From Casetext: Smarter Legal Research

Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.

Appellate Division of the Supreme Court of New York, First Department
Sep 7, 1995
219 A.D.2d 467 (N.Y. App. Div. 1995)

Summary

finding no general contractor liability for "delay damages allegedly sustained by . . . the electrical subcontractor[] as a result of . . . design and engineering changes ordered . . . after commencement of the project"

Summary of this case from Brian Trematore Plumbing & Heating, Inc. v. Walsh Constr. Grp.

Opinion

September 7, 1995

Appeal from the Supreme Court, New York County (Harold Tompkins, J.).


Defendant Lehr, the general contractor on a renovation contract for premises occupied by defendant Rose Associates, should not have been held liable for delay damages allegedly sustained by plaintiff Phoenix, the electrical subcontractor, as a result of labor disruptions caused by Rose personnel or by design and engineering changes ordered by Rose's architect and engineer after commencement of the project. "[A]bsent a contractual commitment to the contrary, a prime contractor is not responsible for delays that its subcontractor may incur unless those delays are caused by some agency or circumstance under the prime contractor's direction or control" ( Triangle Sheet Metal Works v Merritt Co., 79 N.Y.2d 801, 802). The parties whose actions disrupted the project, and allegedly caused Phoenix to sustain delay damages, were not under Lehr's direction or control.

There was no evidence that the parties, by their actions, considered the contract abandoned ( see, AEB Assocs. Design Group v Tonka Corp., 853 F. Supp. 724, 733 [SD N Y 1994]). Nor did the number or character of the changes "alter or destroy the essential identity of the thing contracted for" ( National Contr. Co. v Hudson Riv. Water Power Co., 192 N.Y. 209, 217). Accordingly, Phoenix was entitled to recover only under its contract, and not for quantum meruit.

The late addition of a claim based upon change order 39 was prejudicial to Lehr and thus should not have been permitted ( see, Gonfiantini v Zino, 184 A.D.2d 368, 369), and in any event the proof submitted in support of this claim was inadequate.

The price reductions on certain change orders purportedly authorized by Phoenix's Mr. Koter were made without actual authority, and apparent authority in Koter to make such reductions had to be traceable to conduct by Phoenix, the burden being on Lehr to prove such conduct as well as reasonable reliance ( Ford v Unity Hosp., 32 N.Y.2d 464, 472-473). The court correctly concluded that Lehr failed to meet this burden in both respects.

Interest on the judgment should run from November 3, 1988 rather than November 3, 1987, and there is no reason why this conceded typographical error should not be corrected on appeal.

Concur — Sullivan, J.P., Rosenberger, Kupferman, Ross and Williams, JJ. [As amended by unpublished order entered Nov. 21, 1995.]


Summaries of

Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.

Appellate Division of the Supreme Court of New York, First Department
Sep 7, 1995
219 A.D.2d 467 (N.Y. App. Div. 1995)

finding no general contractor liability for "delay damages allegedly sustained by . . . the electrical subcontractor[] as a result of . . . design and engineering changes ordered . . . after commencement of the project"

Summary of this case from Brian Trematore Plumbing & Heating, Inc. v. Walsh Constr. Grp.
Case details for

Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.

Case Details

Full title:PHOENIX ELECTRICAL CONTRACTING, INC., Respondent, v. LEHR CONSTRUCTION…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Sep 7, 1995

Citations

219 A.D.2d 467 (N.Y. App. Div. 1995)
631 N.Y.S.2d 146

Citing Cases

Sequa Corp. v. GBJ Corp.

The district court did not consider whether Gelmin had established that his reliance on O'Brien's apparent…

Brian Trematore Plumbing & Heating, Inc. v. Walsh Constr. Grp.

At least one court has suggested that this principle applies to delays caused by design defects. See Phoenix…