From Casetext: Smarter Legal Research

Quantum Development Company v. Luckett

Supreme Court of Virginia
Sep 20, 1991
242 Va. 159 (Va. 1991)

Opinion

47220 Record No. 901427

September 20, 1991

Present: Carrico, C.J., compton, Stephenson, Russell, Whiting, Lacy, and Hassell, JJ.

Justice Russell participated in the hearing and decision of this case prior to the effective date of his retirement on July 1, 1991.

The trial court's decree enforcing a mechanic's lien is supported by the evidence and is affirmed.

Creditors' Rights — Mechanic's Liens — Statutory Construction (Code Sec. 43-4) — Contracts

Plaintiff builder agreed with a development company to coordinate and manage construction of a shopping center for a set fee. He was paid in increments as the project progressed and much of the fee was paid as the project neared completion. However, when the job was substantially finished, the builder was removed from the job and he was not paid the balance of his fee. About 90 days later, he filed a memorandum of mechanic's lien. The chancellor decreed enforcement and awarded him a judgment. The defendant contends that the plaintiff failed to prove what labor he furnished within the 150-day period preceding the last day that he worked, as required by Code Sec. 43-4, and appeals.

1. When a trial court has heard evidence ore tenus, its decree is entitled to the same weight as that which attaches to a jury verdict. The trial court's findings of fact are binding unless they are plainly wrong or unsupported by the evidence.

2. On appeal, the evidence and all reasonable inferences it raises are considered in the light most favorable to the party who prevailed at trial.

3. Here, the plaintiff continued to perform his duties under the contract until the near completion of the project. The work was performed under the express contract and for a specified amount of compensation

4. The evidence supports the trial court's finding that plaintiff's claimed lien was for work performed during the 150-day statutory period. Pursuant to the contract, the plaintiff was entitled to the balance of the builders fee.

Appeal from a judgment of the Circuit Court of Prince William County. Hon. Frank A. Hoss, Jr., judge presiding. Affirmed.

Thomas D. Dugan, (Surovell, Jackson, Colten Dugan, on briefs) for appellant.

C. Richard Miserendino for appellee.


The dispositive issue in this appeal is whether the trial court's decree enforcing a mechanic's lien is supported by the evidence.

Robert D. Luckett orally agreed with Quantum Development Company, Inc. (Quantum), to coordinate and manage construction of a small shopping center for Quantum for a builder's fee of $101,500. Luckett's responsibilities included obtaining bids, securing contractors, assigning the contractors to the job, and overseeing their work on a day-to-day basis.

Actual construction of the project began the first week of August 1987. For his services, Luckett was paid in increments of $12,687.50 as the project progressed. By July 1988, the project was 80 percent complete. On July 6, 1988, Luckett was paid a sixth increment of $12,687.50, for a total of $76,125 which represented 75 percent of his builder's fee.

Between July 6 and August 10, 1988, Luckett continued to coordinate and oversee the work of subcontractors. These subcontractors were engaged in paving, replacing cracked curbs and gutters, installing off-site sidewalks, growing and stabilizing grass in certain areas, and replacing dead shrubbery. On August 10, 1988, the project was substantially finished, and on that date, Luckett was removed from the job. However, Luckett was not paid the balance of his builder's fee, $25,375.

On October 31, 1988, Luckett filed a memorandum of mechanic's lien, pursuant to Code Sec. 43-9, for the unpaid balance and, thereafter, brought a chancery suit to enforce his lien. Following a three-day ore tenus hearing, the chancellor decreed enforcement of the mechanic's lien and awarded Luckett a judgment in the amount of $25,375, plus interest at the legal rate from August 10, 1988.

Relying upon Code Sec. 43-4, Quantum contends that Luckett's lien claim must fail. Code Sec. 43-4 states, in pertinent part, that "no memorandum [of mechanic's lien] filed pursuant to [Chapter 1, Title 43 of the Code] shall include sums due for labor or materials furnished more than 150 days prior to the last day on which labor was performed or material furnished to the job preceding the filing of such memorandum."

Quantum contends that Luckett failed to prove what labor he furnished within the 150-day period preceding the last day that he worked. More specifically, Quantum asserts that Luckett "made no effort to distinguish between the nature of the work performed by him during the statutory period and the nature of the work performed by him during the entire year that he was on the job."

[1-2] When a trial court has heard the evidence ore tenus, its decree is entitled to the same weight as that which attaches to a jury verdict. Therefore, the trial court's findings of fact are binding upon us unless they are plainly wrong or unsupported by the evidence. Morris v. Mosby, 227 Va. 517, 522, 317 S.E.2d 493, 497 (1984). Moreover, on appeal, we consider the evidence and all reasonable inferences it raises in the light most favorable to the party who prevailed at trial. Id.

In the present case, the evidence is undisputed. By July 1988, the project was 80 percent complete and Luckett had been paid 75 percent of the agreed fee. Luckett continued to perform his duties under the contract from July 6 until the near completion of the project on August 10, 1988. For example, during the 150-day period, he coordinated and oversaw the subcontractors who topped and striped the paving, completed the masonry work and roofing, finished the drywall, painted the exterior walls, and developed the site. Luckett performed all work under the express contract and for a specified amount of compensation.

Consequently, we hold that the evidence supports the trial court's finding that Luckett's claimed lien was for work performed during the 150-day statutory period. Thus, pursuant to the contract, Luckett was entitled to the balance of the builder's fee, $25,375, which represented payment due for work he performed in completing the project during the remainder of July and part of August 1988. Accordingly, the trial court's judgment will be affirmed.

Affirmed.


Summaries of

Quantum Development Company v. Luckett

Supreme Court of Virginia
Sep 20, 1991
242 Va. 159 (Va. 1991)
Case details for

Quantum Development Company v. Luckett

Case Details

Full title:QUANTUM DEVELOPMENT COMPANY, INC. v. ROBERT D. LUCKETT

Court:Supreme Court of Virginia

Date published: Sep 20, 1991

Citations

242 Va. 159 (Va. 1991)
409 S.E.2d 121

Citing Cases

Wilson v. Com

In Virginia, questions of fact are binding on appeal unless "plainly wrong."Quantum Dev. Co. v. Luckett, 242…

White v. Commonwealth

"In Virginia, questions of fact are binding on appeal unless 'plainly wrong.'" McGee, 25 Va. App. at 198 n.1,…