 1966)

Opinion

No. 1562.

November 30, 1965. On Rehearing January 18, 1966. Rehearing Denied February 15, 1966.

APPEAL FROM NINTH JUDICIAL DISTRICT COURT, PARISH OF RAPIDES, WALTER M. HUNTER, J.

Polk Foote, by William P. Polk, Alexandria, for plaintiff-appellant.

Stafford Pitts, by John L. Pitts, Edwin O. Ware, Alexandria, for defendant-appellees.

Before TATE, FRUGÉ and HOOD, JJ.

Before TATE, FRUGÉ, SAVOY and HOOD, JJ.



During the year 1962 the City of Alexandria entered into a contract with R. J. Jones Sons, a commercial partnership, for the construction of a new city hall in Alexandria. The city hall was to be constructed with its front facing Third Street and in the rear by Main Street, on the south side by Murray Street, and on the north side by DeSoto Street.

Subsequent to this contract, defendant Jones entered into subcontracts with various parties for the performance of various phases of the construction. Among these contracts was one with Central Plumbing and Heating for the construction of plumbing and drainage. Another subcontract was with the plaintiff, Elmer Rayner, doing business as Central Electric, for the electrical work, including the installation of certain electrical transformers.

Prior to November 1, 1963, these electrical transformers were installed in a special vault constructed for them at the corner of Main and DeSoto Streets. The roof of this electrical vault or room was the outside plaza floor which encircles three-quarters of the building. Prior to the installation of the permanent floor of the plaza and roof of the electrical room, Jones constructed a temporary waterproof roof, leaving in said roof openings to accommodate the drainage system to be installed by the defendant, Central Plumbing. In order to prevent water from entering the electrical room through the opening left to accommodate the drain, the defendant Jones sealed off this drain opening by mopping the area with hot tar, placing felt up to the pipe protruding through the hole, and then covering the hole with a can or bucket and sealing that with plastic cement.

On November 1, 1963, it rained. Sometime prior to this the bucket or can had been removed in an unexplained manner and the ran water was permitted to enter the drain hole. As a result of this the water fell on the transformers in the vault and three of the transformers shorted out. This resulted in their complete destruction and the filing of this suit.

After hearing all the witnesses and the evidence, the trial court concluded that the plaintiff had not carried the burden of proof and dismissed the suit.

Plaintiff has perfected this appeal, alleging the following errors:

1. In holding that plaintiff had the obligation of protecting his property after installation, under the terms of the building contract.

2. In holding that the doctrine of res ipsa loquitur was inapplicable.

3. In holding that the general contractor did not have the obligation of protecting the subcontractor's property from damage.

4. In holding that there was no proof of negligence on the part of defendant Jones and defendant Central Plumbing.

The record contains the specifications for the building of the Alexandria City Hall and the liabilities and duties of the various subcontractors to the principal contractor, Jones. In the section of the specifications dealing with the electrical work to be done, it is stated:

"C. Protection of Equipment and Materials. The contractor shall continuously maintain adequate protection of all his work from damage and shall protect the Owner's property from injury arising in connection with his contract. He shall make good any such damage, injury, or loss. At completion of work the fixtures, materials and equipment shall be thoroughly cleaned and delivered in condition satisfactory to the Architect."

Although the language of this section is not perfectly clear, a careful reading leads to the conclusion that the electrical contractor had a duty to protect his work until the total completion of his contract. The duty did not cease as each segment was completed but only when the total work of the electrical contractor on this particular building was completed and delivered. This was a contractual obligation assumed by the plaintiff that renders him liable if his equipment was destroyed.

Generally, in order to apply the doctrine of res ipsa loquitur, the instrumentality allegedly causing the accident must be at the time of the accident in the exclusive possession or control of the defendant. The record clearly shows that the plaintiff knew of the drainage hole in the ceiling of the transformer room and accepted as sufficient the measures taken by Jones with respect to waterproofing the drain. Since he had the contractual obligation to insure that his equipment would not be damaged and was fully aware of the consequence if water drained on the transformers, then the waterproofing of the drain and the duty to insure that the transformer room remained waterproof was not under the exclusive possession and control of Jones. Furthermore, res ipsa loquitur is inapplicable when it can be shown that "an inference that the accident was due to a cause other than defendant's negligence could be drawn as reasonably as one that it was due to his negligence." Gauthier v. Liberty Mutual Insurance Co., La. App., 3 Cir., 179 So.2d 437; Pilie v. National Food Stores, 245 La. 276, 158 So.2d 162, 165.

The fact that the can or bucket over the drain was not in place when the water came in is unquestionable, but who caused the removal of this can is what must be proven by the plaintiff if he is to carry the burden of proof.

Thus, determining that there is no basis to hold Jones liable for the damage to the transformers under the doctrine of res ipsa loquitur, it now becomes the issue whether Jones is liable for some negligence on the part of the subcontractor, Central Plumbing.

The plans and specifications for the building contract clearly disclose that the plumbing contractor had no obligation to the plaintiff with respect to sealing the drain or keeping it sealed and waterproofed during construction. The doctrine of res ipsa is clearly inapplicable to this defendant, and the only way to hold Central Plumbing liable would be predicated on the fact that Central Plumbing negligently removed the bucket and thereby occasioned the damage to the transformers.

The record reveals that the day before the accident two employees of Central Plumbing had worked on some of the drains. The testimony of both these men is to the effect that they did not work on the drains on the DeSoto Street side of the building, not having finished preparing the drains on the Murray Street side for the laying of the finished precast concrete blocks. No witnesses were brought forward placing these two men near the DeSoto Street side or by the drain over the transformer room. Both of these men denied working on the DeSoto Street side and denied removing the waterproofing can.

Singer, Jones' superintendent, testified that after the accident he observed that some concrete had been chiseled out since the drain was sealed by him. He also observed that there were some concrete chippings on the transformer housing. Another witness testified as to the concrete chippings on the transformer housing, but no one other than Singer observed or testified as to the concrete being chiseled around the drain. The trial court concluded that the chipping on the transformer housings came to rest when the "thimble" form was knocked out before the waterproofing of the drain.

The trial court concluded that although the employees of Central Plumbing could have been the ones who removed the waterproofing can, the plaintiff had not sustained the burden of proving this. We see no error in this finding.

Plaintiff had the contractual responsibility to see to it that his equipment was protected. At the time the drain was waterproofed by Jones, the plaintiff accepted and approved the manner by which it was done.

Since plaintiff had the obligation of protecting his equipment until the completion of the job, it was his responsibility of seeing that the can remained intact and in place to insure that no water came into the transformer room. This he failed to do, so he must now accept the responsibility and loss.

Having studied the record carefully, we find no difficulty in reaching the same conclusion as did the trial court. Plaintiff has signally failed to support his allegations of negligence by proof of probable weight adequate to award him judgment. For these reasons the judgment appealed from is affirmed at plaintiff's cost.

Affirmed.

On Rehearing.


The plaintiff-appellant's application for rehearing was granted because by it our attention was directed for the first time to a relevant contractual provision which we had previously overlooked.

The plaintiff Rayner sues to recover for substantial damage to electrical features installed by him under a subcontract. He appeals from dismissal of his suit.

Pertinently for determination of present issues, the facts show:

The defendant general contractor ("Jones") had entered into a contract to construct a new city hall. Jones subcontracted the electrical work to the plaintiff Rayner. The electrical subcontract included the installation of six transformers. Rayner installed them in a transformer vault constructed by Jones for that purpose.

In the transformer-vault's roof at the time there had been left a roof opening for a drainpipe to be installed later. When the transformers were installed, in order to protect them from rain Jones had prevented leakage through the drain opening by placing a 5-gallon can over the hole sealed with tar, felt, and plastic cement.

For reasons we hold to be unexplained by the evidence in the record, some two months after the transformers covering the drain-hole had been installed, the can was removed by an unknown agency before it happened to rain heavily. As a result three of the transformers were seriously damaged through being short-circuited because of the rainwater falling into their works.

Prior to the application for rehearing, our attention was not directed to Article 51 ("Protecting Site and Buildings") of the General Conditions of the Jones's general contract. This provides that the general contractor must "Provide and maintain suitable coverings in all openings of windows; and padlocked temporary doors at all not otherwise enclosed openings as soon as roof is on and provide and maintain suitable covering for all work liable to damage from any cause during the progress of the construction. The [General] Contractor will be responsible for any unnecessary or unwarranted damage done to the building throughout the progress of the work. He will also be responsible for damage to any other features of the site." See Exhibit P-1, GC-13.

Under the terms of this provision, therefore, Jones as general contractor had the general responsibility to provide and maintain a suitable covering for the roof hole in order to prevent the readily foreseeable damage which resulted when the water leaked through the hole into the transformer vault so as to damage the transformers (which had been energized in order for use by Jones in the building operations). The specifications pertaining to the plaintiff Rayner's electrical subcontract specifically provide that the contract's "General Conditions" apply to the electric work subcontracted. Exhibit P-1, Division 45-1.

In our original opinion, on the other hand, we had held that the responsibility to prevent leaks through the roof damaging the transformers was a contractual obligation assumed by the electrical subcontractor. In so holding, we relied upon a quoted clause of the electrical specifications to the effect that the subcontractor "shall continuously maintain adequate protection of all his work from damage * * *." In the absence of other contractual regulation, we then felt that under this particular clause the electrical subcontractor had contractually assumed this responsibility until his entire electrical subcontract was completed, even as to portions completed and being used by the general contractor.

On further reflection, however, and in the light of the above-quoted Article 51 of the General Conditions (not previously called to our attention), we now conclude that the contractual duty of the electrical subcontractor in the present case to "maintain adequate protection" of his work is qualified by such subcontractor's right to rely upon the general contractor's performance of his own contractual obligation to provide and maintain adequate coverings so as to prevent damaging leakage onto work of subcontractors previously installed. In short, in reasonably safeguarding his own work, each subcontractor was entitled to rely reasonably upon adequate performance by the general contractor of his obligation to protect the site and buildings; rather than each subcontractor being separately required to safeguard the site and buildings by each hiring a watchman or each inspecting constantly for roof-leakage to prevent damage in the event that the general contractor defaulted in his own contractual duties in this regard.

Considering the contract as a whole with regard to the respective safeguarding responsibilities of the general contractor and electrical subcontractor as set forth by the two clauses, we are convinced that the plaintiff Rayner did not violate his obligation to provide "adequate protection" for the transformers previously installed by him, and that in our original opinion we were in error in concluding otherwise. Under the terms of the general contract, the general contractor Jones had the express duty to maintain suitable covering for all work liable to be damaged by the failure to provide such. Since Jones had instructed the plaintiff subcontractor to install the transformers under the roofing and at the place situated, the latter could reasonably assume that the general contractor would comply with its contractual duty to provide and maintain a suitable covering to protect the transformers from damage of the nature involved herein.

There is no question but that the failure to maintain adequate covering over the drainpipe-hole in the roof was the cause of the substantial damage sustained by the plaintiff's transformers situated beneath the roof-opening. It was the defendant Jones's contractual duty to provide and maintain adequate covering for this hole, not that of the plaintiff Rayner (at least in the absence of reasonable knowledge that further precautions on his part were necessary to protect his own work, which is not shown here).

Upon proof that the defendant Jones's failure to maintain adequate covering as required by the contract was the cause of the plaintiff's damage, the plaintiff has in our opinion sufficiently proved his right to recover for damages caused by the defendant's failure to perform his contractual duty; there being no preponderant exculpatory proof that such failure resulted from some cause which legally excuses the defendant for the default. See Mathews v. Priest, La. App. 2 Cir., 165 So. 535 and Sanders v. Monroe Sand Gravel Co., 2 Cir., 7 La. App. 254. Since the defendant contractor's default in performance of his contractual obligations was proved, the burden shifted to the contractor to prove there was legal excuse for it, which burden was not met since the evidence fails preponderantly to prove any cause of the removal of the covering over the drain-hole. "The general rule that the burden of proof rests on the party having the affirmative of the issue is applicable to actions on contracts, and the usual test employed to determine on which side the burden of proof lies is to ascertain which party would be entitled to a verdict if no evidence were offered on either side of the issue." 17A C.J.S. Contracts § 578.

Somewhat similarly, in the absence of a contractual agreement otherwise, the general rule is that a subcontractor who contracts to contribute only a part of the work and materials for a particular structure, may recover for the work he has performed and the equipment he has installed if his work is destroyed before entire completion by the general contractor, unless the negligence of the subcontractor or his employees contributed to the loss. Bethea v. Savarese, La. App. 4 Cir., 159 So.2d 368; Ottawa Plumbing, etc., Inc. v. Moore, 190 Kan. 201, 372 P.2d 1011 (1962); Vilbig Brothers, Inc. v. C. H. Leavell Co., Tex. Civ.App., 319 S.W.2d 731 (1958); Annotation, Building Contract — Destruction, 53 A.L.R. 103; 13 Am.Jur.2d "Building, etc. Contracts" Section 67; 17A C.J.S. Contracts § 466(2)b.

The plaintiff additionally sued another subcontractor, Central Plumbing, on allegations that Central Plumbing's employees were responsible for the negligent or wrongful removal of the bucket protecting the transformer-vault from leakage. We find no reason to change the conclusion reached in our original opinion that the plaintiff has not preponderantly proved his allegations in this regard. We find no error in the trial court's dismissal of the suit as against this defendant.

The right is reserved to all parties to apply for further rehearing. See Uniform Rules of the Courts of Appeal (rev. 1963), Rule XI, Section 5.

The parties hereto have stipulated the damages sustained by plaintiff-appellant to be $5,436.81. For the reasons above assigned, the judgment of the District Court is affirmed insofar as it dismissed the plaintiff's suit insofar as against the Central Plumbing and Heating Company, but it is reversed insofar as the judgment dismissed the claim against R. J. Jones and Sons; judgment is now rendered in favor of Elmer Rayner and against R. J. Jones Sons, a commercial partnership composed of Robert J. Jones, Robert H. Jones, and James E. Jones, in the full and true sum of Five Thousand Four Hundred and Thirty-Six and 81/100 ($5,436.81) Dollars, together with legal interest thereon from date of judicial demand until paid, together with all costs of these proceedings.

Affirmed in part; reversed and rendered in part.

CULPEPPER, J., recused.


Summaries of

Rayner v. R. J. Jones Sons

Court of Appeal of Louisiana, Third Circuit
Feb 15, 1966
182 So. 2d 353 (La. Ct. App. 1966)
Case details for

Rayner v. R. J. Jones Sons

Case Details

Full title:Elmer RAYNER, Plaintiff-Appellant, v. R. J. JONES SONS et al.…

Court:Court of Appeal of Louisiana, Third Circuit

Date published: Feb 15, 1966

Citations

182 So. 2d 353 (La. Ct. App. 1966)

Citing Cases

Sam's Style Shop v. Cosmos Broadcasting Corp.

The usual test to determine which side has the burden is to ascertain which party would be entitled to a…

Kelchner Excavating v. Zimmerman

Moreover under a contract to do certain part of the work and other contractors are to do part of the work; or…