From Casetext: Smarter Legal Research

Polyfusion Elecs., Inc. v. Promark Elecs., Inc.

Supreme Court, Appellate Division, Fourth Department, New York.
Jul 19, 2013
108 A.D.3d 1186 (N.Y. App. Div. 2013)

Opinion

2013-07-19

POLYFUSION ELECTRONICS, INC., Plaintiff–Respondent–Appellant, v. PROMARK ELECTRONICS, INC. and Robert Gathercole, Defendants–Appellants–Respondents.

Woods Oviatt Gilman, LLP, Rochester (Andrew J. Ryan of Counsel), for Defendants–Appellants–Respondents. Lawrence C. Brown, Cheektowaga, for Plaintiff–Respondent–Appellant.



Woods Oviatt Gilman, LLP, Rochester (Andrew J. Ryan of Counsel), for Defendants–Appellants–Respondents. Lawrence C. Brown, Cheektowaga, for Plaintiff–Respondent–Appellant.
PRESENT: SCUDDER, P.J., PERADOTTO, LINDLEY, SCONIERS, AND WHALEN, JJ.

MEMORANDUM:

Defendants appeal and plaintiff cross-appeals from a judgment entered following a nonjury trial that dismissed the complaint and awarded defendant Promark Electronics, Inc. (Promark) judgment on the fourth counterclaim, for quantum meruit, plus interest. Plaintiff, a contract electronics manufacturer, hired defendants to generate new business orders and, in 2002, plaintiff signed an agreement providing that plaintiff would pay defendants a five-percent commission on new customers resulting from defendants' efforts. The agreement also contained a 30–day termination clause available to both plaintiff and defendants. It is undisputed that plaintiff restructured the commission schedule in 2005 and that defendants accepted the restructured schedule. Due to financial difficulties, plaintiff was deficient in paying various commissions owed to defendants and, in 2008, plaintiff terminated its relationship with defendants. Plaintiff commenced this action seeking commissions it alleges were wrongly paid to defendants, and defendants asserted counterclaims for the unpaid commissions.

We agree with defendants on their appeal that Supreme Court should have awarded Promark judgment on the second counterclaim, breach of contract, rather than on the fourth counterclaim, for quantum meruit. We therefore modify the judgment accordingly. The agreement between the parties was an enforceable unilateral contract ( see Petterson v. Pattberg, 248 N.Y. 86, 88, 161 N.E. 428), and the existence of an enforceable written contract between the parties precludes recovery in quantum meruit ( see Cox v. NAP Constr. Co., Inc., 10 N.Y.3d 592, 607, 861 N.Y.S.2d 238, 891 N.E.2d 271). Plaintiff's contention on its cross appeal that there were additional unwritten requirements that defendants failed to fulfill and thus that defendants were not entitled to judgment in their favor is without merit; parole evidence is not admissible here because there is no ambiguity in the contract between plaintiff and defendants ( see Schron v. Troutman Sanders LLP, 20 N.Y.3d 430, 436, 963 N.Y.S.2d 613, 986 N.E.2d 430;W.W.W. Assoc. v. Giancontieri, 77 N.Y.2d 157, 162, 565 N.Y.S.2d 440, 566 N.E.2d 639).

We further agree with defendants that Promark is entitled to judgment on the first counterclaim, alleging the violation of Labor Law § 191–c. Labor Law § 191–c(1) provides that, “[w]hen a contract between a principal and a sales representative is terminated, all earned commissions shall be paid within five business days after termination or within five business days after they become due in the case of earned commissions not due when the contract is terminated.” Labor Law § 191–c(3) provides that “[a] principal who fails to comply with the provisions of this section concerning timely payment of all earned commissions shall be liable to the sales representative in a civil action for double damages. The prevailing party in any such action shall be entitled to an award of reasonable attorney's fees, court costs, and disbursements.” It is undisputed that plaintiff failed to pay defendants commissions within five business days after they became due, and the record establishes that plaintiff was a “principal” and defendants were “sales representative[s]” for purposes of the statute. We therefore further modify the judgment by awarding Promark damages in the amount of $47,589.15 on the first counterclaim, representing double damages of the amount awarded on the breach of contract claim, and we remit the matter to Supreme Court for a calculation of reasonable attorney's fees ( see Zeman v. Falconer Elecs., Inc., 55 A.D.3d 1240, 1241–1242, 865 N.Y.S.2d 420). We note that the judgment includes an award of costs to defendants.

Finally, we conclude that the court lacked discretion to vary the statutorily-prescribed interest rate of 9% per annum ( seeCPLR 5004). As this Court has previously recognized, interest at the rate of 9% per annum is mandatory for “sum[s] awarded because of a breach of performance of a contract” (CPLR 5001[a]; see Urban v. B.R. Guest, Inc., 45 A.D.3d 1418, 1418, 845 N.Y.S.2d 584). We therefore further modify the judgment accordingly.

It is hereby ORDERED that the judgment so appealed from is unanimously modified on the law by vacating the award of damages under the fourth counterclaim and awarding instead the same amount of damages to defendant Promark Electronics, Inc. under the second counterclaim, awarding damages to defendant Promark Electronics, Inc. on the first counterclaim in the amount of $47,589.15 along with reasonable attorney's fees, and granting defendant Promark Electronics, Inc. interest on the judgment at the rate of 9% rather than 3% per annum, and as modified the judgment is affirmed without costs and the matter is remitted to Supreme Court, Erie County, to determine the amount of reasonable attorney's fees to be awarded pursuant to Labor Law § 191–c(3) and to recalculate the amount of interest to be awarded pursuant to CPLR 5004.


Summaries of

Polyfusion Elecs., Inc. v. Promark Elecs., Inc.

Supreme Court, Appellate Division, Fourth Department, New York.
Jul 19, 2013
108 A.D.3d 1186 (N.Y. App. Div. 2013)
Case details for

Polyfusion Elecs., Inc. v. Promark Elecs., Inc.

Case Details

Full title:POLYFUSION ELECTRONICS, INC., Plaintiff–Respondent–Appellant, v. PROMARK…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Jul 19, 2013

Citations

108 A.D.3d 1186 (N.Y. App. Div. 2013)
108 A.D.3d 1186
2013 N.Y. Slip Op. 5386

Citing Cases

Emerald Equipment Systems, Inc. v. Gearhart Bros. Services, LLC

failed to raise a triable issue of fact in opposition ( see generally Zuckerman v. City of New York, 49…

Schiferle v. Capital Fence Co.

The arbitration agreement—along with its waiver of plaintiff's right to attorney's fees should he prevail on…