From Casetext: Smarter Legal Research

Podhaskie v. Seventh Chelsea Assocs

Appellate Division of the Supreme Court of New York, First Department
Jan 13, 2004
3 A.D.3d 361 (N.Y. App. Div. 2004)

Opinion

1972, 1973.

Decided January 13, 2004.

Judgment, Supreme Court, New York County, entered February 14, 2003, which, upon orders entered May 31, 2002 and on or about February 14, 2003, granted the cross motion of third-party defendant Regional Scaffolding Hoisting Company, Inc. for summary judgment dismissing the third-party complaint seeking contractual indemnity and all cross claims asserted against it, unanimously reversed, on the law, without costs, the motion denied, and the third-party complaint and all cross claims reinstated. Notice of Appeal from order entered on or about February 14, 2003, deemed to be timely notice of appeal from the judgment. Appeal from the aforesaid order of May 31, 2002, unanimously dismissed, without costs.

Paul Edward Svensson, for Plaintiffs.

Frank H. Wright, for Defendants.

Before: Saxe, J.P., Rosenberger, Friedman, Marlow, JJ.


At the outset, we note that CPLR 5520(c) "grants this Court the discretion to deem certain premature or inaccurate notices of appeal as valid and provides us with the specific authority to correct the procedural problem created here by [third-party] plaintiffs' appeal of the order and not the judgment [citations omitted]" ( Robertson v. Greenstein, 308 A.D.2d 381). This case clearly warrants the exercise of our discretion.

In March 1997, third-party plaintiff Seventh Chelsea Associates owned certain premises located at 160 W. 24th Street in Manhattan (the Owner). Third-party plaintiff HRH Construction Corporation (HRH) was employed as construction manager of the Chelsea Expansion Project (the Project), which consisted of adding a multi-story addition to the owner's premises. Plaintiff, a carpenter, was employed by third-party defendant Regional Scaffolding Hoisting Company, Inc. (Regional). On March 4, 1997, plaintiff was installing scaffolding on the project when he fell and was injured. Consequently, plaintiff and his wife commenced an action against the owner and the construction manager (hereinafter appellants) for, inter alia, personal injuries pursuant to the Labor Law. Appellants in turn commenced a third-party action against Regional for contractual indemnification.

Appellants moved for summary judgment dismissing the complaint and for a declaratory judgment that they were entitled to full contractual indemnification from Regional. Regional cross-moved to dismiss the third-party complaint under Workers' Compensation Law § 11. Because plaintiff did not suffer a "grave injury" as specifically defined by the Workers' Compensation law, appellants must show that their claim for indemnification is based upon a provision in a written contract entered into prior to the accident or occurrence. . . ." If not, the claim against Regional would ordinarily be barred ( see Workers' Compensation Law § 11). The motion court, inter alia, granted the cross motion and dismissed the third-party complaint on the ground that appellants did not establish that there was an existing contract providing for indemnity at the time of the accident.

We reverse. Indemnity contracts must be viewed with reference to the purpose of the entire agreement and the surrounding facts and circumstances ( see Szalkowski v. Asbestospray Corp., 259 A.D.2d 867, 869). Although Workers' Compensation Law § 11 refers to an indemnification clause in a written contract "entered into prior to the accident or occurrence," case law supports appellants' contention that such a clause in a contract executed after a plaintiff's accident may nevertheless be applied retroactively where evidence establishes as a matter of law that the agreement pertaining to the contractor's work "was made 'as of' [a pre-accident date], and that the parties intended that it apply as of that date" ( Stabile v. Viener, 291 A.D.2d 395, lv dismissed 98 N.Y.2d 727; cf. Burke v. Fisher Sixth Ave. Co., 287 A.D.2d 410 [since there was nothing about contracts to suggest they were intended to have retroactive effect, summary judgment dismissing the third-party complaint was properly granted]).

In support, appellants submitted, inter alia, Regional's bid proposal to HRH's subcontractor Annex Contracting Company (Annex) to erect the scaffolding for the project, dated December 13, 1996, a certificate of insurance to be issued on January 29, 1997, which named both the owner and the contract manager as additional insureds on its general liability policy, and a formal contract entered into on March 25, 1997 between Regional and Annex. The bid proposal states in relevant part that "[w]ith respect to any hoist, scaffold work furnished hereunder, the Contract Term shall commence on that date that the hoist has been installed, drop tested by Regional and certified for use by the appropriate authority having jurisdiction over the work. As to any other materials or equipment furnished hereunder, Contract Term shall commence on the date that Regional begins installation of the work provided."

Specifically, the contract of March 25, 1997, requires, inter alia, that "[a]ll the Contract Documents shall be read together as complementary and the rights and obligations thereunder shall be deemed cumulative" (§ 4.1[b]). It also provides that "[i]n the event of a conflict between the various contract documents, the following order of priority shall prevail: (a) the riders hereto; Scaffolding Language Rider, [Regional's Bid] proposal dated 12/13/96(b) this agreement (c) Drawings and Specifications . . ." (§ 4.2). This contract also contains an indemnification clause in favor of the owner and construction manager (§ 12.2). The "Scaffold Language" of the contract requires Regional to provide "an executed endorsement to the comprehensive general liability insurance policy . . . evidencing that the Owner, [Annex stricken] [and] HRH Construction . . . are additional insureds" (325, ¶ [d]).

We find that appellants have raised an issue of fact as to whether Regional's bid proposal, together with the certificate of insurance, and the contract entered into on March 25, 1997 between Regional and Annex, demonstrated Regional's intent to indemnify and hold appellants harmless for the entire period of Regional's work on the project and not just from the date the contracts were entered into ( see Quinn v. Fisher Development Inc., 272 A.D.2d 106; Sweeting v. Board of Coop. Educ. Servs., 83 A.D.2d 103, 111-12, lv denied 56 N.Y.2d 503).

In addition, other documents entered into between the parties raise a question of fact as to when Regional intended to commence coverage. When Annex left the job, HRH assumed responsibility for the Annex-Regional Contract, and on October 8, 1997, HRH and Regional entered into an "Interim Indemnity and Hold Harmless Agreement." According to Regional, this interim agreement was entered into to indemnify HRH until a contract was issued. The interim agreement was superceded by a contract between HRH and Regional, entered into as of December 12, 1997 (but executed eight months later), which mirrored the Annex-Regional Contract. This contract also included an indemnification clause in favor of appellants and required Regional to name them as additional insureds on its general liability policy. We note that because this contract appears to have no date limitations regarding the applicability of the indemnity provisions — when the parties could have easily so provided — we find an issue of fact exists as to the parties' intention in this regard. Consequently, because the parties executed the contract after they fully performed it, appellants have raised a question of fact "as to whether the parties intended the contract's indemnification provision to have retroactive effect" ( see Quinn, 272 A.D.2d at 107). Moreover, neither side cites any authority which would dictate a result where, as here, the accident predates both the contract date and the date of its execution, and also where it is a genuine fact issue whether the parties intended coverage retroactively to the date the work began. Clearly, Regional did not enter into these various documents gratuitously. Rather, Regional took these steps anticipating it would sign a contract with appellants that would cover the challenged time period. Therefore, we find issues of fact exist which preclude summary dismissal of the third-party complaint.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

Podhaskie v. Seventh Chelsea Assocs

Appellate Division of the Supreme Court of New York, First Department
Jan 13, 2004
3 A.D.3d 361 (N.Y. App. Div. 2004)
Case details for

Podhaskie v. Seventh Chelsea Assocs

Case Details

Full title:MICHAEL PODHASKIE, ET AL., Plaintiffs, v. SEVENTH CHELSEA ASSOCIATES, ET…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jan 13, 2004

Citations

3 A.D.3d 361 (N.Y. App. Div. 2004)
770 N.Y.S.2d 332

Citing Cases

Barrett v. Magnetic Constr. Grp. Corp.

Indemnity contracts, however, are strictly construed to avoid reading into them duties that the parties did…

Temmel v. 1515 Broadway Associates, L.P.

Therefore, as held by the motion court, in the absence of any explicit agreement by Wiltel prior to the July…